Henry v. Aetna Indemnity Co.

79 P. 42, 36 Wash. 553, 1905 Wash. LEXIS 627
CourtWashington Supreme Court
DecidedJanuary 5, 1905
DocketNo. 5359
StatusPublished
Cited by3 cases

This text of 79 P. 42 (Henry v. Aetna Indemnity Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry v. Aetna Indemnity Co., 79 P. 42, 36 Wash. 553, 1905 Wash. LEXIS 627 (Wash. 1905).

Opinion

Hadley, J. —

This is an action upon a contractor’s indemnity bond. The complaint shows that the contract price for the construction was $5,940, and avers that the contractor violated the terms of the contract by failing to pay the claims for labor and material which entered into the construction, and thereby allowing such claims to be assessed against the property to the extent of $3,314.06 in. excess of the contract price. It is also averred that, immediately after such default became known to the property owner, he duly notified the surety company thereof, and demanded that it pay, or cause to be paid, the asserted demands, and should save him harmless therefrom. Demands, as asserted in various filed lien notices, are set out, and it is alleged that suits were brought to foreclose the same; that immediately thereafter the property owner notified the surety company in writing thereof, tendered it the defenses to said actions, and demanded that it should defend the same, and save the owner harmless from the ex[555]*555pense of such defenses; that the surety failed and refused to interpose any defenses, or to assume any expense in connection therewith; that the owner was compelled to employ counsel and interpose defenses to said actions, and that he did all that could properly be done to protect the premises against said claims; that said actions were tried and resulted in judgments establishing the liens, together with attorney’s fees and costs, aggregating the sum of $3,146.04; that the owner was thereupon compelled to pay, and did pay and satisfy, said judgment liens, and that he also incurred an additional expense of $200 as attorney’s fees in the defense of said actions. It is further alleged that, before the last payment under the building contract was made, the surety company, through its duly authorized agents, requested that payments under the contract should be made to said agents, and that, for some time prior to the completion of the building, said agents received the money due the contractor, and disbursed it in satisfaction of claims against the building as the surety company directed, all with the consent of the contractor. The answer denies, generally, the material averments of the complaint, and affirmatively alleges that this action was not brought within six months of the contractor’s default, as required by the terms of the bond. The cause was tried by the court without a jury, and resulted in a judgment against the surety in the sum of $4,165.01, and for costs. The surety company has appealed.

Several assignments of error relate to the same general subject and will be discussed together. The local representatives of appellant in Seattle were Calhoun, Denny & Ewing, while its general agents were Clemens & O’Brien, located in Portland, Oregon. It is urged that the court erred in admitting evidence tending to show that the local representatives waived conditions in the bond, and in hold[556]*556ing that their acts were binding upon appellant. The bond provides that the surety company shall be notified, in writing, of any act on the part of the contractor which may involve loss for which the surety is responsible; that such notice shall be given by registered letter, directed to said Clemens & O’Brien, immediately after the occurrence of such act shall have cometo the knowledge of the respondent. It is contended that knowledge of the contractor’s failure to meet the payments due for labor and material came to respondent, and that he did not immediately notify appellant as provided in the bond. We think the evidence satisfactorily shows that -respondent was not advised of the contractor’s probable default until he was notified by - Calhoun, Denny & Ewing, appellant’s own agents in Seattle, that they desired that the payments under the contract should thereafter be made to them instead of to the contractor; even then it was stated to respondent by these agents of appellant that they did not think-any difficulty would arise about the payments, but, as a matter of precaution, they desired respondent to make his payments to them so they could disburse the money. The contractor joined in the request for respondent- to so make his payments, and this course was pursued from some time early in August until about the first of the following October, when the said agents notified respondent that they refused to receive and disburse any further payments. The contract in terms called for the completion of the work August 15, but it- was not so completed, and the work was continued and the payments made in the manner aforesaid after that time.

It is contended by appellant that no authority is shown from it to Calhoun, Denny & Ewing, the agents in Seattle, to receive and disburse the money as was done. It is not disputed, however, that Clemens & O’Bryan, the general agents in Portland, had the power to authorize such a [557]*557course, and we are satisfied from the evidence that they were advised from time to time, by the Seattle agents, as to wbat was being done, and that they acquiesced therein. Thus the probable default of the contractor was brought home to appellant, so that it had actual knowledge thereof, and not only that, but it approved and adopted what it deemed to be a good course in view of such knowledge. Even if respondent had actually known of the contractor’s probable default, it was not necessary that the formal notice specified in the bond should be given when appellant already knew the fact, and was acting upon its knowledge for its own protection. Moreover, as we have said, we do not think it appears that respondent had any intimation of the probable default in payments until he received it from appellant’s agents, and he was even then misled by their remark that they thought no difficulty would arise. As we understand the record, the said Seattle agents were the only representatives of appellant in the state of Washington, and, under the circumstances we have detailed, together with the evidence before us concerning the knowledge of the general agents as to what was being done, and as to their directions in the premises, we think the Seattle agents acted by authority of appellant. The court, therefore, did not err in admitting the criticized evidence, and in holding thereunder that the acts of the Seattle .agents were bj authority of appellant, and amounted to a waiver of the necessity for the formal notice of failure to pay claims against the property. That the acts of appellant’s agents in the premises amounted to a waiver is sustained by the following authorities: 13 Am. & Eng. Enc. Law (2d ed.), p. 345; Cushing v. Williamsburg City Fire Ins. Co., 4 Wash. 538, 30 Pac. 736; Home Ins. etc. Co. v. Myer, 93 Ill. 271; Harris v. Phoenix Ins Co., 85 Ia. 238, 52 N. W. 128; German Fire Ins. Co. v. Stewart, 13 Ind. App. 627, 42 N. E. 286; Rokes v. Amazon Ins. Co., 51 Md. 512, 34 [558]*558Am. Rep. 323. In the last cited case the court, when speaking of the subject of waiver, said:

“Nor is it necessary to prove an express agreement to waive. On the contrary it may be inferred from the acts and conduct of the insurer inconsistent with an intention to insist upon a strict performance of the condition.”

See, also, Ovington v. Aetna Indemnity Co., ante p. 473, 78 Pac. 1021.

What is said above applies also to the necessity ior formal notice of failure to complete the building at the contract time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sumner Phosphate Co. v. Jarecki Chemical Co.
22 Ohio C.C. Dec. 286 (Ohio Circuit Courts, 1910)
Sumner Phosphate Co. v. Jarecki Chemical Co.
14 Ohio C.C. (n.s.) 59 (Franklin Circuit Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
79 P. 42, 36 Wash. 553, 1905 Wash. LEXIS 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-v-aetna-indemnity-co-wash-1905.