Herbert v. Dey

15 Abb. N. Cas. 172
CourtNew York Supreme Court
DecidedMay 15, 1884
StatusPublished
Cited by1 cases

This text of 15 Abb. N. Cas. 172 (Herbert v. Dey) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herbert v. Dey, 15 Abb. N. Cas. 172 (N.Y. Super. Ct. 1884).

Opinion

Daniels, J.

The verdict was rendered for the amount considered by the jury to be unpaid for services performed and materials supplied by the plaintiffs for the defendant. There was no dispute as to what had been done or as to the materials furnished, by them for him. The larger part was for the excavation required, and the labor, and the materials used, in finishing the cellar of the dwelling known as No. 121 East Twenty-fourth street.

They were asserted to have been performed and supplied under a special agreement, by which the plaintiffs agreed to finish the cellar in such a manner that it would be afterwards dry and free from water, and for a stipulated price. There was a controversy in the case concerning the making of the agreement,, the defendant testifying that the plaintiff, by whom the business was transacted in behalf of their firm guaranteed that the cellar should be dry, while this plaintiff in his evidence denied the making of this guaranty, but at the same time conceded that he said the work to be done would, in his judgment, make a tight cellar.

The jury could very well determine from this state of the evidence, as they seem to have done, as they [174]*174rejected the fourth cause of action, which included the charges made for the subsequent work" required to make the cellar dry, that the agreement did contain the guaranty mentioned by the defendant.

' The first work was finished in December, 1874. That was deemed to be all that was needed to render the cellar dry, and to finish it in other respects, as it was desired, and expected that it would be done. And a bill of the labor performed and materials furnished up to that time was rendered to the defendant, and payments were made, as the plaintiff examined as a witness testified, upon this bill, but as the defendant stated them, they were upon the contract. Which statement was most probably correct cannot be very important in the disposition of the appeals, for, as the-money was received by the plaintiffs, it had the effect of reducing the demand, and in that manner the defendant had the full benefit of it in the decision of the case.

But after that work had beén done, it proved to be incomplete in the exclusion of water from the cellar. That still collected there, above the cellar bottom put in by the plaintiffs, to such an extent as to render the dwelling improper for domestic uses. And when the' plaintiffs’ attention was directed to that fact, they resumed their work there again, to secure the end both parties had in view, of making a dry cellar. To do that, required that part of the cellar bottom, which had been laid, should be taken up, and a connection made with a sewer to carry the water accumulating from a spring supplying an old well, away from the-building. By making that connection and restoring and adding to the work, the cellar was finally made dry, and the object the parties had in view was accomplished. It might very well have been done -before, for the remains of the well were to be, and were, seen. Aiid there was reason for asserting that the [175]*175plaintiffs were in fault in the performance of their work, for failing to provide an avenue for the escape of the water before they proceeded to lay the bottom they placed upon the cellar.

For this additional work and material, the plaintiffs charged the further sum of $490.17. But the right to recover it was resisted by the defendant for the alleged reason that it was necessary to complete the performance of the agreement as it had been made by the parties. And the jury seems to have adopted this view for this charge appears to have formed no part of the verdict.

But the defense made was not fully disposed of by rejecting this charge.

The defendant had been excluded from the occupancy and use of his dwelling by -the condition in which the cellar remained after the work done in 1874 had been completed, and during the time also which was consumed in connecting the cellar with the sewer, and again completing the work in the Summer and Fall of 1875. And for that, he claimed he should be recompensed by the verdict in this action. And the court held him to be entitled to that right, if his remedy for its redress had not been lost by the application of the statute of limitations.

Under that statute, it was considered requisite that his claim for the allowance of damages should be made by the service of an answer in the action presenting it as a counter-claim within the period of six years from the time when it accrued. And the jury were directed to allow it if that time had not expired when the answer containing it as a counterclaim was served, but to reject it if the answer was not in fact served before this period of six years had expired.

The effect of this ruling was to continue the application of the statute until the actual service of the defendant’s answer. And that ruling, while it defeated [176]*176the counter-claim, would probably have been strictly accurate if the counter-claim had been an independent cause of action, unconnected with the cause of action itself relied upon by the plaintiffs. But it was not, for the right to damages arose out of the partial failure of the plaintiffs to perform the contract which was the foundation of their own right to recover, for the rendition and acceptance of the account, did not exclude the contract and its terms from the controversy. They were still pertinent and important to the claims of both parties to the action. And if the contract was still continued unaffected by the statute of limitations as to the plaintiffs, it would seem to follow, that it must be in like condition as to the defendant. If it measured the obligations of the defendant, it had the same effect upon those of the plaintiffs. If they were not barred, it was because the contract still remained in force when they commenced their suit.

As they had performed it, their action was to be maintained or defeated. They could only insist upon their right to remuneration as they had performed their agreement. If that were a qualified or defective performance, then the defendant had the right to rely on the qualification or defect. Whatever it was, it was carried along with the contract, and to the extent that it existed, it would defeat the demand made by the plaintiffs for compensation for this work. It was an infirmity affecting the plaintiffs’ rights under the contract, as long as they were in a condition to be asserted. And if the statute of limitations did not defeat their remedy, it equally left the other unaffected, to which the defendant was entitled, for their failure to perform an integral part of the same agreement. If it was preserved in part, it was preserved as a whole, and it continued to be the measure of all the rights and remedies of the parties.

The statute itself contains no provision requiring any [177]*177different construction. It simply prescribes the time when the action itself must be commenced, without imposing any limit whatever on the time within which, in the same action, the defendant is to be restricted to the presentation of his counterclaim for a breach of the same agrément by the plaintiffs. If it had been intended to subject that to any other restriction than that within which it has been provided the answer shall be served, some positive evidence of that intention would have found expression in the law. That has been omitted, and the omission itself evinces the design that no distinction should be made between the right to enforce the several parts of an entire contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooley Trading Co. v. Goetz
247 A.D. 607 (Appellate Division of the Supreme Court of New York, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
15 Abb. N. Cas. 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herbert-v-dey-nysupct-1884.