Hensel Phelps Construction Co. v. Dept. of Corrections and Rehab.

CourtCalifornia Court of Appeal
DecidedFebruary 25, 2020
DocketB293427
StatusPublished

This text of Hensel Phelps Construction Co. v. Dept. of Corrections and Rehab. (Hensel Phelps Construction Co. v. Dept. of Corrections and Rehab.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hensel Phelps Construction Co. v. Dept. of Corrections and Rehab., (Cal. Ct. App. 2020).

Opinion

Filed 1/28/20; Certified for publication 2/25/20 (order attached)

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION FIVE

HENSEL PHELPS B293427 CONSTRUCTION COMPANY, (Los Angeles County Plaintiff and Respondent, Super. Ct. No. BC630469)

v.

DEPARTMENT OF CORRECTIONS AND REHABILITATION,

Defendant and Appellant.

APPEAL from a judgment of the Superior Court of Los Angeles County, Susan Bryant-Deason, Judge. Affirmed in part, reversed in part and remanded with direction. Xavier Becerra, Attorney General, Thomas S. Patterson, Senior Assistant Attorney General, Tamar Pachter and Jose A. Zelidon-Zepeda, Deputy Attorneys General, for Defendant and Appellant. Watt, Tieder, Hoffar & Fitzgerald, David F. McPherson and Robert C. Shaia for Plaintiff and Respondent. Plaintiff Hensel Phelps Construction Company (Phelps) was the low bidder on a public works contract awarded by the California Department of Corrections and Rehabilitation (CDCR) through competitive bidding, and commenced work on the project. Another bidder challenged the award of the contract to Phelps, and was successful, obtaining a ruling in a San Diego trial court that Phelps’s bid was “non-responsive as a matter of law” due to its inclusion of “non-waivable mathematical/typographical errors.” Phelps then brought suit against CDCR, seeking to recover the costs it expended on the project, under a statute which allows for such relief only if the contract is “determined to be invalid due to a defect or defects in the competitive bidding process caused solely by the public entity.” (Pub. Contract Code, § 5110, italics added.)1 CDCR sought judgment on the pleadings, arguing that the San Diego trial court’s determination that the contract was invalid because Phelps’s bid was non-responsive as a matter of law precluded recovery. The trial court disagreed, held a bench trial, and concluded that the San Diego trial court’s ruling was itself the result of a defect in the competitive bidding process caused solely by CDCR. Judgment was entered in favor of Phelps. On CDCR’s appeal, we reverse, concluding judgment on the pleadings should have been granted. However, we affirm the trial court’s denial of recovery on CDCR’s cross-complaint for disgorgement.

1 All undesignated statutory references are to the Public Contract Code.

2 FACTUAL AND PROCEDURAL BACKGROUND 1. The Award of the Contract to Phelps On March 17, 2015, CDCR issued an Invitation for Bid for the Ironwood State Prison Heating, Ventilation and Air Conditioning System – a project which was estimated to cost around $100,000,000. The deadline to submit bids was April 30, 2015 at 2:00 p.m. Phelps submitted its bid on time. The bids were opened, and Phelps was determined to be the “apparent low bidder” with a price of $88,160,000. On May 1, 2015, Phelps submitted an “amended bidder declaration.” The April 30 bid had included a bidder declaration containing information pertaining to subcontractors Phelps intended to use on the project. Among other things, the original bid declaration had indicated the percentage of the contract work to be done by each subcontractor; the amended bidder declaration changed these subcontractor percentages. Phelps believed it was permitted to submit its amended bidder declaration on May 1. During the bid process, prospective bidders had submitted questions to CDCR, which it answered in writing via amendments to the invitation to bid; in this way, all of the prospective bidders had access to the same information. It is undisputed that CDCR had issued an amendment containing a question and answer which permitted bidders to supply certain subcontractor information 24 hours after the bid deadline (the “Q24 answer”). What was disputed was whether the information that could be submitted a day late included the subcontractor percentages.2

2 Phelps’s witness testified that allowing it to submit subcontractor percentages after the bid deadline enabled it to

3 CDCR took the position that subcontractor percentages could not, in fact, be changed by amended bidder declaration. It rejected Phelps’s May 1, 2015 submission, and ultimately mailed it back to Phelps. Phelps was not immediately informed of the rejection, however. In the meantime, on May 6, West Coast Air Conditioning Company, the second-lowest bidder, sent CDCR a complaint letter regarding Phelps’s bid. CDCR did not review it, believing that it had no jurisdiction to hear bid protests. Phelps was informed on May 13, 2015 that its May 1, 2015 amended bidder declaration was rejected. That same day, CDCR issued a notice of intent to award the project to Phelps. Phelps executed the contract on May 18, 2015. The Phelps vice- president who signed the contract testified that, when he did so, he understood that CDCR had rejected the May 1 submission. Nonetheless, he signed the contract, based on the April 30 bid alone, believing that the incorrect subcontractor percentages in the April 30 bidder declaration constituted an “immaterial deviation” which could be waived by CDCR. 2. The San Diego Proceedings Commence On May 22, 2015, West Coast filed a petition for writ of mandate in the San Diego Superior Court seeking to invalidate the contract and prohibit Phelps from constructing the project.

obtain the best possible deal from its subcontractors, and therefore submit the best price it could for the project. That is, its subcontractors were permitted to wait until just before the bid deadline to submit their best prices to Phelps. Phelps incorporated those prices into its bottom line total bid price, but did not have time to update the math in its calculation of the percentages in its bidder declaration by the deadline.

4 In that proceeding, CDCR was the respondent and Phelps was the real party in interest. 3. Construction Begins As we shall discuss, section 5110 provides that when the award of a public contract is challenged, the contract may be entered into pending final decision of the challenge. On July 3, 2015, CDCR executed the contract. On July 7, 2015, it issued a notice to proceed to Phelps. That day, Phelps began work on the project. While the San Diego court proceedings were ongoing, Phelps continued to work on the project. The parties stipulated that CDCR approved and paid Phelps’s first three pay applications, in the total amount of $3,510,180.64. 4. The San Diego Court Invalidates the Contract On September 11, 2015, the San Diego court issued its minute order on West Coast’s mandamus cause of action. The order explained that West Coast sought to have the award of the contract to Phelps set aside for two reasons: (1) Phelps’s bid was non-responsive because it failed to list license numbers for its subcontractors; and (2) Phelps’s bid “contained numerous arithmetical/typographical mistakes which required CDCR to reject [Phelps]’s bid as non-responsive because of these admitted errors which, according to West Coast, afforded [Phelps] a competitive advantage.” The court explained that errors which might otherwise render a bid non-responsive, requiring rejection of the bid, can be waived only if they could not have affected the price and could not have resulted in an advantage or benefit not allowed other bidders. Under this standard, the San Diego court concluded the first error – the failure to list license numbers – was waivable and therefore immaterial. The second error,

5 however, was not. The court stated that it was “undisputed that the [Phelps] bid contained mathematical errors.” Phelps “argues that the errors were not material and . . . that, in essence, the defects could be waived.” The court disagreed, finding that the changes encompassed not only “immaterial percentages” but “certain subcontractor price amounts.” It held these changes material and, therefore, not waivable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blank v. Kirwan
703 P.2d 58 (California Supreme Court, 1985)
Miller v. McKinnon
124 P.2d 34 (California Supreme Court, 1942)
Castillo v. City of Los Angeles
111 Cal. Rptr. 2d 870 (California Court of Appeal, 2001)
Marshall v. Pasadena Unified School District
15 Cal. Rptr. 3d 344 (California Court of Appeal, 2004)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
EEL River Disposal & Resource Recovery Inc. v. County of Humboldt
221 Cal. App. 4th 209 (California Court of Appeal, 2013)
W. Coast Air Conditioning Co. v. Cal. Dep't of Corr. & Rehab.
230 Cal. Rptr. 3d 458 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Hensel Phelps Construction Co. v. Dept. of Corrections and Rehab., Counsel Stack Legal Research, https://law.counselstack.com/opinion/hensel-phelps-construction-co-v-dept-of-corrections-and-rehab-calctapp-2020.