Hendrick Construction Co. v. C. E. Thurston & Sons, Inc.

153 S.E.2d 204, 207 Va. 803, 1967 Va. LEXIS 138
CourtSupreme Court of Virginia
DecidedMarch 6, 1967
DocketRecord No. 6329
StatusPublished

This text of 153 S.E.2d 204 (Hendrick Construction Co. v. C. E. Thurston & Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hendrick Construction Co. v. C. E. Thurston & Sons, Inc., 153 S.E.2d 204, 207 Va. 803, 1967 Va. LEXIS 138 (Va. 1967).

Opinion

Carrico, J.,

delivered the opinion of the court.

C. E. Thurston and Sons, Inc., the plaintiff, filed a motion for judgment against Hendrick Construction Company, Inc., the defendant, seeking to recover the sum of $5,170.24. The trial court, sitting without a jury, entered final judgment in favor of the plaintiff for the full amount of its claim, and the defendant was granted this writ of error.

The controversy involves the construction of the Science Building at the Richmond Professional Institute. On January 12, 1962, the defendant, as general contractor, entered into a contract with the Commonwealth for the construction of the building. Thereafter, the defendant contracted with Dixie Plumbing and Heating Company, Inc., whereby the latter agreed to perform the plumbing and heating work on the project. Dixie, in turn, contracted with the plaintiff for the insulation of the structure.

On December 5, 1962, Dixie was adjudicated bankrupt, at which time it was indebted to the plaintiff in the sum of $5,624.01 for labor and materials furnished to Dixie. The plaintiff received $453.77 in the bankruptcy proceedings, leaving a balance due on its claim of $5,170.24, the amount involved in the present action.

The plaintiff alleged in its motion for judgment that the defendant was liable to it because the defendant “did not require and Dixie did not furnish, as a part of such contract between them, a statutory payment bond, as required by Section 11-20 of the Code of Virginia, obligating the principal and surety on such bond to pay all persons, including Plaintiff, who had and fulfilled contracts directly with Dixie for furnishing materials in the prosecution of the work provided for in said contract between Hendrick and Dixie.”

The plaintiff also alleged that the defendant’s contract with the Commonwealth imposed a duty upon the defendant to require a bond of Dixie for the benefit of the plaintiff.

[805]*805The defendant was negligent, the plaintiff contended in its motion for judgment, in failing to perform its statutory and contractual duty of requiring a bond of Dixie and, as a result, the plaintiff was “deprived of the benefit of a surety of Dixie,” thus obligating the defendant to pay the plaintiff’s claim. The plaintiff further contended that it was a third party beneficiary of the contract between the Commonwealth and the defendant and that since the defendant violated its contractual duty to require a bond of Dixie, the defendant was liable to the plaintiff for the latter’s claim.

Code, § 11-20, upon which the plaintiff relies, is a part of Chapter 4 of Title 11 of the Code, entitled “Public Contracts in General.” The Code section has been amended since this controversy arose; but it was worded at that time, in its pertinent provisions, as follows:

M. TV 'A' 'iV TV
“No contractor, as the lowest responsible bidder, shall subcontract any work required by the contract except under the following conditions: each subcontractor shall furnish, and the contractor shall require as a part of the agreement between the subcontractor and the contractor, a payment bond in the amount of 50% of the work sublet to the subcontractor which shall be conditioned upon the payment to all persons who have, and fulfill, contracts which are directly with the subcontractor for performing labor and furnishing materials in the prosecution of the work provided for in the subcontract. Each such bond shall be construed, regardless of its language, as incorporating, within its provisions, the obligation to pay those persons who furnish labor or materials as aforesaid; provided, however, that subcontracts between the contractor and a manufacturer or a fabricator shall be exempt from the provision requiring a payment bond and provided further that subcontracts for less than $2,500.00 each are also exempt hereunder. Provision for said payment bonds shall be made a part of each agreement between the owner and contractor.
“. . . Persons who have, and fulfill, contracts which are directly with subcontractors for performing labor and furnishing materials in the prosecution of construction work defined in § 11-17 shall have a direct right of action against the obligors and sureties on the bond required herein of the subcontractors. . . .”

[806]*806The contract between the Commonwealth and the defendant contained the following provision, upon which the plaintiff relies:

“17. Contract Security.
# # # *
“ (b) The successful bidder (contractor) shall not subcontract any work required by the contract except under the following conditions:
“Each subcontractor shall furnish, and the contractor shall require as a part of the agreement between the subcontractor and the contractor, a payment bond in the amount of 50% of the work sublet to the subcontractor which shall be conditioned upon the payment to all persons who have, and fulfill, contracts, which are directly with the subcontractor for performing labor and furnishing materials in the prosecution of the work provided for in the subcontract. Every such bond shall be construed, regardless of its language, as incorporating, within its provisions, the obligation to pay those persons who furnish, labor or materials as aforesaid.”

The plaintiff contends that the defendant is liable to it upon either of two theories. The first is that the defendant was negligent in failing to perform its statutory and contractual duty of requiring a bond of Dixie and that the plaintiff is entitled to recover the amount of its claim as damages for such failure. The second is that the defendant breached its contract with the Commonwealth in failing to require a bond of Dixie and that the plaintiff, as a third party beneficiary of that contract, may recover for such breach. The plaintiff further contends that under the statute and the contract, the defendant “was obliged to ascertain if the required bond had been furnished.”

The defendant, on the other hand, contends that the statute and the contract merely required it to “obligate the subcontractor to provide such bond” and that “no duty is placed upon the contractor to police the subcontractors action in the posting of the bond, to determine if the bond is properly written, or to take any other action.”

The crucial issue, then, in determining whether the plaintiff is entitled to recover under either of its theories, is whether the defendant “was obliged to ascertain if the required bond had been furnished.”

The trial court, in a written opinion, held that “the burden is placed upon the general contractor to require of his sub-contractors a bond that will guarantee payment to those who furnish materials [807]*807or labor to such sub-contractor.” The court was of opinion that the required bond was one “with corporate surety.” The court stated that the defendant was obligated “to see to it that these laborers and materialmen are thus protected against default in payment by those subcontractors selected by the general contractor.”

The findings of the trial court are incorrect for two reasons. In the first place, the statute and the defendant’s contract with the Commonwealth did not impose upon the defendant the duty to require a bond of Dixie and “to see to it” that Dixie, in fact, furnished such a bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
153 S.E.2d 204, 207 Va. 803, 1967 Va. LEXIS 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hendrick-construction-co-v-c-e-thurston-sons-inc-va-1967.