Herman Chanen Construction Co. v. Northwest Tile & Terrazzo Com.

433 P.2d 807, 6 Ariz. App. 490, 1967 Ariz. App. LEXIS 613
CourtCourt of Appeals of Arizona
DecidedNovember 16, 1967
Docket1 CA-CIV 432
StatusPublished
Cited by8 cases

This text of 433 P.2d 807 (Herman Chanen Construction Co. v. Northwest Tile & Terrazzo Com.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herman Chanen Construction Co. v. Northwest Tile & Terrazzo Com., 433 P.2d 807, 6 Ariz. App. 490, 1967 Ariz. App. LEXIS 613 (Ark. Ct. App. 1967).

Opinion

DONOFRIO, Judge.

This is an appeal from a summary judgment in favor of Appellee Northwest Tile and Terrazzo Company of Montana, Incorporated (Northwest), plaintiff below, and against Herman Chanen Construction Company, Inc. (Chanen) and its surety, General Insurance Co. of America, defendants below and appellants.

The pertinent facts can be stated briefly as follows: Appellant Chanen was the general contractor in charge of the construction of the terminal building at the Sky Harbor Municipal Airport in Phoenix. It subcontracted the tile and mosaic work to appellee Northwest. Shortly after Northwest had accepted the subcontract from Chanen it had occasion to write the Registrar of Contractors to ascertain whether or not the C-33 (mosaic and terrazzo) license which it held was proper to cover the work involved. The Registrar replied by letter that since a portion of the work concerned laying ceramic tile, which is covered by a C-48 (ceramic, etc.) license, Northwest was not properly licensed; further, that since it had bid on a contract for a job for which it was not licensed, in violation of A.R.S. § 32-1154, subsec. 18, it could not be granted the appropriate license for a period of one year. The Registrar of Contractors also informed Northwest that Northwest’s ceramic tile license for California would not authorize it to do such work in Arizona as there was no reciprocity between California and Arizona on the licensing of contractors. Both the Registrar and Northwest’s own attorney recommended that the portion of the work not covered by the C-33 license should be subcontracted to a properly licensed contractor. Perry Tile and Marble Company of Phoenix was recommended by Chanen as the subcontractor to do the work. Despite the rec-, ommendation, Northwest wanted to assign the ceramic portion of its contract t® Perry outright rather than subcontract it. Chanen insisted, however, after consulting legal counsel, that it should be subcontracted rather than assigned. This was done, and Perry was subcontracted to fill the ceramic portion of the work. Northwest has now paid Perry for this work.

The date for completion of Northwest’s portion of the project was originally set for July 14, 1961, but later it was advanced to.August 14, 1961. Northwest, however, was unable to commence until August 22 and we assume this was through no fault of its own because the parties pushed the deadline to November 22, 1961. The work was not completed until February 2, 1962, seventy-two days later. The contract provided that Northwest would be liable to Chanen on the basis of $250.00 per day for each day of delay beyond the scheduled time of completion. No question was raised that if Northwest was found to be responsible for the delay the amount of liquidated damages would be on the basis of $250.00 per day, and that for the seventy-two days’ delay it would total $18,000. Northwest contends that the delay was caused by Chanen’-s poor organization and other subcontractors’ interference.

Northwest began this action for the over $22,000 due and owing under the contract. When Chanen asserted a defense of delay and $18,000 liquidated damages as a setoff, Northwest then amended the action to pray for over $42,000 damages which it alleged was suffered by reason of the delay which it asserted was due to Chanen’s actions. Aside from the issue of damages for delay, the only monetary question was a small matter of about $400.00 arising over change orders.

The first question we shall consider is the defense to the action that Northwest had contracted to do a job not covered ¡by its *492 license and therefore under A.R.S. § 32-1153 is precluded from recovery;

In line with Supreme Court cases, we have held that by § 32-1153 the Legislature has denied a party entering into a contract the right to sue on that contract if he does not hold the proper license to perform the contracted task. Security Insurance Company of New Haven, a corporation v. Day, 6 Ariz.App. 403, 433 P.2d 54 (1967). In the instant case it is to be noted, however that we do not have a contractor performing work exceeding his license authority, but rather a contractor who sought to perform a task for which it appeared to be licensed. However, when it found that it was not properly licensed it sought advice, and at the suggestion of the Registrar of Contractors and upon the insistence of Chanen, subcontracted rather than assigned the task to a qualified licensed party. A reason given by the defense for not wanting an assignment was that it was desirable to .keep the work subject to Northwest’s bond.

Defense now seeks to deny liability on the contract and payment for the work done by Perry because plaintiff, as original contractor, did not have the proper license and had to subcontract the work to this properly licensed party. Under these circumstances we cannot agree that the Legislature intended this result. The true intent of the legislation contained in Arizona Revised Statutes, Title 32, Chapter 10, was to protect the welfare of the public dealing with persons engaged in the building contracting vocation and to afford such public a protection against incompetent, inexperienced, unlawful and fraudulent acts of the building contractors with whom they contract. We have held its purpose is to regulate the conduct of those engaged in the business of contracting so as to discourage certain bad practices which might be indulged in to the detriment of the public. Security Insurance Co. of New Haven v. Day, supra. In the present case the defendant Chanen not only got skilled craftsmanship, but it was performed by a duly ■ licensed contractor. To say that Northwest is prevented from bringing this lawsuit because it had, on the insistence of defense, subcontracted the ceramic work when instead it wanted to assign, would be a travesty on justice. We believe this is a proper place to invoke the doctrine of estoppel against defendant Chanen.

Briefly, the elements of estoppel are: first, an action which is inconsistent with a later claim; second, action by an adverse party relying on such conduct; and third, injury to the adverse party resulting from repudiation of such conduct. Engler v. Sainer, 4 Ariz.App. 86, 417 P.2d 720 (1966). We find all the elements present in this case. Chanen insisted on Northwest subcontracting the ceramic tile rather than assigning it. Relying on the insistence of defense, the work was subcontracted to Perry. All this was done when both parties were fully informed as to Northwest’s license limitation. Now Chanen wishes to use its insistence to the injury of Northwest. In Bartholomew v. Superior Court, 4 Ariz. App. 50, 417 P.2d 563 (1966), the Court, speaking of estoppel, said:

'The remedy of estoppel * * * is based on the grounds of public policy and good faith, and is interposed to prevent injury, fraud, injustice, and inequitable consequences by denying to a person the right to repudiate his acts, admissions, or representations, when they have been relied on by persons to whom they were directed and whose conduct they were intended to and did influence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Twin Peaks Construction Inc. v. Weatherguard Metal Construction, Inc.
154 P.3d 378 (Court of Appeals of Arizona, 2007)
Lundy v. Prescott Valley, Inc.
511 P.2d 652 (Court of Appeals of Arizona, 1973)
Chickering v. George R. Ogonowski Const. Co., Inc.
501 P.2d 952 (Court of Appeals of Arizona, 1972)
United States Fidelity & Guaranty Co. v. Baird's Bread Co.
499 P.2d 171 (Court of Appeals of Arizona, 1972)
Irwin v. Pacific American Life Insurance Company
457 P.2d 736 (Court of Appeals of Arizona, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
433 P.2d 807, 6 Ariz. App. 490, 1967 Ariz. App. LEXIS 613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herman-chanen-construction-co-v-northwest-tile-terrazzo-com-arizctapp-1967.