Herberg v. Swartz

578 P.2d 17, 89 Wash. 2d 916, 1978 Wash. LEXIS 1390
CourtWashington Supreme Court
DecidedApril 13, 1978
Docket44851
StatusPublished
Cited by59 cases

This text of 578 P.2d 17 (Herberg v. Swartz) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herberg v. Swartz, 578 P.2d 17, 89 Wash. 2d 916, 1978 Wash. LEXIS 1390 (Wash. 1978).

Opinion

Stafford, J.

Appellant Real Estate Consultants, Inc., appeals a judgment entered on a jury verdict in two actions which were consolidated for trial. We affirm.

Appellant purchased the Chieftain Hotel in August of 1973. On October 19, 1973, the hotel was inspected for compliance with the state's minimum fire and life safety standards for transient accommodations. Although approximately 23 state fire code violations were discovered, appellant was given 5 1/2 months to correct them.

Two months later, on December 19, 1973, an arson fire was started on the hotel's first floor. At this time most of the fire code deficiencies were still uncorrected. Appellant notified the City of Yakima (City) fire department sometime in the midafternoon and evacuated all tenants. Before the fire department could arrive the fire had spread throughout the hotel. The fire's rapid spread was caused by at least five, and potentially by twenty, of the uncorrected *919 fire code deficiencies. One serious deficiency in particular, open pipe chases which ran vertically and horizontally throughout the building, accelerated and spread the fire, acting as a series of open chimney flues.

That evening the fire mushroomed from the pipe chases into the attic, causing the roof to collapse. Thereafter efforts to suppress the fire were limited to the exterior of the building.

The fire continued to burn throughout the evening and into that night. At 3 a.m. on December 20, the east wall collapsed. By the afternoon of December 20, the fire was creating such a hazard that the City determined demolition of the remaining walls was necessary. Consequently, appellant engaged Carrell Trucking (Carrell) to reduce the walls to a safe level. 1

Carrell arrived with the demolition equipment that evening and worked on the south wall until 10 or 11 p.m. at which time inadequate visibility prevented further demolition efforts. That night the fire destroyed the supporting structure of the remaining walls. The next morning, December 21, Carrell resumed demolition efforts. However, Carrell discontinued all but standby work at noon following a disagreement with appellant concerning liability coverage to protect Carrell. After 8 hours of negotiation, Carrell and appellant executed a written contract to indemnify Carrell. 2 Thereafter, Carrell resumed full demolition efforts on the west wall. By that time the fire had burned in excess *920 of 50 hours. After ravaging the hotel the fire was eventually contained.

After Carrell had demolished the west wall, only the north wall and the centrally-located elevator shaft remained standing. As Carrell began demolition of the elevator shaft, the crane's cable became entangled. During efforts to extricate the cable from the shaft, the north wall collapsed and fell on the adjoining store owned by respondent Herberg.

In one action respondent tenants sued appellant for loss of their personal property. Appellant asserted a common-law claim for indemnity against the City based upon the City's alleged active negligence in its fire fighting procedures and its failure to contain the fire.

In a second action respondent Herberg sued appellant and Carrell alleging negligence. Appellant, in turn, asserted common-law indemnity claims against both the City and Carrell. Carrell thereafter asserted its written contract of *921 indemnity against appellant and also sought common-law indemnity from the City.

The two actions were consolidated for trial. Prior to trial, the court entered a summary judgment that the written indemnity contract between Carrell and appellant was supported by consideration. The court also granted a summary judgment that appellant was negligent per se for operating the hotel in violation of RCW 70.62. On the day of trial, but prior to the presentation of evidence, Carrell's motion to dismiss appellant's common-law indemnity claim was granted. Thereafter, Herberg took a voluntary nonsuit in his action against Carrell.

During trial, and in response to respondents' motions to exclude evidence of the superseding or intervening negligence of the City and Carrell, appellant's common-law indemnity claim against the City was dismissed and the evidence was excluded. With all claims against the City and Carrell having been dismissed, settled, or nonsuited, the consolidated actions were submitted to the jury with appellant as the sole defendant.

The jury returned verdicts for both respondent hotel tenants and respondent Herberg. The court entered judgment on the verdicts and later denied appellant's motions for judgment n.o.v. or for a new trial. The Court of Appeals certified the appeal to this court.

Appellant assigns error to the following actions of the trial court: (1) granting summary judgment that appellant was negligent per se; (2) dismissing appellant's indemnity claim against the City; (3) enforcing the indemnity agreement between Carrell and appellant; (4) excluding evidence of alleged superseding or intervening negligence of the City and Carrell; (5) improperly instructing the jury on proximate causation and apportionment of liability; and (6) failing to strike the tenants' damage testimony and incorrectly instructing the jury on this issue. Appellant also urges us to adopt a rule that will permit contribution, or apportionment of liability among tort-feasors.

*922 We turn first to the determination that appellant was negligent per se for operating the hotel in violation of the minimum fire and life safety standards promulgated under the Transient Accommodations Act, RCW 70.62.290. Appellant asserts that its duties to the tenants and to Her-berg should have been tested by the common-law standards of sections 343, 353, 364 and 366 of the Restatement (Second) of Torts (1965). It is argued that under those sections the reasonableness of appellant's actions during the 2 months preceding the fire would have presented a question of material fact. Thus, appellant urges, summary judgment was inappropriate. We disagree.

The concept of negligence per se permits a court to substitute legislatively required standards of conduct for lesser common-law standards of reasonableness. Bayne v. Todd Shipyards Corp., 88 Wn.2d 917, 568 P.2d 771 (1977); Kness v. Truck Trailer Equip. Co., 81 Wn.2d 251, 501 P.2d 285 (1972); Restatement (Second) of Torts § 286 (1965). As W. Prosser in Law of Torts § 36 (4th ed. 1971) states at page 190:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Of Washington, V. Malcolm Otha Mcgee
530 P.3d 211 (Court of Appeals of Washington, 2023)
Adelina Gabriela Suarez v. State of Washington
Court of Appeals of Washington, 2022
Rebecca West, V. Ride The Ducks International, Llc
Court of Appeals of Washington, 2021
Carlton Evans & Margaret Evans v. Spokane County
Court of Appeals of Washington, 2020
Zenaida Montoya, V Bank Of America, Etal
Court of Appeals of Washington, 2016
East Valley School District No. 90 v. Taylor
295 P.3d 1224 (Court of Appeals of Washington, 2013)
East Valley School District No. 90 v. Michele Taylor
Court of Appeals of Washington, 2013
Olson Engineering, Inc. v. KeyBank National Ass'n
286 P.3d 390 (Court of Appeals of Washington, 2012)
Council House, Inc. v. Hawk
147 P.3d 1305 (Court of Appeals of Washington, 2006)
Paxton v. City of Bellingham
129 Wash. App. 439 (Court of Appeals of Washington, 2005)
Cotton v. Kronenberg
111 Wash. App. 258 (Court of Appeals of Washington, 2002)
Tyner v. Department of Social & Health Services
1 P.3d 1148 (Washington Supreme Court, 2000)
Tyner v. DSHS, Child Protective Serv.
1 P.3d 1148 (Washington Supreme Court, 2000)
BETTY Y. v. Al-Hellou
988 P.2d 1031 (Court of Appeals of Washington, 1999)
Phillips v. King County
943 P.2d 306 (Court of Appeals of Washington, 1997)
Nelson v. McClatchy Newspapers, Inc.
931 P.2d 870 (Washington Supreme Court, 1997)
Landers v. Municipality of Anchorage
915 P.2d 614 (Alaska Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
578 P.2d 17, 89 Wash. 2d 916, 1978 Wash. LEXIS 1390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herberg-v-swartz-wash-1978.