Helmerich & Payne International Drilling Co. v. BOPCO, L.P.

357 S.W.3d 801, 181 Oil & Gas Rep. 396, 2011 Tex. App. LEXIS 9444, 2011 WL 5999026
CourtCourt of Appeals of Texas
DecidedDecember 1, 2011
Docket11-10-00232-CV
StatusPublished
Cited by3 cases

This text of 357 S.W.3d 801 (Helmerich & Payne International Drilling Co. v. BOPCO, L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Helmerich & Payne International Drilling Co. v. BOPCO, L.P., 357 S.W.3d 801, 181 Oil & Gas Rep. 396, 2011 Tex. App. LEXIS 9444, 2011 WL 5999026 (Tex. Ct. App. 2011).

Opinion

OPINION

TERRY McCALL, Justice.

This case involves the interpretation of a daywork drilling contract. The parties disagree as to the date that the 1,095-day term of the contract commenced. Upon construing the contract, the trial court rendered summary judgment granting declaratory relief to appellee, BOPCO, L.P. 1 The trial court declared, among other things, that the 1,095-day contract term commenced on March 20, 2007. Appellant, Helmerich & Payne International Drilling Co. (H & P), appeals from the trial court’s summary judgment. We affirm.

Background Facts

In late 2005, BOPCO needed a drilling rig for the purpose of drilling wells in Colorado. H & P agreed that it would manufacture a drilling rig and then use that rig to drill wells for BOPCO. In January 2006, representatives from BOP-CO and H & P executed a daywork drilling contract. The parties used a standard fill-in-the-blank form contract prepared by the International Association of Drilling Contractors. The parties deleted parts of the form contract, and they made some additions to the contract.

Under the contract, BOPCO was the “Operator,” and H & P was the “Contractor.” The contract provided that BOPCO had engaged H & P as an independent contractor to drill various wells on a day-work basis. Paragraph 2 of the contract provided as follows:

2. COMMENCEMENT DATE:
Contractor agrees to use reasonable efforts to commence operations for the drilling of the well by on or about the 20th day of March, 2007.

As shown above, the parties struck the word “by” from Paragraph 2 of the form contract. The parties added the “on or about” language and inserted the March 20, 2007 date in Paragraph 2. Paragraph 6 of the contract provided as follows:

6. TERM:
6.1 Duration of Contract: This Contract shall remain in full force and effect until-drilling ope-r-ations-are ■ completed on the well or wells speei-Sed-in-Para-graph-1 above, or for a term of 1095-days, or at rig release of any well being drilled by operator on the 1095th day, whichever is later, commencing on the date specified in Paragraph 2 above (subject to 27.7 Early Termination).

As shown above, the parties struck the language in the contract beginning with the word “until” and ending with the word “or.” The parties added the term “1095-days” in the blank. They also added, in handwriting, the words that are italicized above.

In Paragraph 4 of the contract, BOPCO agreed to pay H & P a day rate of $23,300 per day for work performed by H & P under the contract. By later agreement, the day rate was changed to $23,800 per day. The contract contained an early ter *803 mination provision. Paragraph 27.7 of the contract provided, in relevant part, as follows:

27.7 Early Termination Provision:
Operator shall have the right to terminate the Contract at any time after the date of execution of the Contract by both parties and prior to the expiration of the first 1,095 calendar days thereafter (the “Early Termination”) by giving thirty (30) days’ prior written notice to the Contractor, conditional upon Operator paying Contractor the Early Termination amount and other amounts specified below.
In the event of Early Termination, Operator shall pay to the Contractor an Early Termination Amount equal to the number of days remaining in the 1,095 calendar day term multiplied by $14,000. Operator shall pay in one payment (within thirty (80) calendar days of the date of Contractor’s invoice) such Early Termination amount. The Early Termination amount is in addition to all other amounts due and owing under the Contract prior to the date of such Early Termination, including without limitation the mobilization and demobilization payments.

By later agreement, the parties increased the early termination rate to $14,500 per day.

The parties added a typewritten liquidated damages provision to the contract. Paragraph 27.15 of the contract provided as follows:

27.15 Notwithstanding the foregoing, in the event Commencement of Operations has not occurred by March 20, 2007 for reasons wholly within Contractor’s reasonable control, Contractor will pay Operator, as liquidated damages for such delay and not as a penalty, a sum equal to $2,500 per day (the “Delay Payment”) for each day after April 20, 2007 that Commencement of Operations has not occurred, up to a maximum of $225,000. Such payment will be Operator’s sole remedy and Contractor will have no other liability for any delay in the Commencement of Operations.

H & P experienced delays in manufacturing the rig and, therefore, did not commence drilling operations under the contract until June 4, 2007. As required by Paragraph 27.15 of the contract, H & P paid liquidated damages to BOPCO in the amount of $2,500 per day covering the forty-five day period from April 20, 2007 until June 4, 2007. The liquidated damages totaled $112,500. When H & P commenced operations under the contract, BOPCO began paying H & P the day rate of $23,300 per day for use of the rig.

In 2009, BOPCO exercised its right to terminate the contract early. By letter dated April 21, 2009, BOPCO provided H & P thirty-days’ written notice of its intent to terminate the contract, “effective May 21, 2009 or at rig release from the [well], whichever occurs later.” In the letter, BOPCO’s representative stated that, “[according to section 6.1 and section 2 of the contract, the term of the agreement is 1095 days from March 20, 2007 and thus an early termination payment of approximately $4,228,000 (adjusted to final rig release date if after 5/21/09) will be payable by BOPCO, L.P to H & P within 30 days of receipt of an invoice.” BOPCO’s representative requested H & P to send such an invoice. In response, H & P took the position that, based on the applicable provisions of the contract, the 1,095-day contract term began on the date that it commenced operations under the contract. Therefore, in an e-mail to BOPCO, a representative of H & P stated that “[t]he days remaining in the term, for purposes of Paragraph 27.7, must be calculated from *804 commencement, which was on or after delivery of the rig on June 4, 2007.”

The rig release occurred on May 30, 2009; therefore, the contract was terminated on that date. H <& P calculated that 368.67 days remained on the 1,095-day contract term when BOPCO terminated the contract. Therefore, H & P billed BOPCO as follows: “368.67 Days x $14,500 Early Termination per day = $5,345,715.” BOPCO believed that 292.25 days remained on the 1,095-day contract term when it terminated the contract. Therefore, it paid H & P the amount of $4,091,500 (292.25 days x $14,000). After this case was filed in the trial court, BOP-CO paid H & P the additional sum of $146,125 ($500 x 292.25) because the parties had agreed to increase the early termination rate to $14,500 per day.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
357 S.W.3d 801, 181 Oil & Gas Rep. 396, 2011 Tex. App. LEXIS 9444, 2011 WL 5999026, Counsel Stack Legal Research, https://law.counselstack.com/opinion/helmerich-payne-international-drilling-co-v-bopco-lp-texapp-2011.