Hendrickson Transportation, LLC v. Rust Constructors, Inc.

CourtDistrict Court, W.D. Missouri
DecidedJanuary 16, 2024
Docket5:23-cv-06077
StatusUnknown

This text of Hendrickson Transportation, LLC v. Rust Constructors, Inc. (Hendrickson Transportation, LLC v. Rust Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hendrickson Transportation, LLC v. Rust Constructors, Inc., (W.D. Mo. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF MISSOURI ST. JOSEPH DIVISION

HENDRICKSON TRANSPORTATION, ) LLC, ) ) Plaintiff, ) ) v. ) No. 5:23-cv-06077-DGK ) RUST CONSTRUCTORS, INC., et al., ) ) Defendants. )

ORDER GRANTING MOTION TO DISMISS This case arises from a government contract involving emergency levee restoration in northwest Missouri for the U.S. Army Corp of Engineers (“USACE”). Plaintiff Hendrickson Transportation, LLC alleges Rust Constructors, Inc. (“Rust”), Shimmick Construction Company (“Shimmick”), and AECOM Technical Services, Inc. (“ATS”) (collectively, “Defendants”) withheld payment of $8,707,260 in earthmoving services it performed pursuant to a valid subcontract. Plaintiff now seeks to recover all outstanding payments based on an alleged breach of contract. Now before the Court are the following motions: (1) Rust and Shimmick’s motion to dismiss Plaintiff’s complaint; (2) Rust and Shimmick’s motion to stay case proceedings; and (3) ATS’s motion to stay case proceedings. ECF Nos. 28, 37, 39. For the reasons discussed below, the motion to dismiss is GRANTED, and the motions to stay are DENIED AS MOOT. Background In May 2020, ATS entered into a contract with USACE (the “Prime Contract”) to furnish materials and labor for an emergency levee restoration project in northwest Missouri (the “Project”). Because the Prime contract was a cost-plus-fixed-fee contract, USACE provided daily oversight and direction, including approval of work performed by ATS, Rust, Shimmick, and Rust’s subcontractors. In total, the cost to complete the Project was approximately four times the original estimate. ATS contracted with Rust, an ATS affiliate, to manage the Project. In June 2020, Rust

entered into a subcontract with Plaintiff where Plaintiff agreed to furnish all labor, materials, and equipment necessary to perform earthwork operations on the Project for $2,762,298 (the “Subcontract”). The Subcontract included several provisions central to the motion to dismiss. First, the Subcontract conditions any payment to Plaintiff on Defendants’ receipt of payment from USACE. Specifically, Article 6 provides: “Receipt of payment from the Customer is a condition precedent for Company’s obligation to pay Subcontractor. . . . Subcontractor hereby assumes the risk of the Customer’s nonpayment for Subcontractor’s Work, without recourse to Company.” Compl. Ex. A at 6, ECF No. 1-1. This is commonly referred to as a “pay-if-paid” provision. Second, the Subcontract includes dispute resolution procedures for disputes involving

USACE. Specifically, Article 18 provides: “All of Subcontractor’s claims, controversies, or disputes concerning matters that pertain to disputes cognizable under the Disputes Clause of the Prime Contract shall be governed by the provisions of this Article 18.2;” “[a]ny final decision of the contracting officer under the Prime Contract relating to this Subcontract or Subcontractor’s performance hereunder shall be conclusive and binding upon Subcontractor unless appealed and reversed;” and Defendants may “appeal any such final decision, pursuant to the Disputes Clause of the Prime Contract” and the “Subcontractor shall provide [Defendants] with reasonable assistance in the prosecution of such appeal.” Compl. Ex. A at 25–26. Plaintiff and Rust entered into eight modifications to the Subcontract increasing its overall value to $71,074,627. None of these modifications changed the terms of the Subcontract—e.g., payment or dispute resolution provisions. Further, Plaintiff entered into two other subcontracts (and modifications to them) with Rust related to highway transport and levee surfacing work.

These additional subcontracts have the same payment and dispute resolution provisions noted above. Plaintiff alleges Defendants did not receive USACE approval for most of the modifications before directing Plaintiff to complete work on the Project. In February 2021, USACE assigned a new contracting officer to the Project who questioned the reasonableness of certain expenditures, including Plaintiff’s, and expressed concern about the relationship between Rust, Shimmick, and ATS. Based on these concerns, the contracting officer stopped approving all payment in June 2021. Plaintiff completed its work on the Project in January 2022 and is owed $8,707,260 in unpaid earthmoving services. After USACE stopped making payments, ATS filed a certified claim with the contracting officer seeking payment of all outstanding payments on the Project. The contracting officer denied

ATS’s claim. ATS appealed the unfavorable decision to the Armed Services Board of Contract Appeals (“ASBCA”). On appeal, ATS again seeks payment of all outstanding payments on the Project, including the $8,707,260 owed to Plaintiff. On June 22, 2023, Plaintiff filed this suit. Plaintiff’s complaint asserts four counts: breach of contract (Count I); unjust enrichment (Count II); veil-piercing (Count III); and principal-agent liability (Count IV). Rust and Shimmick now move to dismiss Plaintiff’s complaint pursuant to Federal Rule of Civil Procedure 12(b)(1), or to dismiss Counts I and II pursuant to Rule 12(b)(6). Because the Court dismisses the case in its entirety under Rule 12(b)(1) on ripeness grounds, it declines to address the parties’ Rule 12(b)(6) arguments. Standard Federal Rule of Civil Procedure 12(b)(1) requires the Court to dismiss a complaint if it lacks subject-matter jurisdiction to hear a dispute. In deciding a motion under Rule 12(b)(1), the Court “must distinguish between a ‘facial attack’ and a ‘factual attack.’” Branson Label, Inc. v.

City of Branson, 793 F.3d 910, 914 (8th Cir. 2015) (citing Osborn v. United States, 918 F.2d 724, 729 n.6 (8th Cir. 1990)). Here, Rust and Shimmick make a factual attack on the Court’s subject matter jurisdiction, thus the Court considers matters outside the pleadings. See id. 914–15 (noting “in a factual attack, the existence of subject matter jurisdiction is challenged in fact, irrespective of the pleadings, and matters outside the pleadings, such as testimony and affidavits, are considered” (cleaned up)). “The ripeness doctrine flows both from the Article III ‘cases’ and ‘controversies’ limitations and also from prudential considerations for refusing to exercise jurisdiction.” Pub. Water Supply Dist. No. 10 of Cass Cnty. v. City of Peculiar, 345 F.3d 570, 572 (8th Cir. 2003). It is well settled that the ripeness inquiry requires the examination of both “the fitness of the issues

for judicial decision and the hardship to the parties of withholding court consideration.” Id. at 572– 73. A party seeking judicial relief must necessarily satisfy both prongs to at least a minimal degree. Neb. Pub. Power Dist. v. MidAmerican Energy Co., 234 F.3d 1032, 1039 (8th Cir. 2000). Discussion Rust and Shimmick argue the Court lacks subject matter jurisdiction over this case because Plaintiff’s claims are not ripe for review. Plaintiff has not shown otherwise. I. Plaintiff has not shown its claim is fit for judicial decision.

“A case is fit for judicial decision when it would not benefit from further factual development and poses a purely legal question not contingent on future possibilities.” Sch. of the Ozarks, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Hendrickson Transportation, LLC v. Rust Constructors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/hendrickson-transportation-llc-v-rust-constructors-inc-mowd-2024.