Heritage Square Development Co. v. City of Sandy

648 P.2d 1317, 58 Or. App. 485, 1982 Ore. App. LEXIS 3138
CourtCourt of Appeals of Oregon
DecidedAugust 4, 1982
Docket79-12-199, CA A20092; 79-12-168, CA A20092; 79-12-47, CA A20092
StatusPublished
Cited by5 cases

This text of 648 P.2d 1317 (Heritage Square Development Co. v. City of Sandy) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heritage Square Development Co. v. City of Sandy, 648 P.2d 1317, 58 Or. App. 485, 1982 Ore. App. LEXIS 3138 (Or. Ct. App. 1982).

Opinion

*487 WARREN, J.

This is an appeal from a writ of review proceeding in which the trial court declared void a special assessment and remanded for reassessment. We affirm in part, reverse in part and remand.

FACTS

We summarize the trial court’s findings of fact as supplemented by the parties.

In March, 1976, property owners, including respondents, petitioned the Sandy City Council to construct a 106-space municipal parking lot through a local improvement district (LID). The process for the city proceeding on such petitions is set out in Chapter 12.04 of the Sandy City Code. 1 Pursuant to the Code, the City Engineer was requested to submit a written report.

*489 The engineer’s report was made and approved by the Council on April 19, 1976. The report did not detail plans and specifications but simply listed certain general work with estimated costs. It did not list the cost of property acquisition, appraisal fees, lighting costs, water line and hydrant costs, utilities installation costs or attorney fees. The total cost estimate was $57,565.00. The report did not set forth a description and assessed value of property to be assessed.

The Council set a remonstrance hearing for May 17, 1976, and gave notice of the hearing to property owners to be assessed. Remonstrances at that hearing were only slightly greater than 20 percent of owners affected. A resolution was passed creating LID-4 and directing the engineer to prepare detailed plans and specifications and costs.

By October 1, 1976, when the Council had a regular meeting, certain problems had arisen, and some property owners were concerned as to why the project had not progressed. In executive session held after that meeting, the Council decided to divide the project into two separate phases. Minutes of the Council meeting on November 1, 1976, disclose that Phase I of the project had been approved in executive session and would be up for approval before the Council. This meeting was adjourned until November 4, 1976. Notices to property owners to be assessed, under date of November 2, 1976, were sent by registered mail. The notice indicated that the business before the Council would be that of making a final decision on the improvement to resolve problems so that bids could be let on Phase I of LID-4. The notice did not say that Phase I allowed for only 57 parking spaces, compared to the 106 spaces proposed under the original project. No reference was made in the notice to costs or cost increases.

At the November 4, 1976, meeting, various problems were discussed, and no final decision made. A council member noted that there was some misunderstanding *490 about costs. It was stated at one point that engineering bids could not be let until the needed property was acquired. The entire cost of Phase I had not yet been determined. The Council wanted to expedite the completion without finally determining certain costs that could have been estimated with some accuracy and that later constituted a major portion of total costs. The final result of that hearing was a motion to authorize the City Manager, City Attorney and City Engineer to proceed to expedite Phase I and Phase II.

No further formal notice of Council hearings was served on the property owners to be assessed.

On January 23, 1977, a bid for construction of Phase I was let in the amount of $38,763.40, conditioned on the City’s acquisition of the property. Several Council meetings were held thereafter, during which lighting, landscaping and property-acquisition costs were discussed. No formal notice of these meetings was given to property owners assessed. Phase I was subsequently completed.

In June, 1979, notices of assessment were sent to property owners, including respondents. The total assessed cost of Phase I was $104,979.76. This resulted in an increase in respondents’ assessments greatly in excess of 115 2 percent of the engineer’s original estimate, with the project having been substantially decreased in area available for parking and in access.

Certain properties included in the original plan were not assessed for the improvement by the City on the Council’s finding that they were not benefited, because the properties were either not contiguous to the parking lot or were served by other existing parking areas and because in some instances, the use of the property did not require parking space. 3

Respondents Heritage Square Development Co., Georgia Shaffer and Warren Decker on several occasions urged the Council to proceed with the improvement, having knowledge of the proposal to proceed only with Phase I and of the problems involved but not of the great increase in *491 costs over the engineer’s original estimate. Respondents Bolster and Scales did approve of the proposal to split the project into Phase I and Phase II but were without knowledge of the large increase in costs over the engineer’s original estimate plus 15 percent.

REASSESSMENT

Appellant fails to make any assignments of error but proceeds directly to argument. The scope of our review of writs of review is “as from a judgment of a circuit court in an action.” Assignments of error are required. Former ORAP 7.19; 7.20. ORS 34.100. This is not an equity appeal; because respondents’ cross-appeals do assign errors that require consideration of issues raised in appellant’s arguments, we will consider the arguments.

As framed by the arguments and cross-appellants’ assignments of error, the questions for resolution are (1) whether the matter was properly remanded for reassessment after the assessments were declared void; (2) whether the trial court can limit the amount of cost that is subject to reassessment and, if so, how; and (3) whether substantial evidence supported excluding three properties from the assessment and how that exclusion affects reassessment.

Because we conclude that the matter must be remanded to the City Council for a remonstrance hearing on the issue of creating the LID, we need not reach the other issues.

The city concedes that the proceedings here were defective and that the matter must be remanded, 4 but only for reassessment. It argues that once past the remonstrance *492 stage in creating an LID, all decisions in making the improvement and assessing its cost are political decisions not subject to defeat by remonstrance. The city is correct that, under its ordinances prescribing LID procedures, the only point at which affected property owners may defeat a council decision is at the formation stage. Sandy Code § 12.04.040. Those owners do have, by statute and ordinance, rights to notice and hearing at later stages, but those later rights to be heard do not carry with them the power to defeat council actions taken at those later stages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. City of Powers v. Coos County Airport District
119 P.3d 225 (Court of Appeals of Oregon, 2005)
Martin v. City of Tigard
52 P.3d 1074 (Court of Appeals of Oregon, 2002)
Dittberner v. Windsor Sanitary District Number 1
564 N.W.2d 341 (Court of Appeals of Wisconsin, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
648 P.2d 1317, 58 Or. App. 485, 1982 Ore. App. LEXIS 3138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heritage-square-development-co-v-city-of-sandy-orctapp-1982.