Heldenfels v. School Trustees of School Dist. No. 7, San Patricio County

182 S.W. 386, 1916 Tex. App. LEXIS 38
Court of Appeals of Texas·Decided January 5, 1916·No. No. 5544.·Published·Cited by 3 cases

Opinion

CARL, J.

C. A. Ileldenfels sued the trustees of school district No. 7 in San Patricio county, they being T. D. Cook, J. D. Ezell, and R. L. Anthony, on a certain building contract, entered into on October 12, 1912, between L. W. Franks as contractor and said trustees, wherein the said Franks agreed to erect a school building according to plans and specifications furnished, for the consideration of $11,425. Franks did not complete the contract, but assigned the same to C. A. Heldenfels and he alleges that he did finish the building, and therefore sued for $2,212.-37 alleged to be due on the contract price. 'The school board answered by demurrer and by traverse of every material issue, and, in a cross-action, sued plaintiff L. W. Franks, the original contractor, and the General Bonding & Casualty Insurance Company, which had made the bond of Franks. In this answer the trustees aJllege that Franks abandoned the building and declined to complete same under his contract, and, without the school board’s consent, pretended to assign the contract to C. A. Heldenfels. They say they notified Heldenfels that they would not accept the assignment of the Franks contract, but that, notwithstanding this notice, Heldenfels went to work upon the building. They also charge that the architects Stephenson & Ileldenfels were in collusion with Franks and C. A. Heldenfels for the purpose of constructing said building out of inferior and defective material; that F. W. Ilelden-fels, the architect, was a partner in a lumber yard at Beeville with plaintiff C. A. Hel-denfels ; and that Franks owed Heldenfels Bros, a large bill for lumber, and it was to the interest of said Heldenfels Bros, that the building be constructed as cheaply as possible so that there would be a greater profit in the contract, to the end that Franks’ debt could be collected. They say they did not at the time know that their architects were so interested, and that, in fact, F. W. Helden-fels, in approving work and material on the building, was really not acting for the board, but was acting contrary to their and in his own interest, and for this reason they are not bound by any of his acceptances, etc. Various and sundry items of damage and violations of the plans and specifications are alleged. The board further alleged that, if the assignment of the contract by Franks to G. A. Heldenfels was good, then he breached same by abandoning the building before it was completed, and that the defective material and construction damaged them to the extent of $2,982. The board had employed Marchant & Roberts, architects, to supervise the corrections and the finishing of the building, and they made the above estimate. It is alleged that the plumbing would cost $1,-000, wiring $150; and that the reasonable value of material and labor necessary to construct outside walks and toilet buildings is $645, for which Franks should have credit. Also, that the difference between the cost of the tile roof and metal roof which was put on the building was $520. Or, that the board was entitled to $1,6.70 by reason of such changes, etc., less $645 due Franks by reason of the toilets and walks — a net balance in their favor of $1,025. It was alleged that the board had paid Franks $9,900, and that they did not know of these defects, etc., at the time he was so paid. The contract provided that for each day over the time stipulated for the completion Of the building Franks was to pay $5 and for each day under that time he was to receive a like sum. Therefore the board claimed $4,008 against Franks and the bonding company. Appellants, Hel-denfels and Franks, denied these allegations; *388 and pleaded that the school board was estop-ped to deny that the contract was assigned, that it acquiesced therein and could not be heard to complain, and that the building was completed; and denied any iraud or collusion between the architects and Franks and Hel-denfels Bros.; and pleaded that such changes as were made in the building were made on written order of the school board. The bonding company pleaded that the contract it guaranteed was dated September 21, 1912, and the one that is alleged to have been breached was dated October 12, 1912, and that it was not liable for the breach of such subsequent contract and for changes of which it was never advised. The cause was submitted on special issues, and the judgment entered was that the plaintiffs take nothing, and that the school board recover as against Xj. W. Franks the sum of $446.63; but no recovery was had as against the bonding company and O. A. Heldenfels. Heldenfels and Franks have appealed.

[1] The first assignment of error is directed at the action of the court in admitting testimony as to the difference in cost of the tile roof provided in the contract and the metal roof placed thereon, because the change was ordered in writing in which it was stated that there would be no difference from that provided in the contract. The jury found that the value of the changes was not agreed upon, and the allowance to be made for these changes was $615. And there was a further finding that the architects were guilty of fraud on the school board in supervising the construction and in passing on and accepting material and workmanship in the construction of the building.

F. W. Heldenfels was one of the architects, and O. A. Heldenfels was the man who took over the Franks contract, and in answer to special issue No. 15 the jury found that there was no fraud as between the architects and L. W. Franks. Nor is there any finding that O. A. Heldenfels participated in the fraud of the architects, if they practiced such, on the school board. And, unless he did participate in the same, he would not be chargeable with the fraud. In trying to hold the bonding company, appellees asserted that they had complied with all the conditions of the contract, one of which wqs that “changes must be agreed upon in writing.” This they claim they complied with, and one of the trustees, Mr. Cook, in speaking of these changes, said:

“They (the architects) didn’t talk as if they wanted to change it. The change was finally made with their approval. It was in writing.”

Free access — add to your briefcase to read the full text and ask questions with AI

Heldenfels v. School Trustees of School Dist. No. 7, San Patricio County, 182 S.W. 386, 1916 Tex. App. LEXIS 38 (Tex. Ct. App. 1916).

182 S.W. 386 (Heldenfels v. School Trustees of School Dist. No. 7, San Patricio County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Flatonia Independent School Dist. v. Broesche
176 S.W.2d 223 (Court of Appeals of Texas, 1943)
Hastings v. Champer
139 S.W.2d 863 (Court of Appeals of Texas, 1940)
Baker v. East
197 S.W. 1123 (Court of Appeals of Texas, 1917)