Helms v. Belfor USA Group, Inc. (In Re Helms)

438 B.R. 95, 2010 WL 4259175
CourtUnited States Bankruptcy Court, W.D. North Carolina
DecidedOctober 18, 2010
Docket10-31612
StatusPublished
Cited by1 cases

This text of 438 B.R. 95 (Helms v. Belfor USA Group, Inc. (In Re Helms)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Helms v. Belfor USA Group, Inc. (In Re Helms), 438 B.R. 95, 2010 WL 4259175 (N.C. 2010).

Opinion

ORDER DENYING DEBTORS’ MOTION TO AVOID JUDGMENT LIEN

J. CRAIG WHITLEY, Bankruptcy Judge.

This matter came before the Court for consideration on the Motion to Avoid Judgment Lien (the “Motion”) filed by the Debtors Howard Buddy Helms, Sr. and Sandra Nelson Helms the “Debtors”) [Doc. No. 10], Belfor having filed its Objection to the Motion [Doc. No. 16], the Debtors having filed a Memorandum of Law in Support of the Motion [Doc. No. 37], the Court having conducted a hearing on the Motion on September 30, 2010 and the Court being otherwise fully and duly advised in the premises hereby DENIES the Debtor’s Motion with prejudice and FINDS as follows:

1. Belfor entered into a contract (the “Contract”) with the Debtors whereby Bel- *96 for agreed to provide work, including materials and equipment (the “Project”), for repairs arising from a fire at 15217 Bexley Place, Charlotte, Mecklenburg County, North Carolina (the “Property”).

2. Pursuant to the terms of the Contract, the insurance policy proceeds in the amount owed to Belfor were assigned and to be paid directly to Belfor (the “Assignment”).

3. On October 31, 2007, Belfor began providing the labor, materials and/or equipment to the Project pursuant to the terms of the Contract.

4. Debtors filed an insurance claim and received $266,363.00 for use in repairing the Property. Pursuant to the Assignment, Belfor was to receive the entire insurance policy proceeds. However, Debtors paid Belfor only $96,182.57 of the insurance proceeds.

5. On August 4, 2008, Belfor provided its last labor and materials to the Property. However, despite performing under the Contract and completing the Project, Belfor only received partial payment and was not paid $133,989.87 for the labor, materials and/or equipment furnished for the Project.

6. On November 26, 2008, Belfor filed a Claim of Lien on Real Property (the “Lien Claim”) within 120 days of its last furnishing of labor, equipment and/or materials for the Project pursuant to N.C. GemStat. § 44A, Article 2.

7. On January 22, 2009, Belfor filed a state court judicial action to enforce and perfect the Lien Claim as required by N.C. Gen.Stat. § 44A.

8. On April 28, 2010, the state court entered a Rule 52(a) Judgment (collectively with the Lien Claim, the “Judgment”) and awarded a statutory lien on the Property in the amount of $113,145.30 plus prejudgment interest at the contract rate of 18% per annum and $17,000 for attorneys’ fees in accordance with N.C. Gen. Stat. §§ 44A-17 through 35 with an effective date of October 31, 2007 for purposes of establishing lien priority.

9. On June 6, 2010, the Debtors filed their voluntary petition (the “Petition Date”) under Chapter 7 of Title 11 of the United States Bankruptcy Code (the “Code”). [Doc. No. 1],

10. Debtors filed the Motion pursuant to 11 U.S.C. § 522(f)(1) of the Bankruptcy Code alleging that the Judgment was a “judicial lien” that could be avoided under Section 522(f)(1).

11. Belfor objected for the reason that the Judgment was a “statutory lien” and therefore not avoidable as a judicial lien under Section 522(f)(1).

12. Section 522(f)(1) of the Code provides in pertinent part,

Notwithstanding any waiver of exemptions but subject to paragraph (3), the debtor may avoid the fixing of a lien on an interest of the debtor in property to the extent that such lien impairs an exemption to which the debtor would have been entitled under subsection (b) of this section, if such lien is—
(A) a judicial lien, other than a judicial lien that secures a debt of a kind that is specified in section 523(a)(5)....

11 U.S.C. 522(f)(1).

13. Section 101(36) of the Code defines a “judicial lien” as a “lien obtained by judgment, levy, sequestration, or other legal or equitable process or proceeding.” Conversely, section 101(52) of the Code defines “statutory lien” as a “lien arising solely by force of a statute on specified circumstances or conditions....” As a result, section 522(f)(1) expressly provides relief only for judicial liens and does not *97 allow a debtor to avoid statutory liens. See In re Chambers, 264 B.R. 818 (Bankr. N.D.W.Va.2001); Colliee on Bankruptcy, ¶ 522.11.

14. The Judgment constitutes a mechanics’ lien. The legislative history of the Bankruptcy Code indicates that Congress considered mechanics’ liens to be statutory liens:

The definition [of a statutory lien] excludes judicial liens and security interests, whether or not they are provided for or are dependent on a statute, and whether or not they are made fully effective by statute. A statutory lien is only one that arises automatically, and is not based on an agreement to give a lien or on judicial action. Mechanics’, mate-rialmens’, and wharehousemens’ liens are examples.

S.Rep. No. 95-989 at 27, 95th Cong., 2d Sess. (1978), U.S.Code Cong. & Admin. News 1978, at 5787, 5818, quoted in In re Chambers, 264 B.R. 818, 820-21 (Bankr. N.D.W.Va.2001). As a general rule, courts have defined mechanics’ liens as statutory liens. See, e.g., In re Concrete Structures, Inc., 261 B.R. 627, 631-32 (E.D.Va.2001).

15.In North Carolina, the various forms of mechanics’ liens against real property arise under North Carolina Code Chapter 44A, Article 2 entitled “Statutory Liens on Real Property.” A material-man’s lien, such as that of Belfor, arises specifically under section 44A-8. This section provides that:

Any person who performs or furnishes labor ... .pursuant to a contract, either express or implied, with the owner of real property for the making of an improvement thereon shall, upon complying with the provisions of this Article, have a right to file a claim of lien on real property on the real property to secure payment of all debts owing for labor done or professional design or surveying services or material furnished or equipment rented pursuant to the contract.

16. The methods of perfecting and enforcing materialmens’, laborers’ and other mechanics’ liens are set forth later in Article 2 of the North Carolina Code. Section 44A-12 states, in part that:

All claims of lien on real property must be filed in the office of the clerk of superior court in each county where the real property subject to the claim of lien on real property is located. The clerk of superior court shall note the claim of lien on real property on the judgment docket and index the same under the name of the record owner of” the real property at the time the claim of lien on real property is filed....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Cunningham
478 B.R. 346 (N.D. Indiana, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
438 B.R. 95, 2010 WL 4259175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/helms-v-belfor-usa-group-inc-in-re-helms-ncwb-2010.