Hellar v. City of Tacoma

87 P. 130, 44 Wash. 250, 1906 Wash. LEXIS 821
CourtWashington Supreme Court
DecidedOctober 30, 1906
DocketNo. 6373
StatusPublished
Cited by1 cases

This text of 87 P. 130 (Hellar v. City of Tacoma) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hellar v. City of Tacoma, 87 P. 130, 44 Wash. 250, 1906 Wash. LEXIS 821 (Wash. 1906).

Opinion

Mount, C. J.

This appeal is from an order of the superior court of Pierce county, adjudging a contract between the city of Tacoma and the Barber Asphalt Paving Company void, and for that reason annulling an assessment made by the city to pay for certain street improvements made under the contract. The city appeals.

The facts are that the city of Tacoma, in the year 1905, passed a resolution and ordinance, providing for the paving of certain streets and alleys in said city, designating the district as “improvement district No. 252.” These improvements were ordered to be made at the expense of the property specially benefited thereby, payment to be made to the contractors in bonds which were to mature annually for a period of years. The commissioner of public works was directed to prepare plans and specifications and make estimates of the cost of the improvements, and to call for bids for the work. This was done, and upon public advertisement a contract was let to the Barber Asphalt Paving Company, and duly signed on March 29, 1905. By the terms of this contract and the specifications which were made a part thereof, [254]*254the work was to be completed within one hundred and sixty days after the execution of the contract, which provided:

“If said improvements be not completed within one hundred and twenty days after the execution of this contract, a demurrage will be charged as hereinafter set forth, but due allowance will be made for such days that rain prevents the execution of this work in a proper manner. The commissioner of public works shall decide the number of days to be allowed. Said time, however, shall not extend beyond the one hundred and sixty day limit.”

The demurrage provided for was $25 per day after one hundred and twenty days. The contract also provided that the work should be done under the supervision and to the satisfaction of the commissioner of public works. The paving company, after making the contract, entered upon the work, and continued to perform the same until about the 13th day of July, 1905, when the paving company was directed by authority of the commissioner of public works to cease work until other pavement which was being done in other districts adjoining district No. 252 could be brought up and fitted and connected to this work. In obedience to this request, the paving company ceased work on this contract until about September 14, 1905. The one hundred and sixty-day limit expired on September 5, 1905. On the next day these respondents served written notice on the commissioner of public works that the time limit for the. completion of the contract had expired, and demanded that he permit no further work by the paving company upon said contract, and that the commissioner of public works proceed to let a contract for the completion of the work; The commissioner of public works paid no attention to this notice, but permitted the paving company to finish the work on or about the 14th and 15th days of September, and thereafter accepted the completed work.

Subsequently an assessment roll was prepared, assessing the property of respondents and others specially benefited, for the payment of the cost of the improvement, viz.', $105,-[255]*255450. The respondents, representing property in the district assessed for about $41,000, appeared before the city council and objected to the assessment upon several grounds. All the objections were heard and considered by the city council and rejected. Respondents thereupon appealed to the superior court of Pierce county, but upon such appeal waived all of their objections except two, which are substantially as follows: That the charter provisions as to the time within which work must be done are mandatory and binding on all the parties, and the work not having been done within one hundred and sixty days, the contract is void; that the demurrage of $25 per day must be enforced against the contractor after one hundred and twenty days, even if the work was completed within the one hundred and sixty-day limit.

Upon trial to the court without a jury, the court found that the contract had not been completed within one hundred and sixty days as therein provided, and was therefore void; and concluded that the city of Tacoma had no power to levy an assessment for work done under the contract, and entered a judgment annulling the assessment in so far as the same affects the respondents’ property.

The question in this case is, did the commissioner of public works have authority for any reason'to stop the work under the contract, and thereby extend the time when the work should be finally completed? Respondents contend that he had no such authority. Appellant, while contending for the affirmative of the question, also insists that the work was substantially completed when it was stopped by the commissioner of public works; the facts in this respect being that the whole contract contained about forty thousand square yards of paving which had all been done except about eight hundred and thirty-six square yards, or, as is claimed by the respondents, about'one thousand four hundred and sixty-four square yards, which uncompleted work was at several street intersections. It was claimed that these intersections could [256]*256not be completed so as to make a good job until other work should be done on the intersecting streets, and that it was for the benefit of the city that the work was stopped in its incomplete state.

Under the view we take of the main question in the case, it will not be necessary to decide or to discuss the question of substantial performance. The city charter of Tacoma provides at § 160, that all public work authorized by the city council shall be done by contract under the supervision of the commissioner of public works; but before awarding any contract, the commissioner of public works shall cause notice to-be given inviting sealed proposals therefor. Section 164 provides that the notice shall contain a general description of the work to be done, the materials or supplies to be furnished, and the time within which the work is to be commenced and when to be completed, and shall refer to the plans and specifications on file in the office of the commissioner of public works for full details of the work. ’Section 165 provides that all contracts shall be drawn under the supervision of the city attorney and shall have attached thereto detailed specifications of the work to be done, which shall be referred to and made part of the contract; that every contract entered into by the commissioner of public works shall be signed by him and by the other contracting party, and that,

“ . . . the contract for work shall specify the time within which the work shall be commenced and when to be completed as was specified in the notice inviting proposals therefor. In case of failure on the part of the contractor to complete his contract within the time fixed, his contract shall be void, and the city shall not pay or allow him any compensation for work done by him under said contract.

“Sec. 166. If the contractor does not complete his work within the time limited therein, said commissioner of public \works may reject the unfinished portion óf said work after pursuing the formalities hereinbefore prescribed for the letting of the whole.

[257]*257“Sec. 167- The work in this article provided for must be done under the direction and to the satisfaction of the said commissioner of public works, and all materials and. supplies furnished must be in accordance with the specifications and to Ms satisfaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Irelan v. Portland
179 P. 286 (Oregon Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
87 P. 130, 44 Wash. 250, 1906 Wash. LEXIS 821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hellar-v-city-of-tacoma-wash-1906.