Hernandez v. Big 4, Inc.

241 F. Supp. 2d 715, 2003 U.S. Dist. LEXIS 999, 2003 WL 168901
CourtDistrict Court, S.D. Texas
DecidedJanuary 9, 2003
DocketCIV.A.G-02-298
StatusPublished

This text of 241 F. Supp. 2d 715 (Hernandez v. Big 4, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hernandez v. Big 4, Inc., 241 F. Supp. 2d 715, 2003 U.S. Dist. LEXIS 999, 2003 WL 168901 (S.D. Tex. 2003).

Opinion

ORDER DENYING DEFENDANT AND CROSS-PLAINTIFF DAVID E. HARVEY BUILDERS, INC.’S MOTION FOR PARTIAL SUMMARY JUDGMENT

KENT, District Judge.

Plaintiff Horacio Hernandez brings this personal injury action seeking damages from Defendant and Cross-Plaintiff David E. Harvey Builders (“Harvey”) and Defendant and Cross-Defendant Big 4 Erectors, L.P. (“Big 4”), amongst others. Now before the Court is Harvey’s Motion for Partial Summary Judgment, which seeks a declaration that Big 4 is contractually obligated to defend Harvey in the underlying personal injury action. Further, Harvey requests the Court to award reasonable attorney fees to Harvey for the costs it incurred in prosecuting this cross-claim against Big 4. After carefully and thoughtfully reviewing the Motion, the Response thereto, the summary judgment evidence and the applicable law, the Court concludes that, for the reasons articulated below, Harvey’s Motion for Partial Summary Judgment must be DENIED.

I. BACKGROUND

Horacio Hernandez was injured on January 30, 2002, at a construction site (“the Project”) located in Houston, Texas. Harvey was the general contractor and overseer of the Project. Harvey contracted out the erection and installation of all structural steel at the Project to Big 4. Big 4 then contracted out portions of its con *717 tract to other subcontractors. Hernandez apparently was an employee of a subcontractor that Big 4 contracted with in order to complete the erection of the structural steel at the Project. While Hernandez was in the course of erecting structural steel at the Project, he fell and injured himself-whieh is the basis for the underlying personal injury action before the Court.

Harvey’s Motion is based solely upon the contract (“Contract”) between it and Big 4, signed on August 27, 2001, for the erection of all structural steel at the Project. 1 Harvey seeks a declaration that Hernandez’s claims fall within the scope of certain indemnity provisions contained in the Contract; and therefore, that Big 4 is obligated to defend Harvey regardless of Big 4’s fault. The relevant Contract provision, section 7(b) titled “Additional Indemnity,” states:

Subcontractors shall defend, indemnify and hold harmless Contractor, Contractor’s Surety, if any, Owner, and Archi-techt (and their officers, directors, shareholders, agents and employees) (hereinafter collectively referred to as “indemnified parties”) from and against any and all claims, causes of action, lawsuits, judgments, and liability of every kind, including all expenses of litigation, court costs, and attorneys’ fees, for injury to or death of any person (including without limitation, Subcontractor’s employees) and for damages to any property, arising out of or relating to or in connection with the operations, performance, or acts of omissions of Subcontractor (including all employees, sub-subcontractors, suppliers and others for whom subcontractor is responsible), or the work performed or to be performed by Subcontractor. Subcontractor’s above indemnity obligation is limited to the extent such injury or damage is caused in whole or in part by negligent acts or omissions of Subcontractor. Subcontractor’s above duty to defend extends to such injury or damage caused by the negligence of an indemnified party, including the sole negligence of an indemnified party; provided however, without relieving Subcontractor of its obligations- hereunder, any of the indemnified parties, at their election, may defend or participate in the defense of any claim to which Subcontractor’s duty to defend extends.

(emphasis added). The Parties agree that this clause controls the resolution of this Partial Summary Judgment. Harvey contends that section 7(b) of the Contract clearly and unambiguously requires Big 4 to defend Harvey from any claims relating to Big 4’s steel erection operations (Hernandez’s action), regardless of whether Big 4 was actually negligent or not. Harvey contrasts the duty to defend obligation (3rd sentence of section 7(b)) with the more limited duty to indemnify obligation (2nd sentence of section 7(b)), which obligates Big 4 to only indemnify other Parties for the proportion of fault that Big 4 attributed to Hernandez’s injury. Harvey contends that the two separate duties are not inconsistent, but rather carefully drafted to fulfill the Parties intentions. Harvey asserts that Big 4’s interpretation of the Contract would render the third clause of section 7(b) meaningless, which is contrary *718 to the rule of construction that assumes the Parties intended to give effect to every clause.

Big 4 argues that section 7(b) is not enforceable as a matter of law because the cited provision is internally contradictory, and thus, ambiguous; hence, it presents a fact question. Because of this alleged internal contradiction, Big 4 urges the Court to employ secondary rules of construction. Big 4 cites the common rule that when there is an irreconcilable conflict between two clauses in a contract, the first is to be given effect. Thus, Big 4 contends that its duty to defend should be based upon its relative fault, consistent with its indemnity obligation. With these facts and arguments in mind, the Court now turns to the task of interpreting the Contract and applying the applicable law.

II. ANALYSIS

Summary judgment is appropriate if no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. See Fed.R.Civ.P. 56(c); see also Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986). When one party moves for summary judgment, the non-moving party must set forth specific facts showing that there is a genuine issue for trial. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 250, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Issues of material fact are “genuine” only if they require resolution by a trier of fact. See id. at 248, 106 S.Ct. at 2510. The mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment. Only disputes over facts that might affect the outcome of the lawsuit under governing law will preclude the entry of summary judgment. See id. at 247-48, 106 S.Ct. at 2510. Nevertheless, if the evidence is such that a reasonable fact-finder could find in favor of the nonmoving party, summary judgment should not be granted. See id.; see also Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986); Dixon v. State Farm Fire & Cas. Co., 799 F.Supp. 691 (S.D.Tex.1992) (noting that summary judgment is inappropriate if the evidence could lead to different factual findings and conclusions).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Amica Mutual Insurance Company v. Donna Moak
55 F.3d 1093 (Fifth Circuit, 1995)
Dixon v. State Farm Fire & Casualty Co.
799 F. Supp. 691 (S.D. Texas, 1992)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Riley v. Champion International Corp.
973 F. Supp. 634 (E.D. Texas, 1997)
Allright, Inc. v. Elledge
515 S.W.2d 266 (Texas Supreme Court, 1974)
Dallas Bank & Trust Co. v. Frigiking, Inc.
692 S.W.2d 163 (Court of Appeals of Texas, 1985)
Ethyl Corp. v. Daniel Construction Co.
725 S.W.2d 705 (Texas Supreme Court, 1987)
Enserch Corp. v. Parker
794 S.W.2d 2 (Texas Supreme Court, 1990)
Dresser Industries, Inc. v. Page Petroleum, Inc.
853 S.W.2d 505 (Texas Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
241 F. Supp. 2d 715, 2003 U.S. Dist. LEXIS 999, 2003 WL 168901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hernandez-v-big-4-inc-txsd-2003.