Herzfeld Lumber Co. v. Langley

93 So. 378, 18 Ala. App. 485, 1922 Ala. App. LEXIS 167
CourtAlabama Court of Appeals
DecidedMay 9, 1922
Docket5 Div. 363.
StatusPublished
Cited by2 cases

This text of 93 So. 378 (Herzfeld Lumber Co. v. Langley) is published on Counsel Stack Legal Research, covering Alabama Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herzfeld Lumber Co. v. Langley, 93 So. 378, 18 Ala. App. 485, 1922 Ala. App. LEXIS 167 (Ala. Ct. App. 1922).

Opinion

’ SAMFORD, J.

This action is grounded on two contracts for the salé of lumber; counts 1, 2, 3, and 4, claiming under the common counts for the entire purchase price of one carload shipped on defendants’ order to Chattanooga, Tenn., and counts 5 and 6 claiming for a balance due on the purchase price of a carload shipped on defendants’ order to Buffalo, N. Y. For convenience in dealing with the assignments of error, we will follow the order as outlined in appellants’ brief. No brief has come to the hands of the court for appellees.

The Buffalo car was shipped under a written order, dated May 22, 1920; the terms of payment being 80 per cent, cash, less 2 per cent, discount on receipt of invoice and bill of lading; balance, less 2 per cent., on receipt of destination report. Time of shipment was two weeks. The car was shipped as per order, and 80 per cent., less 2 per cent., paid. The defendants refused to pay the balance, claiming that no destination report has been received by them, and that therefore, under the contract of sale, the bal *487 anee is not due. Of course, if the balance of 20 per cent, is not due, the plaintiffs cannot recover for the amount claimed in counts 5 and 6. In order for the plaintiffs to recover, they must prove to the reasonable satisfaction of the jury every material allegation of the complaint — in this case, that the sale was made, a delivery according to the terms of the contract, and a failure on the part of defendants to pay the balance of the purchase price when due. Having introduced the written order for lumber in evidence, and relying upon its terms for a recovery, the plaintiffs were bound to show compliance on their part and a default on the part of defendants. But, when plaintiffs had proven to the satisfaction of the jury the terms of the contract of sale, the delivery within the time, the payment of the 80 per cent, cash, and a reasonable time, in the ordinary course of trade, for the shipment of lumber to have reached its destination, been checked, and a destination report returned to defendants, the burden of plaintiffs was discharged. The clause in the contract, “Balance, less 2 per cent., on receipt of destination report,” means that the 20 per cent, does not become due until defendant has had a reasonable time, in the ordinary course of business, for the lumber to be transported to Buffalo, N. Y., to be checked, inspected, and report returned to defendant. Bradford v. Marbury, 12 Ala. 520, 46 Am. Dec. 264. After such reasonable time has elapsed, the balance of 20 per cent, is due. Bradford v. Marbury, supra.

It was shown without dispute that the car of lumber for Buffalo, N. Y., was shipped in .Tune, 1920, and this suit brought January 15, 1921. Coupled with the judicial knowledge of the court as to geography and common knowledge as to railroad transportation, it was a question for the court to say as to whether the defendants had had a reasonable time in which to get a “destination report,” in the absence of proof tending to prove that such time between the shipment and the bringing of this suit was reasonable, 15 R. C. L. 1120, § 49; Alford v. Creagh, 7 Ala. App. 358, 62 South. 254; Cotton v. Cotton, 75 Ala. 345; American Oak Ex. Co. v. Ryan, 104 Ala. 267, 15 South. 807; Harris v. Free, 6 Ala. App. 113, 60 South. 423. The fact that defendants had written plaintiffs from time to time that no destination report had been received, or as to whether defendants ever received such report, or the letters written by defendants to Elias & Bro., to Buffalo, demanding the report, can have no bearing on this case. It was the duty of defendants to have had the report within a reasonable time, and, failing to do so, the balance of 20 per cent, became due and payable. There are cases where the reasonableness of the time of performance is a question for the jury, but not where the facts are undisputed. Watt v. Sheppard, 2 Ala. 425; Drake v. Goree, 22 Ala. 409.

The Chattanooga ear was ordered August 16, 1920, to be shipped within 10 days to O. B. Andrews Company, Chattanooga, Tenn. Terms of payment, 80 per cent, cash, less 2 per cent, on receipt of invoice and bill of lading- ; 20 per cent., less 2 per cent, on receipt of destination report. There was no question as to the giving of the order and(its acceptance. On August 17th defendants wrote plaintiffs, instructing them not to ship the car of lumber ordered on the 16th for “a few days," and promising future instructions as to disposition, basing the request for delay upon a wire from the Andrews Company requesting delay on account of shortage of labor. On August 25th plaintiffs wrote defendants, asking for shipping instructions on the Chattanooga car. On August 30th defendants wrote plaintiffs again delaying shipment and promising shipping instructions later. On September 2d, according to plaintiffs’ testimony, plaintiffs called defendants over the phone and demanded shipping instructions. Upon being further instructed to wait, plaintiffs told defendants that, if instructions were not sent that day, shipment would be made anyway. To this defendants only promised to let plaintiffs know “shortly.” Nothing more being heard from defendants, plaintiffs on September 11th shipped the car of lumber, as per instructions in the original order, to O. B. Andrews Company, Chattanooga, Tenn., and carried the invoice and bill of lading to defendants, demanding payment of 80 per cent., less 2 per cent, which was refused, and the invoice and bill of lading returned to plaintiffs. The car in due time ' arrived in Chattanooga, was switched into the yard of the O. B. Andrews Company, and by them unloaded. It is true the witness Harless testified as his conclusion that Andrews Company did not accept the ear, but he and others testified to the facts incident to the car’s arrival, unloading, and disposition of the lumber. That made this a jury question, as also the question as to whether the lumber in the car was up to grade, size, dimensions, etc. In all of the letters and conversations between plaintiffs and defendants, the request for delay in shipment was based upon requests from Andrews Company for delay in shipment on account of the crowded condition of their yard in Chattanooga and inability to handle the car on that account.

Of course, if there was no breach of the contract before. shipment, and no change agreed upon as to its terms, except to delay shipment until such time as the O. B. Andrews Company would accept the car when received, and plaintiffs executed the contract by a delivery of the possession of the ear of lumber to the O. B. Andrews Company as contemplated in the original order, and before a breach had occurred, the plaintiffs may recover the purchase price under the common counts. Vinegar Bend Lumber *488 Co. v. Soule Steam Feed Works, 182 Ala. 146, 62 South. 279. It cannot lie said that the letter of defendants to plaintiffs dated August 17th, as follows:

“Please refer to our order No. 299-F for one car 1x4 and wider, for shipment to O. B. Andrews Company, Chattanooga, Tennessee, and withhold shipment of this car for a few days. Our customer has just wired us they had forty cars on the tracks now on demurrage, and with the scarcity of labor there they have asked that we not ship any more until they could get their track cleared, and we have wired them to-day that we would withhold shipment for a few days on this account.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bailey v. City of Mobile
167 So. 2d 294 (Supreme Court of Alabama, 1964)
Leigh v. Cornelius
15 S.E.2d 827 (Court of Appeals of Georgia, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
93 So. 378, 18 Ala. App. 485, 1922 Ala. App. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herzfeld-lumber-co-v-langley-alactapp-1922.