Henry v. Corporation Commission

1990 OK 104, 825 P.2d 1262, 61 O.B.A.J. 2546, 1990 Okla. LEXIS 111, 1990 WL 142044
CourtSupreme Court of Oklahoma
DecidedOctober 2, 1990
Docket68776, 68793 and 68795
StatusPublished
Cited by38 cases

This text of 1990 OK 104 (Henry v. Corporation Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry v. Corporation Commission, 1990 OK 104, 825 P.2d 1262, 61 O.B.A.J. 2546, 1990 Okla. LEXIS 111, 1990 WL 142044 (Okla. 1990).

Opinions

LAVENDER, Justice.

The issues presented on appeal are 1) did AOG’s customers have sufficient notice of the Commission’s intent to increase AOG’s base cost of gas and line loss and 2) is the Commission’s order increasing the amount of refund owed AOG’s customers a valid order. We hold that the Commission’s notice was insufficient to adequately inform AOG’s customers that an increase in line loss or base cost of gas was to be considered. We further find that the Commission’s order increasing the amount of refund owed AOG’s customers is valid in that AOG waived its right to challenge the order on appeal having failed to contest the staff’s motion during the Commission’s proceedings.

I. Facts

On December 26, 1985, Arkansas Oklahoma Gas Corporation (AOG), a gas utility serving certain communities and rural areas in Sequoyah, LeFlore and Haskell counties in Oklahoma, filed an application with the Oklahoma Corporation Commission seeking a general rate increase. The Corporation Commission designated this application as Public Utility Docket Cause No. 79. On April 24, 1986, the Eastern Oklahoma Legislative Delegation (EOLD), as representatives of the customers of AOG, filed a protest to the application for an increase in utility rates. In May of the same year the Attorney General of Oklahoma also filed an intervention as to the application for rate increase as representative of the public.

On April 24, 1986, the same date that EOLD entered its appearance in the general rate increase proceeding initiated by AOG, the Commission staff filed an application which was designated as Public Utility Docket Cause No. 158. In the application in Cause No. 158, the Commission staff alleged that in the course of monitoring AOG’s compliance with Commission [1265]*1265Rules and Regulations governing fuel adjustment clauses1 it had discovered that AOG was recovering line loss2 through the purchased gas adjustment clause.3 The application alleged that this recovery was not permissible through this mechanism.4 Because AOG had a seven and one-half percent line loss factored into its base rates under the previous Commission order establishing general rates, the recovery of actual line loss through the purchased gas adjustment clause had resulted in an ov-errecovery of fuel costs. The application sought an order from the Commission directing a refund to AOG’s customers. Additionally, the application requested that AOG’s gas costs be rebased. No mention was made that an increase in line loss was to be considered or that other appropriate relief would be considered.5

A hearing was set on the staff application in Cause No. 158 and notice was mailed to counsel for AOG and to the Attorney General. No other notice was given as to the hearing in this matter. The hearing was held on May 6,1986. The Commission entered Order No. 297572 which directed AOG to refund to its customers an amount in excess of $400,000, the exact amount to be determined at a later time, plus interest at the rate of six percent during the course of billing over the next twelve months. The order also allowed AOG to rebase its gas costs from $1.41 per MCF to $2.05 per MCF and to increase the line loss factor in its rate base from seven and one-half percent to eleven percent effective in its May 1986 billings.

‘Fuel adjustment clause’ means any mechanism which allows a public utility or electric generating cooperative to automatically adjust its charges above or below the base amount included in its rates, based upon changes in costs of fuel for generation of electricity, purchased power or purchased gas....

On January 21, 1987, the Commission staff filed an application to increase the amount of refund determined in Cause No. 158. This application, however, was filed under Cause No. 79. A copy of this motion was therefore delivered to all parties having entered appearances in the general rate proceeding. As a result EOLD was given actual notice of this application and of the subsequent order setting a hearing date for the motion.

However, on January 15,1987 EOLD had already filed a motion in Cause No. 79 challenging the proceedings as to the May 6, 1986 hearing on the grounds of lack of notice to the public. EOLD amended this motion on February 19, 1987 to more particularly challenge the lack of notice, and requested a cancelation of that part of Order No. 297572 which allowed AOG to increase its rates. The Attorney General filed a motion in support of the position of EOLD on February 23, 1987. The Attorney General challenged the order on the basis of lack of notice of the intent to consider increasing AOG’s line loss factor, as well as raising questions of evidentiary support and Commission authority to take [1266]*1266the action of increasing AOG’s rates to its consumers under this procedure.

In Order No. 310988 the Corporation Commission granted the staff application to increase the refund, ordering AOG to refund an additional $126,615 plus interest to AOG’s customers. The Commission denied EOLD's and the Attorney General’s requests to delete the rate increase provisions of Order No. 297572.

The Attorney General, EOLD and AOG have each filed separate appeals from Commission Order No. 310988. The Attorney General challenges the adequacy of the notice received as to Cause No. 158. EOLD challenges the validity of Order 297572 because of the failure to give notice to the public which EOLD represents. AOG challenges the increase in the refund it must make to its customers. All three appeals have been consolidated for disposition. We address first the challenge brought by EOLD as to the validity of Order No. 297572 and ultimately, the correctness of Order No. 310988.

II.

EOLD argues that the provisions of Order No. 297572 allowing a rate increase, i.e. the allowance of increased line loss factor and base gas costs, are invalid because the Commission failed to give notice to the consumers affected by the increase. This Court has held that “rate making” being a legislative power ... “judicial due process notice and hearing ... unless specifically required by statute ...”6 are not required. While EOLD does not cite a statutory basis for its contention, it does claim that notice was required under the Oklahoma Constitution Art. IX § 18. However, these constitutional provisions provide for publication notice only in a situation where the Commission is engaged in general actions not directed at any named utility. Here the action involved a named utility and therefore that portion of Art. IX § 18 relied on by EOLD has no application.7

EOLD also argues that the Corporation Commission Rule of Practice 8-27(b) requires that notice of the application in Cause No. 158 be given to the consuming public. Rule 8-27(b) provides:

Notice of hearing of an application for approval of any schedule, rate, charge, classification, rule or regulation which will directly or indirectly alter charges made for services performed, shall be published once each week for two (2) consecutive weeks at least fifteen (15) days prior to a hearing in a newspaper of general circulation published in each county in which are located utility customers affected thereby, unless the Commission directs otherwise.

AOG and the Commission argue that Rule 8-27(b) does not apply in this situation because Order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CITY OF OKLAHOMA CITY v. OKLAHOMA CORPORATION COMMISSION
2024 OK 77 (Supreme Court of Oklahoma, 2024)
STATE ex rel. OKLAHOMA BAR ASSOCIATION v. BAILEY
2023 OK 34 (Supreme Court of Oklahoma, 2023)
EAGLE ENERGY PRODUCTION, L.L.C. v. THE CORPORATION COMMISSION
2015 OK CIV APP 51 (Court of Civil Appeals of Oklahoma, 2014)
Hoover v. BOONE OPERATING, INC.
2012 OK CIV APP 39 (Court of Civil Appeals of Oklahoma, 2012)
Beets v. Metropolitan Life Insurance Co.
1999 OK 15 (Supreme Court of Oklahoma, 2011)
City of Midwest City v. House of Realty, Inc.
2008 OK 28 (Supreme Court of Oklahoma, 2008)
Pollock v. Patuxent Institution Board of Review
823 A.2d 626 (Court of Appeals of Maryland, 2003)
Satellite System, Inc. v. Birch Telecom of Oklahoma, Inc.
2002 OK 61 (Supreme Court of Oklahoma, 2002)
R.K. Black, Inc. v. Oklahoma Tax Commission
2002 OK CIV APP 8 (Court of Civil Appeals of Oklahoma, 2001)
Jackson v. Scott
2000 OK CIV APP 139 (Court of Civil Appeals of Oklahoma, 2000)
In re the Non-Reemployment of Isch v. Oklahoma Independent School District No. I-89
1998 OK CIV APP 90 (Court of Civil Appeals of Oklahoma, 1998)
Opinion No. (1997)
Oklahoma Attorney General Reports, 1997
Bank IV Oklahoma, N.A. v. Southwestern Bank & Trust Co.
1997 OK 31 (Supreme Court of Oklahoma, 1997)
Southwestern Bell Telephone Co. v. Oklahoma Corp. Commission
897 P.2d 1116 (Supreme Court of Oklahoma, 1995)
Southwestern Bell Telephone Co. v. Oklahoma Corporation Commission
1994 OK 38 (Supreme Court of Oklahoma, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
1990 OK 104, 825 P.2d 1262, 61 O.B.A.J. 2546, 1990 Okla. LEXIS 111, 1990 WL 142044, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-v-corporation-commission-okla-1990.