Heritage Standard Bank & Trust Co. v. Steel City National Bank

599 N.E.2d 1283, 234 Ill. App. 3d 48, 175 Ill. Dec. 269, 1992 Ill. App. LEXIS 1372
CourtAppellate Court of Illinois
DecidedAugust 27, 1992
DocketNo. 1—91—3191
StatusPublished
Cited by5 cases

This text of 599 N.E.2d 1283 (Heritage Standard Bank & Trust Co. v. Steel City National Bank) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heritage Standard Bank & Trust Co. v. Steel City National Bank, 599 N.E.2d 1283, 234 Ill. App. 3d 48, 175 Ill. Dec. 269, 1992 Ill. App. LEXIS 1372 (Ill. Ct. App. 1992).

Opinion

JUSTICE McMORROW

delivered the opinion of the court:

The trial court entered an order granting a preliminary injunction which enjoined defendants from terminating a real estate contract pursuant to a notice of default from defendants to plaintiffs. On interlocutory appeal from that order, defendants contend that the trial court abused its discretion in issuing the injunction because plaintiffs failed to establish the elements necessary for issuance of preliminary injunctive relief.

The underlying litigation concerns a real estate contract entered into on August 12, 1986, for the sale and purchase of approximately 200 acres of land situated in unincorporated Palos Township in southwest Cook County, Illinois. The land had been zoned for a planned unit development (PUD) and is hereafter referred to as “Palos West.”

Plaintiff Heritage Standard Bank & Trust Company is the trustee of land trust 3167 and the contract purchaser of Palos West. Plaintiff Orchard Hill Building Co., a general partnership, is the sole beneficiary of the land trust, and plaintiff Robert C. Gallagher is a partner in Orchard Hill Building Co., who holds the power of direction under the trust. Defendant Steel City National Bank, as trustee of land trust 2536, is the contract seller of Palos West. The other defendants are the First Cook Community Bank, the beneficiary of the land trust, and Michael Habidas, the chairman of the board of directors of First Cook Community Bank and guarantor of the obligations of the land trust under the real estate contract. We will generally refer to the parties collectively as plaintiffs and defendants.

On January 18, 1990, plaintiffs filed a five-count complaint alleging that defendants were in breach of the terms of the contract, a copy of which was attached to the complaint. Under the terms of the contract, plaintiffs agreed to purchase subdivided, improved, single-family residential lots from defendants at the price of between $35,000 and $40,000 per lot. The parties anticipated that when fully subdivided, the Palos West property would yield approximately 500 residential lots. Defendants were to convey a specified number of lots in seven annual stages, from December 24, 1986, through December 24, 1992. As each group of lots was conveyed, plaintiffs would construct single-family homes on them for sale to the public. Plaintiffs paid $500,000 as earnest money deposit, and agreed to pay 10% interest on the principal balance pursuant to a formula detailed in the contract. The contract further provided:

“[I]n the event Seller is not able to convey title to any group of lots by the date upon which Seller is obligated to convey such lots fully improved [in accordance with the Palos West PUD Plan], because Seller has not completed the improvements relating to such group of lots in time, through no fault of the Purchaser, then, interest on the monies due from Purchasers for such group of lots shall not accrue from and after the agreed upon completion date of the improvements on such lots, up to and including their conveyance to Purchaser, fully improved as herein provided. If Seller fails to complete the improvements on such group of lots within sixty (60) days after the closing date with regard to such group of lots, then, all interest shall cease to accrue on the entire principal balance remaining due, until the improvements on such group of lots are completed ***.”

The first group of lots, consisting of 113 parcels, was conveyed on December 24, 1986. The stage 2 and stage 3 lots were conveyed in October 1987 and April 1989, respectively. Plaintiffs’ complaint related to a disagreement which arose prior to the conveyance of all of the stage 4 lots.

Plaintiffs alleged that under the original PUD plan, Palos West was to be a single unified community connected by a subdivision street system and containing numerous lake lots adjacent to a water detention area on the property. The complaint stated that on December 4, 1989, defendants, for the first time, furnished plaintiffs with a “Proposed Palos West Plan,” dated June 14, 1989, and informed plaintiffs that the proposed plan had already been approved by the Cook County Zoning Board of Appeals. Plaintiffs alleged that defendants’ failure to consult with plaintiffs or seek plaintiffs’ approval for the proposed plan violated the contract provision giving plaintiffs the right to approve the site plans for those portions of Palos West which had not yet been approved by Cook County. In a letter dated December 19, 1989, plaintiff Robert Gallagher notified defendant Michael Halikias that plaintiffs objected to the proposed plan because it: eliminated the lake frontage lots in the original PUD plan; eliminated a section of street which connected an otherwise isolated 10-acre tract of the development; created a traffic hazard by adding an intersection nearby two others; and decreased the average lot size by adding four lots to the isolated 10-acre tract. In a second letter, also dated December 19, 1989, Gallagher further advised Halikias that the contract obligated defendants to complete construction on “Phase VII” of Palos West and to convey the remaining, improved stage 4 lots by the scheduled closing date of December 24, 1989. Gallagher stated that if the property was not improved and conveyed in accordance with the original plan, interest on those lots would cease to accrue as of February 27, 1990, and that interest on all remaining lots would cease to accrue on March 24, 1990. Plaintiffs alleged, and defendants do not dispute, that defendants did not complete the improvements on 71 of the 240 stage 4 lots as provided in the original contract, and that no lots have been conveyed to plaintiffs since April 4,1989.

Plaintiffs asserted that defendants’ refusal to perform its obligations to improve the property in accordance with the original PUD plan constituted a breach of the real estate contract. Plaintiffs alleged that defendants’ failure to subdivide and improve the property in accordance with the original plan would cause irreparable injuries to plaintiffs. Plaintiffs sought a permanent prohibitory injunction restricting defendants from proceeding with the subdivision and improvement of Palos West under the proposed plan, a mandatory injunction compelling defendants to subdivide Palos West in accordance with the original plan, and specific performance.

On March 29, 1990, defendants filed their answer denying the material allegations of plaintiffs’ complaint. In early April 1990, plaintiffs tendered two checks to defendants as payment of interest owed on previously conveyed lots and a prorated portion of the interest for the quarter ending March 31, 1990. In a letter dated April 30, 1990, defendants asserted that the amount tendered by plaintiffs for the quarter ending March 1990 was insufficient. Defendants noted that the contract provided for the suspension of interest payments only if the failure to convey lots was “through no fault of the [plaintiffs].” Defendants maintained that plaintiffs were at least partially at fault for the delay at issue and, therefore, that interest continued to accrue and that plaintiffs’ failure to pay it constituted a breach of the contract. In a letter dated May 8, 1990, plaintiffs denied that they were partially at fault and stated that, absent substantiation of that claim, interest payments would not be made until defendants improved and conveyed the lots in accordance with the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Happy R Securities, LLC v. Agri-Sources, LLC
2013 IL App (3d) 120509 (Appellate Court of Illinois, 2013)
Save Prairie Society v. Greene Development Group Inc.
752 N.E.2d 523 (Appellate Court of Illinois, 2001)
Gerber v. Hamilton
659 N.E.2d 443 (Appellate Court of Illinois, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
599 N.E.2d 1283, 234 Ill. App. 3d 48, 175 Ill. Dec. 269, 1992 Ill. App. LEXIS 1372, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heritage-standard-bank-trust-co-v-steel-city-national-bank-illappct-1992.