Helena Light & Ry. Co. v. Northern Pacific Ry. Co.

186 P. 702, 57 Mont. 93, 1920 Mont. LEXIS 4
CourtMontana Supreme Court
DecidedJanuary 2, 1920
DocketNo. 4,063
StatusPublished
Cited by18 cases

This text of 186 P. 702 (Helena Light & Ry. Co. v. Northern Pacific Ry. Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Helena Light & Ry. Co. v. Northern Pacific Ry. Co., 186 P. 702, 57 Mont. 93, 1920 Mont. LEXIS 4 (Mo. 1920).

Opinions

MR. JUSTICE MATTHEWS

delivered the opinion of the court.

The plaintiff instituted this action to recover from the defendant the sum of $1,016.75, alleged to be due for electricity furnished for lights and power during the months of May, June and July of the year 1915, at its special instance and request. The respondent admits the use and consumption of the electricity as alleged, but contends that said electricity was fur[100]*100nislied and was used, under a contract entered into between the parties hereto in the year 1910, under and' by the terms of which the amount due was $494.50, which amount respondent duly tendered to appellant, when due.

The ease was tried in the district court on an agreed statement of facts, from which it appears:

1. That on the third day of December, 1909, appellant and respondent entered into a written contract by the terms of which the appellant agreed to furnish to the respondent “all the electric current the railway company may require for lighting and power purposes at its pumping station — approximately two and a half miles west of the Northern Pacific Passenger Station, and at its roundhouse, machine-shop, ear-shop, coal dock, passenger and freight stations, lunch-room, offices and other buildings and premises at Helena, Montana.”

2. This contract or agreement was to continue in force for a term of five years from the date of the installation of the secondary lighting and power systems of the company, which installation was not completed until April 30, 1910.

3. The contract further provided that the railway company reserved the right, at its option, upon giving the power compány thirty days’ written notice prior to the expiration of the contract, “to renew the same for an additional period of five years. ’ ’

4. The rates fixed by the contract for electric current for power and light were about one-third the regular rates in effect in the months of May, June and July, 1915.

5. It is agreed that “the inducing cause or reason for entering into such a contract by the plaintiff at.the rates for electric current therein named was that the defendant was to use electric current and power at its pumping station — but the plaintiff did not state to the defendant what the inducing cause or reason was for entering into the contract.”

6. The agreed statement of facts recited further “that at or prior to the making of said contract neither the defendant nor its agent or representatives made any statement or representa[101]*101tion to tbe plaintiff, or its agents or representatives, regarding tbe amount of electric current to be used, or the time, manner or places of using said electric current, other than the statements and representations in said contract contained.”

7. The power company performed its part of the contract, and in doing so expended the sum of $948.78, in erecting a system to supply the current at the pumping station.

8. The railway company lived up to the terms of its agreement in all particulars, save and except that on or about November 27, 1913, it abandoned its pumping station, and consequently, since that date has used no electric current at or for the pumping station, which fact was known to the power company within thirty days thereafter, and no objection or protest was made by the power company to such abandonment or discontinuance of the use of electric current at the pumping station, but continued to furnish, and collect for, electric current, as formerly under the contract.

9. That on the twenty-first day of January, 1915, and within the time provided for in the contract, respondent notified appellant in writing that it desired to renew the contract for the additional term of five years under the option contained in the contract.

10. On April 28, 1915, the appellant notified respondent in writing that it would not renew the contract, on the ground that the respondent was “guilty of a breach of the contract in part during its existence”; the breach, as stated in the notice, consisted in the abandonment of the pumping station and the discontinuance of the use of electric current at that point, which, the notice recites, “was one of the principal items of the contract and greatly influenced in making the reduced rate”; and, continuing, said notice advised the railway company that from and after May 1, the power company would furnish light and power to the railway company at the rates regularly filed with the Public Service Commission.

11. It is further agreed that the current used by respondent at the pumping station amounted to 24% per cent of the electricity used by respondent under the contract.

[102]*102The court found in favor of the railway company and rendered judgment but for the amount due under the contract, and entered its decree to the effect that the contract in question had been duly extended and continued for the additional term of five years. The appeal is from the judgment.

The question here presented is: "Was there, during the months of May, June and July, 1915, a valid and existing contract in full force and effect ? Appellant contends that the contract was one which could not be renewed, for the following reasons:

1. That the respondent company violated the terms of the contract by abandoning its pumping station and its refusal to take any power.

2. A renewal of a portion of the contract only is desired.

3. Such contract is unlawful under the present statute.

We will take the matters suggested up in order and under the subheads employed in appellant’s brief.

1. The “inducing cause” referred to in the statement of facts [1] is relied upon to establish a breach of the contract. The contract was complete in itself, the result of the meeting of the minds of the contracting parties, and the obligations of each, as expressed, depend upon the corresponding obligations of the other, and on no extrinsic matter. (9 Cyc. 643.) Being in writing, the contract supersedes all oral stipulations of the parties. (Rev. Codes, secs. 5018, 7873.) This being so, it cannot be said that an inducing cause, in the mind of one of the contracting parties, undisclosed to the other, can thereafter be read into the contract as a part of the consideration for its execution.

Counsel contends that courts must give to a contract such a construction as was within the contemplation of the parties at the time they entered into it. This is true, but an “inducing cause” or motive, hidden in the breast of one, does not come within the rule. This court has said, in the case of Armington v. Stelle, 27 Mont. 13, 94 Am. St. Rep. 811, 69 Pac. 115; “Even if everything that was said and done at the time the lease was executed by the defendants were admissible, as defendants contend, for the purpose of showing what the con[103]*103tract actually was, the unexpressed motive or mental reservation entertained by the defendants could not aid the court in arriving at a correct conclusion, nor could the defendants be permitted to testify to it in order to modify or add to the express words of their contract.”

Mr. Elliott, in his work on Contracts, section 204, has this to say on the subject: “The ‘motive’ for entering into a contract and the ‘consideration’ of the contract, are not the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Savage v. State
453 P.2d 613 (Washington Supreme Court, 1969)
Brown v. American Bank of Commerce
441 P.2d 751 (New Mexico Supreme Court, 1968)
State ex rel. Preston v. Ferguson
170 Ohio St. (N.S.) 450 (Ohio Supreme Court, 1960)
Higby v. Hooper
221 P.2d 1043 (Montana Supreme Court, 1950)
Signal Oil Co. v. Commissioner
2 T.C. 90 (U.S. Tax Court, 1943)
Brown v. Homestake Exploration Co.
39 P.2d 168 (Montana Supreme Court, 1934)
In Re United Cigar Stores Co. of America
72 F.2d 673 (Second Circuit, 1934)
In Re United Cigar Stores Co. of America
8 F. Supp. 243 (S.D. New York, 1934)
Willapa Electric Co. v. S. L. Dennis Construction Co.
12 P.2d 609 (Washington Supreme Court, 1932)
Great Northern Utilities Co. v. Public Service Commission
293 P. 294 (Montana Supreme Court, 1930)
State Ex Rel. Federal Land Bank of Spokane v. Hays
282 P. 32 (Montana Supreme Court, 1929)
Hill Cattle Corporation v. Killorn
256 P. 497 (Montana Supreme Court, 1927)
City of Billings v. Public Service Commission
214 P. 608 (Montana Supreme Court, 1923)
Felder v. Hall Bros.
235 S.W. 789 (Supreme Court of Arkansas, 1921)
Harrington v. Moore Land Co.
196 P. 975 (Montana Supreme Court, 1921)
Blinn v. Hutterische Society of Wolf Creek
194 P. 140 (Montana Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
186 P. 702, 57 Mont. 93, 1920 Mont. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/helena-light-ry-co-v-northern-pacific-ry-co-mont-1920.