Hennemuth v. Weatherford

278 S.W.2d 271, 1955 Tex. App. LEXIS 2620
CourtCourt of Appeals of Texas
DecidedApril 7, 1955
Docket3263
StatusPublished
Cited by12 cases

This text of 278 S.W.2d 271 (Hennemuth v. Weatherford) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hennemuth v. Weatherford, 278 S.W.2d 271, 1955 Tex. App. LEXIS 2620 (Tex. Ct. App. 1955).

Opinion

McDONALD, Chief Justice.

This suit was brought' by Plaintiff-Appel-lee Roofing Company against Defendant-Appellant houseowner for breach of a written contract wherein plaintiff was to apply asbestos shingles to the outside walls of defendant’s house and do certain other work, and be paid therefor the sum of $550. Plaintiff’s suit-further alleged that it was to do certain additional and extra specified work and be paid therefor the sum of $40 based on cost of time and materials spent on such extra work. Plaintiff further prayed for reasonable attorney’s fees and for foreclosure of a materialman’s and mechanic’s lien on the premises of Defendant.

Trial was to the court without a jury, who entered judgment for plaintiff for $500, plus $150 for attorney's fees, and foreclosure of the materialman’s and mechanic’s *272 lien on the'premises, and directed that an order of' sale issue to sell defendant’s premises as under execution in satisfaction of the judgment.

Defendant appeals to this court, contending: (1) The Trial Court erred in rendering judgment for the plaintiff for $500 on the contract when the pleadings and the evidence showed a written contract price of $550 for the performance of the work. (2) The Trial Court erred in ordering foreclosure of the materialman’s and mechanic’s lien on the judgment for $500 since the written contract lien was in the sum of $550. (3) The Trial Court erred in foreclosing the materialman’s and mechanic’s lien in the sum of $150 allowed as attorney’s fees. (4) The Trial Court erred in fore-, closing the materialman’s and mechanic’s lien because. Defendant had not acknowledged the contract.

The Trial Court upon request filed Findings of Fact and Conclusions of Law as follows:

. Findings of Fact
(1) Plaintiff and defendant entered into a written contract wherein plaintiff was to do and perform certain work on defendant’s house, and in consideration therefor was to be .paid $550.
(2) Plaintiff substantially completed the work in question and reasonably complied with his obligations to defendant.
(3) Defendant has made no payment to plaintiff.
' (4) The sum of $500 is a reasonable sum to compensate plaintiff for his work furnished Defendant.
(5) Plaintiff filed a Mechanic’s Lien Affidavit in the Deed Records of Dallas County on 19 April 1952 and within 90 days after the work in question was performed and payment due.
(6 and 7) Plaintiff engaged an attorney and a reasonable attorney’s fee is $150.
(8) Defendant has occupied the premises in question as her homestead since 1924.
Conclusions of Law
(1) Plaintiff is entitled to judgment against defendant for $500, plus $150 as attorney’s fees, with interest on $500 from 1 March 1952.
(2) Plaintiff is entitled to foreclosure of his materialman’s and mechanic’s lien.
Defendant’s 1st contention is that the Trial Court erred in rendering judgment for the plaintiff for $500 on the contract when the pleadings and evidence show a written contract price of $550 for the performance of the specified work. Defendant urges that there is no support in the pleadings and no evidence whatever to sustain the Trial Court’s judgment in the amount of $500; and that under the record made the Trial Court would have had to have rendered a judgment for plaintiff for $550 or nothing.
Plaintiff, of course, contends that it is entitled to have the court’s judgment of $500 affirmed even though it brought suit for $550 under the contract, and that it is within the province of the court to award such a sum for the substantial performance of the building and construction contract.
The Trial Court found that the contract called for a consideration of $550, that the plaintiff substantially completed the work in question and reasonably complied with his obligation to defendant, and that plaintiff is entitled to judgment for $500 as reasonable compensation.
There is evidence in this record to sustain the findings of the Trial Court.

The Law in Texas concerning the right of a building contractor to recover for work done and performed under a building contract was stated by our Supreme Court in Graves v. Albert & Fuess, 104 Tex. 614, 142 S.W. 869, 39 L.R.A.,N.S., 591. The rule as set forth in that case is: In -the case of Building and Construction Contracts, strict and literal performance is not essential to enable the contractor to recover on the contract; if he has substan- *273 tidily performed, he may recover the contract price less the reasonable cost of remedying trivial defects and omissions so as to make the structure comply with the contract.

The foregoing case is precisely in point with the case at bar, and the rule set forth has been followed in the following cases: Linch v. Paris Lumber & Grain Co., Tex., 14 S.W. 701; Timmins v. Independent Lumber Co., Tex.Civ.App., 7 S.W.2d 130. 7 Tex.Jur., 577, states the rule thusly: “Substantial performance is regarded as full performance, insofar as the rule that performance is a condition precedent to the right to recover on the contract is concerned. A contractor who has in good faith substantially performed may sue under the contract But it is not regarded as full performance so far as to entitle the contractor to recover the full contract price.”

Defendant’s 2nd contention- is that the Trial Court erred in foreclosing the materialman’s and mechanic’s lien' on the judgment' for $500 when the written contract lien was for $550.

The record reflects that the original contract affidavit was filed for record in the Mechanic’s and Materialman’s Lien Records of Dallas County, and was based specifically on the written contract in question. Defendant maintains that since the recovery allowed was less than that claimed by plaintiff as being due under the contract as recited in the contract itself as consideration for performance of the contract work, that recovery was not under the contract and therefore no contractor’s lien could be in esse or inure to plaintiff’s benefit.

Defendant cites cases refusing to allow a contract lien because recovery was for a lesser amount than was sued upon. In all of those cases the contract price was for an amount considerably in excess of the amount recovered, and was only in quantum meruit for the work done. In those cases there was no performance or substantial performance of the contract work. ' The court was simply allowing the contractor to recover on an uncompleted' contract for reasonable value of his services performed. Such is clearly not the instance'in. the case at bar. The Findings of the-Trial Court clearly show that plaintiff substantially performed his contract so as to allow him to recover under the contract and not bn quantum meruit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palomita, Inc. v. Medley
747 S.W.2d 575 (Court of Appeals of Texas, 1988)
Hunter v. Andrews
570 S.W.2d 590 (Court of Appeals of Texas, 1978)
Godde v. Wood
509 S.W.2d 435 (Court of Appeals of Texas, 1974)
Diaz v. Trevino
430 S.W.2d 742 (Court of Appeals of Texas, 1968)
Graham Construction Co. v. Walker Process Equipment, Inc.
422 S.W.2d 478 (Court of Appeals of Texas, 1967)
Wood v. Barnes
420 S.W.2d 425 (Court of Appeals of Texas, 1967)
Treiber v. Schaefer
416 S.W.2d 576 (Court of Appeals of Texas, 1967)
Rhoades v. Miller
414 S.W.2d 942 (Court of Appeals of Texas, 1967)
United Finance & Thrift Corp. v. Smith
387 S.W.2d 752 (Court of Appeals of Texas, 1965)
Judson v. Scanlan
341 S.W.2d 702 (Court of Appeals of Texas, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
278 S.W.2d 271, 1955 Tex. App. LEXIS 2620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hennemuth-v-weatherford-texapp-1955.