Hemink Farms, Ltd, Laurens Schilderink, Ilona Van Vliet A/K/A Ilona Schilderink and Hemink Management, LLC v. BCL Construction, LLC

CourtCourt of Appeals of Texas
DecidedMarch 20, 2019
Docket07-17-00457-CV
StatusPublished

This text of Hemink Farms, Ltd, Laurens Schilderink, Ilona Van Vliet A/K/A Ilona Schilderink and Hemink Management, LLC v. BCL Construction, LLC (Hemink Farms, Ltd, Laurens Schilderink, Ilona Van Vliet A/K/A Ilona Schilderink and Hemink Management, LLC v. BCL Construction, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hemink Farms, Ltd, Laurens Schilderink, Ilona Van Vliet A/K/A Ilona Schilderink and Hemink Management, LLC v. BCL Construction, LLC, (Tex. Ct. App. 2019).

Opinion

In The Court of Appeals Seventh District of Texas at Amarillo

No. 07-17-00457-CV

HEMINK FARMS, LTD., LAURENS SCHILDERINK, ILONA VAN VLIET A/K/A ILONA SCHILDERINK, AND HEMINK MANAGEMENT, LLC, APPELLANTS

V.

BCL CONSTRUCTION, LLC, APPELLEE

On Appeal from the 64th District Court Castro County, Texas Trial Court No. A10098-1608, Honorable Robert W. Kinkaid, Jr., Presiding

March 20, 2019

MEMORANDUM OPINION Before QUINN, C.J., and PIRTLE and PARKER, JJ.

Appellants Hemink Farms, Ltd., Laurens Schilderink, Ilona Van Vliet, and Hemink

Management, LLC, appeal from the jury verdict and judgment in favor of BCL

Construction, LLC, on its claims arising from the construction of a house near Hart, Texas.

We affirm in part and reverse and render in part. Background

In 2012, BCL finished construction on a house for Schilderink and Van Vliet that

another contractor had begun. The house was later sold and, in 2015, BCL was hired to

build a new house for Schilderink and Van Vliet. The new home was to be a near-replica

of the first one. It was constructed on property owned by Hemink Farms, a company

which is owned by Schilderink and Hemink Management. Both Schilderink and Van Vliet,

husband and wife, exercised control over the project and had power to make payments.

There was no written contract.

The first house had been completed at a cost of approximately $1.3 million.

Schilderink testified that his budget for the second house was $1.5 million. When Thomas

Robertson, who was a subcontractor BCL hired to be the project manager, outlined a

projected budget of $1.57 million, Schilderink said it was close enough, and to get started.

Schilderink and his family were living in a rental property and wanted to move into the

new house at the end of their one-year lease term. Robertson testified that the budget

was “a starting point,” because he did not have all the facts or any design. Both Robertson

and Schilderink said that the parties agreed that BCL would build the house for cost plus

a flat builder’s fee of $200,000.

Construction on the house was soon underway. Over the course of the project,

Schilderink and Van Vliet made changes to the design of the house and to the materials

used. For example, they raised the pitch of the roof after construction had started, put in

stamped concrete, added a theater room to the basement, built an indoor pool instead of

an outdoor pool, upgraded finishes in the pool house, used solid cedar beams rather than

2 the faux beams used in the first house, increased the size of the garage, installed a “man

cave” constructed with materials from an old barn which BCL gathered, and more. Also,

some features of the house, such as cabinetry and millwork, were redone multiple times

as a result of Schilderink and Van Vliet changing their minds or communicating

contradictory instructions. This led to additional expenses. By the end of 2015, Hemink

Farms had paid $1.678 million in construction costs. Steve Long, the owner of BCL,

testified that as the project neared completion, Schilderink was slow in making payments.

This caused Long to get behind in paying subcontractors. Long testified that when he

sought assurances from Schilderink, Schilderink told him to “just finish, and I’ll pay you.”

He believed Schilderink was withholding payment with the intent to get the project finished

faster. Robertson also testified about the changes and additions made to the house and

stated that “the overarching statement that Mr. Schilderink continued to make to me, was

‘get these finished and I’ll pay you.’”

The family moved into the house in March of 2016, by which time the project had

reached substantial completion. Robertson had made a “punch list” of items that

Schilderink and Van Vliet had identified as requiring completion or correction to finish the

house, and BCL was working on those items in April 2016.

On April 27, 2016, Robertson met with Schilderink at Schilderink’s Spandet Dairy

office to discuss payment of two invoices which remained unpaid. The first, dated March

11, 2016, was for $197,683.43, and the second, dated April 22, 2016, was for

$328,688.34. Schilderink told Robertson he was not expecting another bill, as he

believed he had already paid too much. He testified, “I knew I was over the 1.5 million

but I thought it was still fairly close and I – and I added it up. So we came to 2.1 million I

3 already paid and then I got $500,000-something thousand on top of that, I really got a

shock of that [sic].” Robertson testified that Schilderink wanted to hold BCL to a $1.5

million budget even though he continued to order expensive items for the house.

Robertson had brought the box of invoices for the project, but Schilderink did not want to

review them. Schilderink indicated that he wanted to speak to Long, so Long came from

Amarillo to join the meeting.

All three men testified at trial that, at the time of their April meeting, a dispute

existed regarding payment. Schilderink offered to pay the smaller of the two still-due bills,

but Long said that was not enough and that Schilderink needed to pay the larger bill.

Eventually, Schilderink wrote BCL a check for $263,185, roughly half of the amount due

under the two final bills. BCL deposited the check. Schilderink testified that Long agreed

to “call it good” and took the position that the $263,185 payment was a final settlement.

Long, however, testified that he did not agree to accept the check as a settlement of the

two invoices.

No further payment was forthcoming, so Long eventually filed a mechanic’s and

materialman’s lien against the property. BCL then filed suit against appellants, seeking

foreclosure of the lien and alleging breach of contract, suit on a sworn account, quantum

meruit, and promissory estoppel. Appellants asserted that BCL’s claims were barred by

the doctrines of accord and satisfaction and waiver. Hemink Farms filed counterclaims

against BCL, alleging breach of contract and fraudulent lien filing.

Following a four-day trial, the jury found that all parties, BCL, Schilderink, Van Vliet,

Hemink Farms, Ltd., and Hemink Management, LLC, had agreed that BCL would

4 construct the project and be paid construction costs plus a $200,000 builder’s fee. The

jury found for BCL against all four defendants on its theories of breach of contract,

quantum meruit, and promissory estoppel. Additionally, the jury found that BCL and

Hemink Farms, Ltd., had not reached a settlement agreement that Hemink Farms would

pay $263,185 and receive a credit of $263,186.77. The jury awarded BCL $193,592.99

in damages, representing the amount owed after a partial payment and the punch list

items credited by BCL, on BCL’s contract claim and equitable claims. The jury also

awarded BCL $72,546.50 in legal fees. Appellants filed a motion for judgment

notwithstanding the verdict. The trial court entered judgment on the jury’s verdict. After

their motion for new trial was overruled by operation of law, appellants brought this

appeal.

Analysis

Accord and Satisfaction

In their first two issues, appellants contend they established their affirmative

defense of accord and satisfaction as a matter of law and the jury’s failure to find an

accord and satisfaction was against the overwhelming weight of the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Ready Mix Concrete Co. v. Islas
228 S.W.3d 649 (Texas Supreme Court, 2007)
Lopez v. Muñoz, Hockema & Reed, L.L.P.
22 S.W.3d 857 (Texas Supreme Court, 2000)
Richardson v. Allstate Texas Lloyd's
235 S.W.3d 863 (Court of Appeals of Texas, 2007)
Jenkins v. Henry C. Beck Company
449 S.W.2d 454 (Texas Supreme Court, 1969)
Hixson v. Cox
633 S.W.2d 330 (Court of Appeals of Texas, 1982)
Domingo v. Mitchell
257 S.W.3d 34 (Court of Appeals of Texas, 2008)
Iron Mountain Bison Ranch, Inc. v. Easley Trailer Manufacturing, Inc.
42 S.W.3d 149 (Court of Appeals of Texas, 2001)
Pate v. McClain
769 S.W.2d 356 (Court of Appeals of Texas, 1989)
Vortt Exploration Co., Inc. v. Chevron USA, Inc.
787 S.W.2d 942 (Texas Supreme Court, 1990)
Harris v. Rowe
593 S.W.2d 303 (Texas Supreme Court, 1979)
" MOORE" BURGER, INC. v. Phillips Petroleum Company
492 S.W.2d 934 (Texas Supreme Court, 1972)
Indiana Lumbermen's Mutual Insurance Co. v. State
1 S.W.3d 264 (Court of Appeals of Texas, 1999)
Uniroyal Goodrich Tire Co. v. Martinez
977 S.W.2d 328 (Texas Supreme Court, 1998)
Avary v. Bank of America, N.A.
72 S.W.3d 779 (Court of Appeals of Texas, 2002)
Heldenfels Bros. v. City of Corpus Christi
832 S.W.2d 39 (Texas Supreme Court, 1992)
Pileco, Inc. v. HCI, INC.
735 S.W.2d 561 (Court of Appeals of Texas, 1987)
First State Bank of Panhandle v. Knapp
3 S.W.2d 468 (Court of Appeals of Texas, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
Hemink Farms, Ltd, Laurens Schilderink, Ilona Van Vliet A/K/A Ilona Schilderink and Hemink Management, LLC v. BCL Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hemink-farms-ltd-laurens-schilderink-ilona-van-vliet-aka-ilona-texapp-2019.