Herbert Shaffer Assoc., Inc. v. First Bank of Oak Park

332 N.E.2d 703, 30 Ill. App. 3d 647, 1975 Ill. App. LEXIS 2669
CourtAppellate Court of Illinois
DecidedJuly 17, 1975
Docket60391
StatusPublished
Cited by26 cases

This text of 332 N.E.2d 703 (Herbert Shaffer Assoc., Inc. v. First Bank of Oak Park) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herbert Shaffer Assoc., Inc. v. First Bank of Oak Park, 332 N.E.2d 703, 30 Ill. App. 3d 647, 1975 Ill. App. LEXIS 2669 (Ill. Ct. App. 1975).

Opinion

Mr. JUSTICE McNAMARA

delivered the opinion of the court:

Plaintiff, Herbert Shaffer Associates, Inc., filed suit in the circuit court of Cook County to foreclose a mechanic’s lien for architectural services expended by it in connection with work on a dwelling project in the City of Chicago. Defendants were the legal owner of the property, First Bank of Oak Park, as trustee, and the beneficial owner of the property, Michael Stein. Defendants counterclaimed for a refund of part of the money already paid to plaintiff, alleging that they had overpaid plaintiff on the basis of work completed by it. At the close of all the evidence, the trial court, as trier of fact, entered judgment for plaintiff, assessed damages in the amount of $6,340.32, and dismissed the counterclaim.

Although the voluminous record contains scores of exhibits, the case actually revolves upon the construction of a standard, written architect’s contract. It was plaintiff’s position at trial that pursuant to that document it was entitled to compensation for work done up to the time defendants terminated the contract. Defendants maintained that they had never terminated the contract and that plaintiff had been overpaid. The pertinent facts are as follows.

The parties entered into a written contract for services on December 17, 1970, although they had been working on an oral agreement since earlier in that year. As stated in the contract, the owners’ intention was to erect “a multiple dwelling building consisting of approximately thirty-seven units located on four stories” at 732-46 Gordon Terrace in Chicago. The contract specified that plaintiff was to prepare drawings for various phases of development of the project. These drawings were to consist of schematic design studies, design development drawings, and working (construction) documents. The manner in which plaintiff was to be compensated for its services is outlined in paragraph II of the contract. In pertinent part that provision reads as follows:

“a. FOR THE ARCHITECT’S BASIC AND ADDITIONAL SERVICES, * * * compensation computed as follows:
Principals’ time at the fixed rate of Twenty-Five dollars ($25.00) per hour. * * *
Employees’ time computed at a multiple of two & one-half (2%) times the employees’ Direct Personnel Expense as defined in Article 4.
Services of professional consultants at a multiple of one and one-quarter (PA) times the amount billed to the Architect for such services.
ft ft ft
c. FOR THE ARCHITECT’S REIMBURSABLE EXPENSES, amounts expended as defined in Article 5.
d. THE TIMES AND FURTHER CONDITIONS OF PAYMENT shall be as described in Article 6 and as follows:
Compensation for BASIC SERVICES shall be limited to a total of $15,000.00 and shall be due and payable according to the following Schedule of Payment:
On Completion of the Schematic & Design Development Phases:
One Thousand Dollars ($1,000.00)
On Completion of the Construction Documents:
Five Thousand, Five Hundred Dollars ($5,500.00)
During Construction Phase, on reaching roof level, the remainder of the compensation, not to exceed
Eight Thousand, Five Hundred Dollars ($8,500.00) Compensation for ADDITIONAL SERVICES to be made monthly.
The above Schedule of Payments shall not be applicable under the conditions described in Article 5, paragraph 6.3 hereinafter.”

Melvin Kantor, a licensed architect and associate in plaintiff’s firm, enjoyed both a business and social relationship with Stein at the time the latter approached him in early 1970 to relate his interest in erecting a high-rise, multiple-unit dwelling on the subject property. A meeting was arranged in February at plaintiff’s offices, attended by Kantor, Stein, and Herbert Shaffer, plaintiff’s president. As a result of that and subsequent meetings, Stein engaged plaintiff on a fee basis to prepare some preliminary studies on the economic feasibility of Stem’s plan. Sometime between March 13 and 19, plaintiff presented its analysis of the plan, and Stein determined his proposal was economically unfeasible. Stein then instructed plaintiff to study the feasibility of a low-rise dwelling of 37 units. Later in March, Kantor informed Stein that a zoning variation would have to be obtained in respect to the location of the building on the site. Stein replied that zoning would be no problem, that he would secure the zoning change, and that plaintiff should proceed with the preparation of the preliminary designs on the operating premise that the variation had already been secured.

Kantor further testified that the sketches and drawings prepared under his supervision concerning the project were continually being modified and revised by Stein or his financial backers. Stein would appear at plaintiff’s office frequently and observe the work being done. Reproductions of the preliminary plans were continually being mailed or given to Stein or his representatives. On October 20, 1970, Kantor appeared and testified on defendants’ behalf before the Zoning Board of Appeals. The variation request was denied.

Plaintiff continued to work on the project. On February 6, 1971, a final definitive design plan for the project was complete and was forwarded by transmittal letters dated February 7 and 9. On February 18, Kantor sent Stein a letter verifying that the plans submitted were final. His reason for sending the letter was to prevent further changes by Stein.

Kantor then directed Ronald Ringman, another licensed architect and associate in plaintiff’s firm, to begin preparation of working drawings. Stein had asked to have those drawings prepared as soon as possible. Under Kantor’s supervision, Ringman prepared definitive working drawing sketches of the project between February 15 and March 5 in connection with the preparation of final working drawings. At the time Stein ordered the work stopped on March 12, the final working drawings were at an incomplete stage.

On cross-examination, Kantor testified that the stage of completion of the working drawings at the time work was stopped could not properly be characterized as partial, although he conceded that a substantial amount of work still remained before they could be considered completed. Kantor further testified that on March 10, 1971, he became aware of certain proposed zoning amendments that would directly affect the project so as to necessitate a variation or a substantial change in the plans.

Ronald Ringman, the principal draftsman of the working drawings, testified that to a certain degree the preliminary and working drawings bear similarities. He noted that substantial progress can be made in the preparation of working drawings without a final preliminary drawing and without final structural calculations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PQ Corp. v. Lexington Insurance Co.
860 F.3d 1026 (Seventh Circuit, 2017)
Perez v. McDonald's Corp.
60 F. Supp. 2d 1030 (E.D. California, 1998)
Davis v. McDonald's Corp.
44 F. Supp. 2d 1251 (N.D. Florida, 1998)
Derby Meadows Utility Co. v. Inter-Continental Real Estate
559 N.E.2d 986 (Appellate Court of Illinois, 1990)
Sahadi v. Continental Illinois National Bank
706 F.2d 193 (Seventh Circuit, 1983)
Country Service & Supply Co. v. Harris Trust & Savings Bank
430 N.E.2d 631 (Appellate Court of Illinois, 1981)
URS Corp. v. Ash
427 N.E.2d 1295 (Appellate Court of Illinois, 1981)
C. G. Caster Co. v. Regan
410 N.E.2d 422 (Appellate Court of Illinois, 1980)
Maloney v. Maloney
410 N.E.2d 316 (Appellate Court of Illinois, 1980)
Ricke v. Ricke
405 N.E.2d 351 (Appellate Court of Illinois, 1980)
AZL Resources, Inc. v. Bromagen
398 N.E.2d 292 (Appellate Court of Illinois, 1979)
National Aircraft Leasing, Ltd. v. American Airlines, Inc.
394 N.E.2d 470 (Appellate Court of Illinois, 1979)
Epstein v. Yoder
391 N.E.2d 432 (Appellate Court of Illinois, 1979)
Halper v. Halper
373 N.E.2d 598 (Appellate Court of Illinois, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
332 N.E.2d 703, 30 Ill. App. 3d 647, 1975 Ill. App. LEXIS 2669, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herbert-shaffer-assoc-inc-v-first-bank-of-oak-park-illappct-1975.