Hengst v. John B. Carter Co.

235 F. 982, 1916 U.S. Dist. LEXIS 1444
CourtDistrict Court, D. New Jersey
DecidedSeptember 18, 1916
StatusPublished
Cited by2 cases

This text of 235 F. 982 (Hengst v. John B. Carter Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hengst v. John B. Carter Co., 235 F. 982, 1916 U.S. Dist. LEXIS 1444 (D.N.J. 1916).

Opinion

RELLSTAB, District Judge.

This is a suit for an accounting. On February 27, 1909, the plaintiff and the defendant entered into a written agreement, whereby the former became the manager of the latter in carrying on certain work in connection with the construction of the railway of the Rake Erie & Pittsburg Railway Company. A summary of the provisions of the contract, pertinent to the present controversy, is as follows: The plaintiff was to receive monthly the sum of $250 as an advance, together with his necessary traveling expenses in connection with said employment. On completion of said contract and payment to the defendant of the amount due it for said work, an accounting to ascertain the profits of such construction work was to be had, and, after deducting said monthly advances and other obligations owing by plaintiff to defendant, the latter was to pay the former one-third of said profits. In ascertaining said profits, the contract was to be debited with all machinery, tools, supplies, plant, and other articles purchased by the defendant for said work, and said contract was to .be credited with all payments made on account of the sale of any of said machinery, etc. The plant was not to be considered as a permanent investment of the defendant, but as an expense on account of such work, and in ascertaining said profits the parties were to “agree upon the reasonable value of the plant.” The defendant was to endeavor to secure work to keep said plant continuously employed, in which event said contract was to cover such new work. Each new contract was to “be charged with the reasonable value of the plant as the same may have been fixed on completion of the preceding contract.” If plaintiff abandoned the work before its completion, said monthly payments were to be full payment of his services; but, in the event of his death or disablement prior to said completion, he or his heirs, etc., were to receive one-third of the accumulated profits “to be computed as near as may be to the date of his death or disability, after deducting therefrom so much of the monthly advances of two hundred fifty dollars ($250.00) and any other obligations then owing by the second party (plaintiff) to the construction company (defendant).”

Two other pieces of construction work were secured, and said contract was extended to cover them. The first of these additional constructions was for the Chicago, Burlington & Quincy Railroad, and the second for the Cincinnati, Hamilton & Dayton Railroad. The extension of said contract over the first of these additional works was

[984]*984accomplished by correspondence without any change of terms. In extending said contract to the last construction, a supplemental agreement, dated March 21,, 1910, was entered into, a summary of the pertinent provisions of which is as follows: If, on completion of said work and the rendition of the final accounting, the defendant shall have secured other work upon .which to use said plant, and the plaintiff shall desire to continue in defendant’s service and enter upon such work, he shall be credited upon the defendant’s books with the amount earned by him on said work, less advances made to him and his obligations to the defendant; that so long as said employment continued the amount carried by him, less said advances, should remain with the defendant “on plant account until such time as the parties mutually agree”; the monthly advances were increased to $300, and, if amount earned by plaintiff did not amount to said advances, the plaintiff on demand was to repay the difference to the defendant.

The plaintiff continued in the defendant’s employment until the construction work in said three contracts was finished, and, upon their failure to agree as to the results of the last work, the present suit was instituted to recover alleged profits of $22,159.53. The defendant answered that the last construction had resulted in a loss to an amount in excess of $30,000 and sought by counterclaim to recover the advances made to plaintiff during the progress of the work. On reference the master found that there was due the plaintiff the sum of $20,-917.67, with interest from April 1, 1913. Both parties'filed exceptions to the master’s report. The main controversies raised by these exceptions are over tire interest claimed by the defendant on the capital invested by it in furthering said work, the payment by it of certain salaries, and the value of the plant on hand when the work on the Cincinnati, Hamilton & Dayton contract was completed.

The plaintiff contends that “the reasonable value of the plant” means that the several items making up the plant used should be valued at their fair worth to the owner, that the cost less depreciation was the valuation adopted by the parties upon the termination of the previous jobs, and that in the present accounting the valuation of plant should be made on the same basis. The defendant contends that “reasonable value” means market value, and that, as at the conclusion of such construction work the plant was “secondhand,” market value means “the fair selling value as secondhand materials.”

The master adopted the plaintiff’s theory of valuation. , I agree with the master. If the business relations between these parties had ended with the completion of the work which called the first contract into being, and the parties had failed to agree upon the meaning of the term “reasonable value,” I should be loath to accept the interpretation suggested by the defendant, in view of the fact that it was in the construction business generally and continued therein after the contractual relations between it and the plaintiff ceased, and had use for that kind of material. The price at which property is bid in at public sale is no criterion of value. Martinett v. Maczkewicz, 59 N. J. Law, 11, 35 Atl. 662; Holcombe v. Trenton White City Co., 80 N. J. Eq. 122, 82 Atl. 618, affirmed 82 N. J. Eq. 364, 91 Atl. 1069; In re [985]*985Mary E. McAuslaud, 235 Fed. 173. And the price that a dealer in or user of secondhand material is willing to give for it is usually as misleading as a test of its value. But the question of interpreting the “reasonable value” comes before the court in a less restricted form. The business relations of the parties did not end with the completion of the work specifically named in the contract. New work, as contemplated by said contract, was entered upon under it, and a valuation of the used plant and materials to he charged against the new contracts was agreed upon by the parties.

At the time the original contract was made, the defendant was already engaged in the construction business. It did not come into existence for the particular job mentioned in such contract. It had a construction plant on hand. More would probably be required. All would be secondhand as soon as use was made of it. Some portions, through such use, would become worthless; others would depreciate in utility, and therefore in value; and still others would remain efficiently serviceable after the particular construction was finished.

As the contract reflects that the defendant contemplated continuing in the construction business with or without the aid of the plaintiff after the Fake Erie & Pittsburg Railway Company’s work was finished, and as the ownership of the plant was in the defendant, it would not be in the power of the plaintiff to force the defendant to dispose of it at the conclusion of such work, that an accounting of profits might be had.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goldstein v. United States
63 F.2d 609 (Eighth Circuit, 1933)
John B. Carter Co. v. Hengst
246 F. 674 (Third Circuit, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
235 F. 982, 1916 U.S. Dist. LEXIS 1444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hengst-v-john-b-carter-co-njd-1916.