Henry v. Hinds

18 Mo. App. 497, 1885 Mo. App. LEXIS 369
CourtMissouri Court of Appeals
DecidedJune 15, 1885
StatusPublished
Cited by6 cases

This text of 18 Mo. App. 497 (Henry v. Hinds) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry v. Hinds, 18 Mo. App. 497, 1885 Mo. App. LEXIS 369 (Mo. Ct. App. 1885).

Opinion

Opinion by

Philips, P. J.

1. It is insisted by appellant (defendant below) that the court erred in refusing the sixth instruction asked by her. This instruction announced a correct proposition of law, and there was evidence to support it. Livermore v. Wright, 33 Mo. 31; Phillips on Mechanics? Liens, sec[508]*508tions 822 and 324. Bnt the difficulty in defendant’s way is that she has not, in my opinion, sufficiently raised this issue by her answer. Instructions must be framed with regard to the issues made in the pleading. Benson v. R. R. Co., 78 Mo. 504. The petition, in conformity with the statutory requirement in such actions, distinctly alleged that the demand became due on the second day of March, 1882, and that within four months thereafter, to-wit, on the eleventh day of May, 1882, they filed the account, etc., for the lien. ' This was a material averment under the statute. Section 3179, Revised Statutes. The statute further provides (section 3545) that, “Every material allegation of the petition not controverted by the answer, shall, for the purposes of the action, be taken as true.”

We fail to find in the answer any denial of this allegation. , Even as to the matters sought to be denied, the plea is bad, as it only avers the want of knowledge on the part of the defendant. Revely v. Skinner, 33 Mo. 98; Watson v. Hawkins, 60 Mo. 550.

It is not correct to say that the matter averred by the petition is a mere conclusion of law. It alleges a distinct fact, that the demand became due on a certain named day, and then sets out the items of the account, which show primes fade a running account, the last date of the items corresponding with the averment of the petition. As the defendant did not deny this allegation, nor plead any new fact in contradiction of it, the allegation stood as if the answer had admitted in express terms, that the demand did become due on that day; which would have been equivalent to saying it did not accrue on any other day.

2. The important question presented by this appeal is, that portion of the defence and proof, which pleaded and established, that under and pursuant to defendant’s contract with the contractor, Hinds, she fully paid him the whole contract price for the building, every dollar of which was applied to the liquidation of claims for work and materials thereabouts; that she did so in good faith, without any knowledge whatever of the existence of plaintiffs’ demand.

[509]*509This raises a question of great practical importance, and one that ought to be definitely settled, so far as a direct decision can determine it. Counsel for respondent contends that this question was passed upon by the supreme court of this state in Hilliker v. Francis 65 (Mo. 598).

If that be so, and the decision is the latest holding of the court on the subject, we should feel bound by it. But a careful examination of the case satisfies my mind that this question, in its broad and true. significance, was neither in the mind of counsel who argued the case, nor of the learned judge who delivered the opinion. The principal questions at issue there were, whether the proper parties were in court; the settlement interposed as a defence by defendants ; the right of the defendant bank to take an appeal, and sufficiency of the account filed as the basis for the lien.

The phraseology of the instruction numbered four, and the language of Judge Henry in adverting casually to it, plainly indicate that it was intended merely to bear on the question, as to whether the sub-contractor could recover the contract price between the owner and the contractor, or the reasonable value of the materials. So Judge Henry says, as the instruction did not assert that the bank is liable to plaintiff for the price agreed upon by the contractors, without regard to the actual value, and there was no evidence to show that the work, etc., were worth less than the contract price, and the question discussed by counsel is not presented by the instruction, it is not objectionable. This is the whole of it. It would be quite unsatisfactory to regard such a decision as disposing of so grave a question. No such issue in fact was presented by the record.

The first section of the Mechanic’s Lien Law (section 3172 Revised Statutes), gives to every mechanic, or other person, who shall do any work upon, or furnish any material for any building, etc., under or by virtue of any contract with the owner or his agent, contractor or subcontractor, a lien upon such building.

It must be admitted that this language is quite broad. [510]*510But it should receive such construction as, while upholding its true object and preserving its spirit, yet, would not allow it to become an intolerable oppression, or to impinge upon deep rooted principles of universal justice, or to strike down the inviolability of property rights, against the consent of the owner. No court has as yet exhibited the temerity to assert that the contractor, himself, could enforce a lien for one dollar’s worth of work or material beyond his contract price. By the express provision of the statute, his right to the lien depends and rests upon the existence of a contract between him and the property owner. That his sub-contractor, who never saw nor communicated with the owner, can occupy in this respect a better position than the principal contractor, must strike the judicial mind as violative of every principle of recognized law and every dictate of justice. Such a right cannot stand on the doctrine of principal and agency. Deardorff v. Everhartt, 74 Mo. 37. He who deals with a special agent must take notice of the extent of his authority and the limitations upon his office.

The sub-contractor is, sometimes, designated as a quasi agent. How the quasi agent can have a wider range of powers than the full agent is not apparent. It is to make the prefix greater than that which it qualifies. The only rational basis for the legislation giving the subcontractor a lien against the property owner, is the principle of substitution. By which, it would seem, the party substituted, by operation of law, could occupy no better situation than he for whom he is substituted.

The statute, without the aid or assent of the owner, creates a privity between a sub-contractor and contractor. So it is held, and properly, that the sub-contractor is in law presumed to have notice of the terms of the contract between the owner and the contractor. Stewart v. Wright, 52 Iowa 335; Garnett v. Berry, 3 Mo. App. 205; Scott v. Cook, 8 Mo. App. 193; Jensen v. Brown, 2 Col. 697. “ The material man, or sub-contractor, deriving all his claims from the original contract, must look to its terms for the extent and limits of his capacity to fasten [511]*511alien, upon the owner’s property.” Garnett v. Berry, supra.

‘ ‘All such persons are presumed to have notice of the existence of such contract, a general knowledge of its terms, and the rights and obligations of' the parties thereto, and to have taken sub-contractor’s contributed labor and furnished materials, in strict subordination to such terms, relative rights and obligations, in respect to the amount which the owner may be required to pay under his contract.” Jensen v. Brown, supra.

So it was held in Bowen v. Aubry, et al. (22 Cal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hightower v. Bailey
56 S.W. 147 (Court of Appeals of Kentucky, 1900)
Jones v. Great Southern Fireproof Hotel Co.
79 F. 477 (U.S. Circuit Court for the District of Southern Ohio, 1897)
Chilton v. Lindsay
38 Mo. App. 57 (Missouri Court of Appeals, 1889)
Henry & Coatsworth Co. v. Evans
97 Mo. 47 (Supreme Court of Missouri, 1888)
Pullis v. Hoffman
28 Mo. App. 666 (Missouri Court of Appeals, 1888)
Kansas City Planing Mill Co. v. Brundage
25 Mo. App. 268 (Missouri Court of Appeals, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
18 Mo. App. 497, 1885 Mo. App. LEXIS 369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-v-hinds-moctapp-1885.