Hercules Construction Co. v. C.J. Moritz Co.

655 S.W.2d 779, 1983 Mo. App. LEXIS 3397
CourtMissouri Court of Appeals
DecidedJuly 12, 1983
DocketNos. 45319, 45324 and 45354
StatusPublished
Cited by6 cases

This text of 655 S.W.2d 779 (Hercules Construction Co. v. C.J. Moritz Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hercules Construction Co. v. C.J. Moritz Co., 655 S.W.2d 779, 1983 Mo. App. LEXIS 3397 (Mo. Ct. App. 1983).

Opinion

DOWD, Judge.

Plaintiff-respondent Hercules Construction Company (hereinafter Hercules) brought suit for breach of contract against its subcontractor, C.J. Moritz Company (hereinafter Moritz) to recover expenses it incurred as general contractor in replacing a supply air fan at the St. Charles Civic Center. In the court tried case, defendant Moritz impleaded John F. Steffen Associates, Inc. (hereinafter Steffen), Western Engineering & Manufacturing Company (hereinafter Western), and Lyon Sheet Metal Works, Inc. (hereinafter Lyon), as third party defendants. At the close of Moritz’ evidence, the trial court sustained Steffen’s motion for a directed verdict and denied similar motions by Western and Lyon. At the conclusion of all the evidence, the trial court rendered judgment on behalf of Hercules in the amount of $24,970.76. The trial court also awarded defendant-third party plaintiff Moritz judgment against both of the remaining third party defendants (Lyon and Western) in the amount of $8,161.60 each. We affirm.

The controversy involves the alleged faulty installation and performance of a supply air fan which was installed in the St. Charles Civic Center for that building’s heating, ventilation, and air conditioning system (hereinafter called HVAC). Hercules was the general contractor for the construction of the civic center. Moritz was the subcontractor who was in charge of the HVAC system. Steffen was the consulting engineering firm hired by the city’s architect to design and formulate the plans and specifications for the HVAC system. Western was the manufacturer of the fan in question and Lyon was the installer of the fan.

The agreement between Hercules and Moritz was embodied in a written contract which placed the entire responsibility for the HVAC work upon Moritz. Article II of [782]*782this contract, denominated “Subcontractor’s Responsibilities,” includes a specific paragraph covering warranties, quality of work, and defects. That provision reads as follows:

“The Subcontractor warrants that all materials and equipment furnished and incorporated by him in the Project shall be new unless otherwise specified and that all Work under this Subcontract shall be. of good quality, free from faults and defects and in conformance with the Contract Documents. All Work not conforming to these standards may be considered defective. The warranty provided in this Paragraph 11.9 shall be in addition to and not in limitation of any other warranty or remedy required by law or by the Contract Documents.”

In formulating its bid on the project, Moritz made available the specifications for the supply air fan to Combustion Kinetics Corporation (hereinafter Combustion), the locally licensed dealer and representative for Western, so that Moritz might obtain a price quote for a Western supply air fan. After receiving notification that its bid was accepted, Moritz issued a purchase order to Combustion for a Western Vaneaxial supply air fan per specifications.

The specifications provided that the supply fan could be either the type manufactured by Joy, a competitor of Western, or a type of similar specifications. The contract documents also set forth the specifications of the Joy fan: one capable of producing 40,000 cubic feet of air per minute at 6.3 inches of static pressure, (emphasis ours)

Western prepared shop drawings for the supply air fan it manufactures and submitted these drawings for approval to the project architect and to Steffen, the consulting engineers. Western’s shop drawings indicated a fan producing 40,000 cubic feet of air per minute at 6.3 inches of total pressure, (emphasis ours) Steffen approved these shop drawings as being in conformance with the building specifications even though the shop drawings used total pressure while the specifications called for static pressure. At the time of the trial, Western could not determine whether it possessed information regarding the fan’s specifications when the shop drawings were prepared.

The specifications specifically provide that the architect’s approval of shop drawings shall not relieve the contractor of responsibility for any deviation from the requirements of the contract documents, nor shall the architect’s approval relieve the contractor from responsibility for errors or omissions in the shop drawings. According to the agreement between Hercules and Moritz, the subcontractor (Moritz) is bound to the contractor (Hercules) by those same terms.

The specifications called for a fan which could be mounted horizontally, vertically, or at any incline. Lyon’s foreman, who was in charge of installation of the fan, interpreted from these specifications that the fan could be installed in any fashion. Lyon’s crew installed the fan with the device known as the vortex damper operator on the bottom side of the fan. In comparison with Western’s diagram of the fan, the fan was inverted.

The City of St. Charles took occupancy of a portion of the building in April of 1976 and the HVAC system became operational in May of the same year. Witness Carl Austin, the building superintendent for the City of St. Charles, testified that there was trouble with the fan from the very beginning in 1976 and in early 1977 the wires in the motor exploded.

In 1976, Mr. John Flynn was in charge of Hercules’ field operations at the St. Charles Civic Center construction site. He testified concerning three instances in 1976 when the fan failed to operate. On these occasions the fan’s actuater linkage was found broken. Mr. Flynn further testified that he inspected the plans, drawings, and specifications and determined that the fan had been mounted in an inverted position. Mr. Keith St. Onge, Western’s product manager, testified that the probable cause of the wires exploding was the excessive moisture in the motor. This moisture was not able to escape through the “weep holes” in the fan [783]*783because these were located on top of the motor, due to the fan being mounted in an inverted position.

The Senco Corporation conducted a performance test of the supply air fan shortly after it was installed. The results thereof are known as a balancing report. According to the balancing report, the supply air fan was producing 33,273 cubic feet of air per minute while the specifications for the fan called for 40,000 cubic feet of air per minute. Moreover, the reading of 33,273 cfm was obtained at a total pressure of only 4.8 inches — substantially less than the 6.3 inches of total pressure which Western designed the fan to work against.

In May of 1977, Western’s field service representative inspected the supply air fan at the civic center. Western’s report on the inspection indicated that the linkage on the activator was broken, the blade shanks were binding, the sensor controls were manually overridden to keep the fan at a maximum pitch, the fan housing had fatigue cracks, and the fan was installed upside down. The Western field service representative placed additional braces on the fan to support the motor, recommended that the fan be rotated to allow the motor condensate drains to work, and indicated that some welding would be necessary in order to repair cracks in the fan housing.

A second field service report dated August 20,1976, disclosed that the fan assembly and conduit box were inundated with water from condensation and the field service report on November 24, 1976, revealed that the fan linkage was again sheared off and needed to be replaced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schaefer v. Rivers
965 S.W.2d 954 (Missouri Court of Appeals, 1998)
Gilmartin Bros., Inc. v. Kern
916 S.W.2d 324 (Missouri Court of Appeals, 1995)
Missouri Farmers Ass'n v. Campbell
754 S.W.2d 596 (Missouri Court of Appeals, 1988)
Wyrozynski v. Nichols
752 S.W.2d 433 (Missouri Court of Appeals, 1988)
Davis v. City of Kinloch
752 S.W.2d 420 (Missouri Court of Appeals, 1988)
Means v. Clardy
735 S.W.2d 6 (Missouri Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
655 S.W.2d 779, 1983 Mo. App. LEXIS 3397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hercules-construction-co-v-cj-moritz-co-moctapp-1983.