Henkel Construction Co. v. State

10 Ill. Ct. Cl. 538, 1939 Ill. Ct. Cl. LEXIS 30
CourtCourt of Claims of Illinois
DecidedApril 12, 1939
DocketNo. 2155
StatusPublished

This text of 10 Ill. Ct. Cl. 538 (Henkel Construction Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henkel Construction Co. v. State, 10 Ill. Ct. Cl. 538, 1939 Ill. Ct. Cl. LEXIS 30 (Ill. Super. Ct. 1939).

Opinion

Mr. Justice Tantis

delivered the opinion of the court:

Henkel Construction Company, claimant herein, is a co-partnership, engaged in the business of building and constructing highway improvements in Illinois and other states. It submitted a bid to the State of Illinois, Department of Public Works and Buildings, Division of Highways, at a letting held on August 4, 1926, and thereafter claimant was awarded a contract for the building and construction of Sections 19 and 20 of S. B. I. Route No. 18. On August 18, 1926 the following letter was mailed to claimant by Frank T. Sheets, Chief Highway Engineer:

“Gentlemen:
“On August 7, you were awarded the contracts for the above mentioned sections subject to the following special provision in each of these contracts:
“ ‘Right of Way. The right of way for the road to be built under the terms of this contract has not as yet been secured, but will be secured on behalf of the Department of Public Works and Buildings. No work shall be done on this section until formal written notice to proceed has been given by the Department to the contractor, but the work shall be completed within six months after said formal notification has been given. No extra compensation nor claim for damages will be allowed the contractor on account of delay in securing the right-of-way and starting work.’ ”
“The right of way for the following portions of these sections has now been secured:
“Section 19 from Station 109/00 to Station 213/00.
“Section 20 from Station 14/36 to Station 276/00.
“Work may, therefore, be started immediately on the portions for which the right of way has been secured. No work should be undertaken on the remainder of the sections until you have been further advised by this Department.”

Separate contracts for the construction of the several sections were entered into, and one section known as 20-X provided for under Contract No. 2793, was carried on to completion, and was not involved in any delay in connection with the construction of Sections 19 and 20.

Claimant was authorized by letter, dated August 18,1926, signed by C. M. Hathaway, Engineer of Construction, to place orders for cement for use in building Sections 19 and 20. Claimant also received a letter, dated August 19, 1926, signed by M. J. Fleming, District Engineer, urging claimant to commence work on Sections 19 and 20 as soon as possible, such letter stating,

"five miles of right of way had been cleared up on Section 20 extending from Mendota to Meriden and two miles had been cleared up on Section 19 extending through Earlville and to the west.
“* * * * will be glad to receive your letter as soon as possible, advising when the culvert and grading outfits can start.”

C. M. Hathaway, Engineer of Construction, also wrote claimant on August 24, 1926 stating to claimant that construction of these sections (19 and 20) this season is extremely important and every effort should be made on your part to start work immediately. Claimant notified Hathaway by telegram and letter that they expected to start work the next Friday or Saturday, i. e. September 3rd or 4th, 1926. In that letter claimant stated, “our plans are to move our outfit on the job this fall and winter and be all set for an early start on the paving next spring. ’ ’ During September, 1926 claimant started work building culverts, excavating and grading and continued until stopped by bad weather. This work was resumed in the spring of 1927, and on May 27th C. M. Hathaway authorized claimant to place further orders for cement. In the early part of June, 1927 claimant moved in its paving outfit to the location near Meriden and commenced laying cement on the sections of S. B. I. No. 18 covered by its contracts. It continued its work until June 25, 1927 when a telegram was received by Carl Henkel as follows:

“Supreme Court of Illinois in Hill, et al. vs. County of LaSalle, et al., holds that bill for injunction in reference to location or Route Eighteen, Section Nineteen and that portion of Section Twenty from Meridian east should be heard on its merits. Therefore we direct you to stop work today until location has been approved by the courts.”

This injunction suit was predicated on averments that the right of way indicated by the Division of Highways for a distance of approximately eighteen miles between the Villages of Somonauk and Meriden, was through territory over which no highway had ever been previously established and did not conform to the route set forth in the bond issue statute under which the road was being constructed.

Upon receipt of this telegram claimant discontinued its work on Section 19 and that part of Section 20 east of Meriden which were involved in and affected by the above decision of the Supreme Court, but proceeded to carry on the construction of pavement on that part of Section 20 lying west of Meriden.

The paragraph concerning right of way, contained in the letter from Mr. Sheets to claimant under date of August 18, 1926, was also included as a special provision in each of the contracts which claimant signed.

After claimant completed its work west of Meriden and having been notified not to proceed further with work lying east of Meriden pending the determination of the controversy under the Hill case, claimant early in the year 1928 abandoned its camp and moved its supplies to another section of the State where it had other work.

As a result of the above suit and the adjustment made thereunder, the route of S. B. I. No. 18 was relocated, so as to be entirely clear of Section 19 and a part of Section 20. These portions of Sections 19 and 20 as specified in the contract were abandoned and such portions of Sections 19 and 20 as relocated were thereafter constructed under the provisions of Supplementary Agreement, signed by claimant on October 24,1928. These Supplemental Agreements contained recitals referring to the prior execution of the original contracts on August 7, 1926; that a decision of the Supreme Court had been entered on June 23, 1928, making it necessary to modify the location of certain portions of Route No. 18, and that,

“For and in consideration of the payments and agreements herein contained, party of the second part (claimant herein) agrees with said party of the first part at his own proper cost and expense to perform all the work, furnish all the materials and all labor necessary for the construction of a Portland cement concrete pavement on a location which will be a modification of the location as described in the above mentioned contract for said Section 19 * * ", as provided in the revised plans for Section 19, approved by said party of the first part, August 11, 1928, and which are made a part hereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hill v. County of Lasalle
158 N.E. 112 (Illinois Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
10 Ill. Ct. Cl. 538, 1939 Ill. Ct. Cl. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henkel-construction-co-v-state-ilclaimsct-1939.