Herbert M. Baruch Corp. v. United States

92 Ct. Cl. 571, 1941 U.S. Ct. Cl. LEXIS 155, 1941 WL 4594
CourtUnited States Court of Claims
DecidedJanuary 6, 1941
DocketNo. 43142
StatusPublished

This text of 92 Ct. Cl. 571 (Herbert M. Baruch Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herbert M. Baruch Corp. v. United States, 92 Ct. Cl. 571, 1941 U.S. Ct. Cl. LEXIS 155, 1941 WL 4594 (cc 1941).

Opinion

Green, Judge,

delivered the opinion of the court:

On October 13, 1932, the plaintiff entered into a contract with the United States whereby, for a consideration of $52,150, plaintiff agreed to furnish all labor and materials and perform all work required for the construction of a Post Office at Bingham Canyon, Utah, in accordance with the specifications, schedules and drawings made a part of the contract. The contract provided that the work should be commenced as soon as practicable after the date of receipt of notice to proceed, and should be completed within 360 calendar days after the receipt of such notice.

On November 11, 1932, plaintiff received notice to proceed with the work. The date for completion was subsequently extended until December 5, 1933 became the date for completion.

The contract provided that the work should be performed under the supervision of the defendant’s construction engineer, who arrived at the location the latter part of November 1932, and at which time the work was commenced. The building was substantially completed in December 1933 and turned over to the Government on December 20, 1933. From and after January 1, 1934, the building was occupied by the defendant and no more work was performed' by the plaintiff.

The plaintiff seeks to recover on four items of alleged damages. The first of these items is the increased costs of excavating material of a rock-like nature. This excavating was done for the placing of foundations and for that purpose a power shovel was placed on the premises. Paragraph 66 of the specifications attached to the contract specified the extent of the excavations. Paragraphs 67 and 68 of the specifications read as follows:

67. The basis of bidding shall be that all other material to be removed is earth. Material. which it is practicable to remove and handle with pick and shovel or by hand or to loosen and remove with a power shovel shall be classed as earth.
68. If excavation of other materials becomes necessary the additional expense will be determined by the contracting officer.

[584]*584The findings sKow that excavation was done in tbe winter when the ground was frozen, the freezing extending downward to approximately three feet below the surface. They further show that 2,480 cubic yards consisted of boulders, dirt, natural debris, timbers, and junk, dumped there in the process of back-filling voids left in gold-mining operations or in the abandonment of old flumes. This heterogeneous material was frozen together and could not be removed without blasting.

The plaintiff wrote a letter to the Supervising Architect, January 23, 1933, describing the situation, quite particularly as shown in Finding 6, and asking an increase in the contract-price for this excavation. Several communications passed between the Supervising Architect and the plaintiff. The Supervising Architect finally notified the plaintiff that a report of the construction engineer did not bear out the contention that solid rock was encountered or that any of the material could not be loosened without a pick or power shovel, and this decision was affirmed on appeal to the Secretary of the Treasury.

The defendant relies largely on Article 15 of the contract which reads as follows:

Disputes. — Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within thirty days to the head of the department concerned, whose decision, shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as ' directed.

The defendant also says that the plaintiff was slow in commencing the work and in its prosecution, but that the ground was frozen about December 1st and remained so frozen to an approximate depth of three feet until the following first of April. The delay on the part of the defendant in sending its construction engineer to the work prevented any substantial amount of the work being done until after the first of December, when the ground was frozen. Even if the work had not been delayed it would not have been practicable to [585]*585remove with pick and shovel, or power shovel, the material encountered as above described.

The defendant contends that the character of the material to be removed is a question of fact and that the decision of the contracting officer thereon, subject to appeal, was final. If this was a matter as to which there was some doubt' this would be true, but it is clear that when the definition of “earth”, set out in specification 67, is considered, the holding of the contracting officer with reference to the material which plaintiff encountered is grossly erroneous and shows such bias and prejudice as to be purely arbitrary and to imply bad faith. We are therefore justified in disregarding his decision under the repeated holdings of this court. It would not be “practicable” to remove such material in the manner described in the specifications even if the ground had not been frozen, and the evidence shows that it was not the fault of plaintiff that the work had not been commenced earlier and finished before freezing weather set in.

The contract provided that the defendant might make changes in the work required, but as was said in Rust Engineering Co. v. United States, 86 C. Cls. 461 (a case in which the facts were quite similar and exactly the same provisions were in the contract), this does not prevent recovery for changes based upon conditions which are unknown and materially different from anything contemplated by the parties when the contract was executed. See also Maurice H. Sobel v. United States, 88 C. Cls. 149, and Stapleton Construction Co. v. United States, No. 48527, decided December 2,1940.

We think it is satisfactorily shown that the plaintiff has a just claim for the excavation of material which could not be classed as “earth” under Specification 67. The testimony as to the additional cost of removing this material consists of cost sheets of plaintiff which were introduced in connection with oral testimony as to the nature of the material, and plaintiff’s president testified that the amount which was claimed was the actual additional cost over the cost of removing earth. Moreover, in the extensive correspondence had between the parties the defendant made no defense based upon the value of the work. The claim was denied solely on the ground that the material was not of the nature [586]*586claimed by plaintiff, which, as we have said above, is grossly erroneous and directly contrary to the uncontroverted evidence. We find that the plaintiff is entitled to recover additional compensation for 2,430 cubic yards at $1.25 per yard, or $8,037.50.

Plaintiff also claims damages by reason of the alleged delay by defendant in reaching a decision on the footings and foundation changes, also for the additional work in relation thereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rust Engineering Co. v. United States
86 Ct. Cl. 461 (Court of Claims, 1938)
Sobel v. United States
88 Ct. Cl. 149 (Court of Claims, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
92 Ct. Cl. 571, 1941 U.S. Ct. Cl. LEXIS 155, 1941 WL 4594, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herbert-m-baruch-corp-v-united-states-cc-1941.