Hershey v. H. S. Kerbaugh, Inc.

88 A. 1009, 242 Pa. 227, 1913 Pa. LEXIS 869
CourtSupreme Court of Pennsylvania
DecidedJuly 10, 1913
DocketAppeal, No. 99
StatusPublished
Cited by10 cases

This text of 88 A. 1009 (Hershey v. H. S. Kerbaugh, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hershey v. H. S. Kerbaugh, Inc., 88 A. 1009, 242 Pa. 227, 1913 Pa. LEXIS 869 (Pa. 1913).

Opinion

Opinion by

Mr. Justice Potter,

In the years 1904 and 1905 Andrew H. Hershey, Ezra M. Good and Christian H. Holt were the owners as tenants in common of several small islands in the Susquehana river, lying about 1,600 feet from the east shore, in Conestoga township, Lancaster County, and containing about 136 acres of land of which about 80 acres were subject to cultivation. There were also upon [230]*230the islands deposits of molding sand, which had commercial value. As occasion for it arose, the produce and sand were, according to the testimony, taken off by means of rafts and flat boats, through a channel running between the islands and the east bank of the river, where a public road was reached. In the latter part of the year 1904 and in 1905, the defendant, which is a corporation engaged in the contracting business, was constructing a railroad for the Pennsylvania Railroad Company along the east bank of the Susquehanna river opposite these islands. The evidence tended to show that in the process of grading and blasting the high rocky bluff, considerable amounts of rock were thrown into the channel, and into the public road, with the effect of blocking the channel and preventing its use as a means of passage to and from the islands. After bringing this suit to recover damages, all the interests of the original plaintiffs in the action were assigned and transferred to J. W. Fehl, and the suit was marked to his use upon the record. The trial resulted in a verdict for the plaintiffs in the sum of $7,916. Judgment was entered on the verdict and defendant has appealed.

The first assignment of error is to the admission in evidence of plaintiffs’ offer to prove by the witness Good, one of the plaintiffs, that the channel of the river was filled up by rock, caused by the blasting of defendant, to such an extent that it could no longer be operated, and also that the defendant “placed a pier or abutment of a bridge in the public road and likewise (on) a portion of the right of way over the public road, and absolutely destroyed the same.” Upon objection being made, the trial judge restricted the testimony to showing interference with the channel. Plaintiffs’ counsel then put this question to the witness: “Was the public road at which you landed then, practically wiped out by the construction of this company?” By the word “construction” was meant apparently the pier or abutment of the bridge mentioned in the former offer. The bridge was [231]*231however erected by the railroad company under its power of eminent domain. The trial court admitted the question, with the qualification, “if it was off the right of way.” We find neither allegation nor proof that the pier or abutment was off the right of way. Plaintiffs contended that the defendant had blocked up the roadway for some distance between the bridge and the river, but the evidence as to this is vague. It was not shown what the cost of removing this rock, so as to clear a passageway, would have been, nor was there anything to show that the railroad had not, or would not perform its statutory duty in constructing another road. In the absence of such testimony, we think the court erred in overruling the objection to this last question.

The second assignment alleges error in refusing binding instructions for defendant. The third assignment is to the refusal to enter judgment for the defendant non obstante veredicto; and the fourth assignment alleges that the court below erred in entering judgment on the verdict. These assignments are all based upon the theory that the plaintiffs had no right to recover in this action. In support of their contention in this respect, counsel for defendant advance three reasons: 1. That as the action included a demand for exemplary or punitive damages which is not assignable, and as the suit was maintained by an assignee of the original plaintiff, no recovery could be had. 2. Because there was pending at the time a suit in equity in which the original plaintiffs had applied for an injunction to restrain the defendant, and the Pennsylvania Railroad Company, from carrying on blasting operations; and, 3. Because no damages could be recovered in a private action for the result of a public nuisance. None of these reasons seem to us to be well taken. As to the first one, the trial judge ruled squarely that under the evidence no recovery could be had for punitive damages, and he so instructed the jury. As to the second reason, — the pendency of the equity suit — that is a matter which should have been [232]*232raised by plea in abatement: Gardner v. Kiehl, 182 Pa. 194. Even if the question were properly raised, it by no means follows that the pendency of the equity suit would be a bar to the present action. The plaintiffs are at liberty to discontinue the former suit at any time, and if called upon to do so, can make reply that no such action is pending: Findlay v. Keim, 62 Pa. 112.

As to the third reason, it is apparent that plaintiffs suffered some special damage from the public nuisance of which complaint was made, beyond that which affected the public at large; and because of the special injury suffered, they may recover damages. In Penna. & Ohio Canal Co. v. Graham, 63 Pa. 290, Mr. Justice Sharswood said (p. 296) : “It has been settled law from the year books downward, if a party has sustained any special damage from a public nuisance beyond that which affects the public at large, whether it be direct or consequential, an action will lie against the author of the nuisance, for redress.” As the evidence tended to show that the owners of the islands in question suffered some special damage, they were entitled to maintain an action therefor, and the court below could not therefore have entered judgment for defendant. Nor would it have been proper for him to have confined the recovery to a nominal sum. The jury were instructed that they might find nominal damages or a greater amount, in accordance as they should find the facts.

In the eighth assignment it is alleged that the court below erred in affirming plaintiffs’ second point for charge, which permitted the jury to award damages for obstructing a public road outside the right of way of the railroad company. We do not find in the record any evidence tending to show that the obstructions in the road could not have been removed, nor any evidence as to what the cost of such removal would have been. Nor was it shown that if they had been removed, the railroad bridge would not still have interfered with tha use of the road by plaintiffs. If the obstructions could have been [233]*233removed at reasonable cost, obviously that amount would have been the proper measure of damages, in so far as that item was concerned. And if the obstructions were due in part to the act of the railroad company in locating the abutments of its bridge at that point, the responsibility for that act would be upon the railroad company, and not upon the defendant. We are not able to find in the record evidence from which the amount of damages due to the obstructions of the road could have been ascertained by the jury. We think, therefore, that the trial judge erred in permitting them to include in the verdict anything for this item.

In affirming plaintiffs’ third point of which complaint is made in the ninth assignment of error, and in that part of the general charge which is set forth in the tenth assignment, the trial judge instructed the jury that the measure of damages was the difference between the market value of the land before the trespass was committed, and its market value afterwards.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. B. Corp. v. Jessop Steel Co.
42 Pa. D. & C.3d 363 (Chester County Court of Common Pleas, 1985)
Ambrose v. Western Maryland Railway Co.
63 Pa. D. & C. 150 (Franklin County Court of Common Pleas, 1947)
Toy v. Atlantic Gulf & Pacific Co.
4 A.2d 757 (Court of Appeals of Maryland, 1939)
Blythe v. Rupf
6 Conn. Super. Ct. 195 (Connecticut Superior Court, 1938)
Blythe v. Rupf
6 Conn. Supp. 195 (Pennsylvania Court of Common Pleas, 1938)
Commonwealth Trust Co. v. Heh
99 Pa. Super. 479 (Superior Court of Pennsylvania, 1930)
Titus v. Poland Coal Co.
119 A. 540 (Supreme Court of Pennsylvania, 1923)
Feather v. Hustead
98 A. 971 (Supreme Court of Pennsylvania, 1916)
Hettrick v. Eby
62 Pa. Super. 21 (Superior Court of Pennsylvania, 1915)
Trimmer v. Berkheimer
61 Pa. Super. 269 (Superior Court of Pennsylvania, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
88 A. 1009, 242 Pa. 227, 1913 Pa. LEXIS 869, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hershey-v-h-s-kerbaugh-inc-pa-1913.