Hepding v. Debra Corp.

255 A.2d 352, 254 Md. 641, 1969 Md. LEXIS 906
CourtCourt of Appeals of Maryland
DecidedJuly 10, 1969
DocketNo. 311
StatusPublished

This text of 255 A.2d 352 (Hepding v. Debra Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hepding v. Debra Corp., 255 A.2d 352, 254 Md. 641, 1969 Md. LEXIS 906 (Md. 1969).

Opinion

Barnes, J.,

delivered the opinion of the Court.

This appeal presents to us the question of whether or not the trial court (Mayfield, J.) was clearly in error in declining to disallow certain items claimed by the builder, The Debra Corporation (Debra), appellee in this Court and plaintiff in the trial court, in a suit to enforce a mechanics’ lien asserted by Debra against the land and dwelling of the appellants, James A. Hepding and Ann M. Hepding, his wife, who were defendants below. There are no questions presented in regard to the form of the mechanics’ lien asserted by Debra, the description of the property or the proper giving of the required notice to assert the lien. There is no contention that the work was defective.

In the early part of July 1966, Debra, through its president, Raymond W. Griffith, and the Hepdings entered into an oral contract whereby Debra was to construct a dwelling for the Hepdings on a lot containing 21,600 square feet, known as 3 Allview Drive, Simpsonville, Howard County. Mrs. Hepding had prepared a sketch of the proposed construction which was used by an architect [643]*643to prepare the plans. There was no total cost figure agreed upon, although Mr. Hepding testified that he did not want the total cost of the dwelling to exceed $30,000. Mr. Griffith testified that the figure of $30,000 was mentioned when the oral contract was made but that the figure was “an estimate.” Debra was to supervise the construction and was to receive a $2,000 “supervision fee” as its profit on the project. The estimated time for the completion of the work was ninety days. The Hepdings agreed to pay the bills for labor and materials used in the construction when presented to the office of the attorney for the Hepdings. All disbursements were to be made from that office but only upon the prior approval of Mr. Hepding.

This method of billing and disbursement continued for a while, but eventually Mr. Hepding authorized the secretary to his counsel to make disbursements without having received or seen any bills. The secretary testified that the Hepdings placed approximately $37,000 in her hands for disbursement for the construction costs. When approximately $23,000 had been disbursed she told Mr. Griffith that she needed bills to support the previous payments at which time Mr. Griffith had brought her “a stack of bills.” At one time during the construction, Mrs. Hepding had expressed concern in regard to the rising costs of the dwelling, but no maximum cost figure was ever established.

The dwelling in question is a stone ranch-type home with three bedrooms, three bathrooms, a living room, dining room, kitchen, den, porch and garage all on the first floor, with a family room, laundry, powder room, bar, utility and storage rooms in the basement or lower floor, part of which is unexcavated. The photographs of the completed home indicate that it is well-built, with a modern kitchen, and that it generally has superior appointments for this type of house. The testimony indicated that from time to time there were changes in the plans for certain interior construction which increased the cost of construction and delayed the completion of the work. [644]*644Construction began on July 21, 1966 and was not completed until some time in April of 1967, a period of approximately nine months instead of the estimated three months.

The final bill submitted by Debra to the Hepdings on May 1,1967, was as follows:

“Balance brought forward ................ $22,196.81 (total of invoices presented to Mr. and Mrs. Hepding for payment prior to presentation of the final bill)

Materials and Miscellaneous ............ $ 8,269.09 (all presented for the first time in the final bill)

Labor .................................................. $14,076.60

$44,542.50

Payments received............................ —37,399.51

Sub-balance ........................................ $ 7,142.99

Bookkeeping Expenses .................... 450.00

Profit per agreement ........................ 2,000.00

Charge for additions and changes.... 1,000.00

Balance due ........................................ $10,592.99”

The mechanics’ lien asserted by Debra is for the claimed balance of $10,592.99.

Included in the item of $8,269.09 marked “Materials and Miscellaneous” are the following charges:

1. Rental of Trucks, Loaders, Backhoes $ 3,277.00

2. Lee Rose and Truck (“hauling”) 247.00

3. Lee Rose (Supervision) 800.00

The item of $14,076.60 for labor includes the charges:

1. Carpenters (Rough and Finish) $12,639.10

2. Common Labor 1,257.50

3. Sam Moore, additional job 180.00

Total.................... $14,076.60

[645]*645In explanation of the first mentioned charge for carpenter labor of $12,939.10, Mr. Griffith itemized it as made up of the labor of three carpenters and an item of carpentry work of $492.00 for a subcontractor, B & I Construction Company, as follows:

1. James Barrick (9811/2 hrs. at $4.50 an hour) $4,416.75

2. Frank Cameron (847 hrs. at $2.50 an hour) 2,117.50

3. Jack Johnson (885 hrs. at $3.00 an hour) 2,655.00

4. Subcontractors 492.00

Total............... $9,681.25

The total given by Mr. Griffith was $9,680.17, representing a slight error in calculation. The correct difference between the $12,639.10 figure given for carpenter labor and the amount of $9,681.25 is $2,957.85. Mr. Griffith indicated that the difference was $2,958.93 (reflecting the error in addition mentioned). Mr. Griffith acknowledged that this was an overcharge. His testimony was:

“Q. So there’s twenty-nine hundred and fifty-eight dollars and ninety-three cents ($2958.-93) in carpenters, assuming what you say so far is correct, that that would be out.
Isn’t that correct?
“A. That’s right.”

Jacob Schwartz, a part time accountant, who made up the payroll records, including the withholding tax records, for Debra, testified that the information in regard to the time spent by the carpenters on the Hep ding job as well as the amount of time for the equipment was telephoned in to him at the end of each week by Mr. Bar-rick, or in some instances by Lee Rose. Based on that in[646]*646formation Mr. Schwartz issued the pay checks and made up the payroll records.

Mr. Barrick, called by the Hepdings as a witness, testified that he did the principal part of the carpentry work on the Hepding dwelling and he kept a daily record of the time he had spent working on the Hepding dwelling. His records indicated that he had spent 720% hours on the job at $4.50 an hour or a total of $3,242.25 (versus 981% hours and a charge of $4,416.75 claimed by Debra). He also testified that he was on the job every day from November 1966 to March 1967 and that Mr. Johnson during that period only spent approximately two weeks on the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goodwin v. Lumbermens Mutual Casualty Co.
85 A.2d 759 (Court of Appeals of Maryland, 1970)
Burroughs International Co. v. Datronics Engineers, Inc.
255 A.2d 341 (Court of Appeals of Maryland, 1969)
Mayor of Baltimore v. Sitnick
255 A.2d 376 (Court of Appeals of Maryland, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
255 A.2d 352, 254 Md. 641, 1969 Md. LEXIS 906, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hepding-v-debra-corp-md-1969.