Hejin Hong v. Nations Renovations, LLC

CourtCourt of Appeals of Texas
DecidedDecember 29, 2016
Docket05-15-01036-CV
StatusPublished

This text of Hejin Hong v. Nations Renovations, LLC (Hejin Hong v. Nations Renovations, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hejin Hong v. Nations Renovations, LLC, (Tex. Ct. App. 2016).

Opinion

Affirmed and Opinion Filed December 29, 2016.

In The Court of Appeals Fifth District of Texas at Dallas No. 05-15-01036-CV

HEJIN HONG, Appellant V. NATIONS RENOVATIONS, LLC, Appellee

On Appeal from the County Court at Law No. 4 Dallas County, Texas Trial Court Cause No. CC-14-00212-D

MEMORANDUM OPINION Before Justices Francis, Lang, and Stoddart Opinion by Justice Stoddart

This is an appeal from a final judgment following a jury trial in a suit to recover for

breach of a construction contract and quantum meruit. After fire damaged a rental house owned

by appellant Hejin Hong, she contracted with Nations Renovations, LLC to repair the house.

Nations alleged it performed significant additional work outside the scope of the construction

contract. When Hong failed to pay the balance due on the contract and for the additional work,

Nations sued her for breach of contract, quantum meruit, and other theories. The jury found

Hong breached the contract, Nations performed additional work outside the scope of the contract

for which it was not paid, and failed to find that Nations breached the construction contract. The

jury found damages for breach of contract and quantum meruit, and attorney’s fees. The trial

court rendered judgment on those findings. Hong raises six issues on appeal, arguing: the trial court erred by (1) rendering judgment

on quantum meruit when the parties had a written contract; (2) granting a directed verdict on her

counterclaim for DTPA1 violations, fraudulent inducement, and fraud; (3) refusing to submit jury

questions and instructions on those claims; (4) rendering judgment for Nations for attorney’s

fees, interest, and costs, where Nations was not a prevailing party and did not segregate its

attorney’s fees evidence; and that (5) the amount of attorney’s fees awarded through trial was

excessive; and (6) the evidence was factually insufficient to support the several of the jury’s

findings. As explained below, we reject these issues and affirm the trial court’s judgment.

BACKGROUND

On September 27, 2012, a rental house owned by Hong was damaged by fire. Hong

received offers from several contractors including Nations. On October 19, 2012, Hong signed a

contract with Nations for repairs to the house (the Contract). The Contract provided that Nations

would do the repairs at a price agreeable to Hong’s insurance company and Nations with no

additional cost to Hong except her deductible. At Hong’s request, four items were handwritten

on the Contract under the heading “Recommendations and Notes.”

After work began, Nations’s owner, Michael Cass, discovered that Hong’s insurance

policy covered only the actual cost value of the property at the time of the loss instead of the

replacement cost of property. As a result, Nations could not agree with the insurance company

to replace damaged property with new property. Except for the roof and certain items approved

by insurance, Nations repaired the damaged property or replaced it with used items. During the

repairs, Nations discovered other items damaged by the fire and submitted a supplemental claim

to the insurance company, which was approved.

1 TEX. BUS. & COM. CODE ANN. § 17.41–.63, known as the Deceptive Trade Practices-Consumer Protection Act. (“DTPA”).

–2– When the work was nearing completion, Cass and Hong discussed additional upgrades

and repairs including the items listed in the Recommendations and Notes section of the Contract

(the Extra Work). Cass explained he could not do the Extra Work under the Contract because

the insurance policy did not cover replacement value for upgrades or items not damaged by the

fire. Cass told her it would cost over $15,000 to do the Extra Work, but he would do it for as

close to $15,000 as possible. Hong denied discussing the Extra Work with Cass and said the

work was always included within the scope of the Contract.

Nations completed the original work under the insurance estimate. After inspection,

Hong’s mortgage company released the final insurance payment for that work. Nations also

completed the work under the supplemental insurance claim as well as the Extra Work. Nations

did the Extra Work for a total of $15,462.54. The city inspected the work during the repairs and

ultimately issued a certificate of occupancy.

The insurance company paid Hong $8,584.49 for the supplemental insurance claim,

which did not include her $1,000 deductible. When Nations requested the supplemental

insurance payment plus Hong’s deductible, she refused to pay and complained of several defects

in the work and delay in completing the project. Nations also requested payment for the Extra

Work, but Hong refused.

Nations continued to pursue its demands for payment. Hong’s husband, Wei Wei, a

patent attorney, responded in writing claiming Nations was liable to Hong for material breach of

the Contract, damages for delay and consequential losses, and DTPA violations. Nations then

filed suit against Hong and her husband for breach of the Contract, quantum meruit for the Extra

Work, and other claims. On its contract claim, Nations sought to recover the supplemental

insurance payment plus the replacement cost value of the work. After the suit was filed, Hong

voluntarily paid Nations $2,500 from the supplemental insurance claim.

–3– Hong and Wei defended the suit, raising affirmative defenses and filing several motions

for summary judgment. Hong filed a counterclaim for breach of the Contract, DTPA violations,

fraudulent inducement, and fraud. The trial court granted partial summary judgment denying

Nations’s argument for replacement cost value and its claims against Wei, resulting in his

dismissal from the suit. The case then proceeded to trial.

At the close of evidence, Nations moved for directed verdict on Hong’s DTPA,

fraudulent inducement, and fraud claims based on a disclaimer of reliance in the Contract. The

trial court granted the motion. The trial court submitted Nations’s breach of contract claim and

claims for the Extra Work, as well as Hong’s counterclaim for breach of contract, to the jury.

The jury charge included an instruction regarding segregating attorney’s fees.

The jury found Hong breached the Contract, Nations’ damages for that breach were

$7,084.49, Nations performed compensable work for which it was not paid, and damages for

quantum meruit in the amount of $15,462.54. Additionally, the jury found that Nations’s

reasonable and necessary attorney’s fees through trial were $61,400.00 and that Nations did not

breach the Contract.

The trial court rendered judgment for Nations against Hong in the amount of $22,547.03

(the total of the breach of contract and quantum meruit damages found by the jury), attorney’s

fees through trial in the amount of $61,400.00, conditional attorney’s fees for appeals as found

by the jury, pre- and post-judgment interest, and court costs.

STANDARD OF REVIEW

To evaluate the factual sufficiency of the evidence to support a finding, we consider all

the evidence and will set aside the verdict only if the evidence supporting the jury finding is so

weak or so against the overwhelming weight of the evidence that the finding is clearly wrong and

unjust. See Crosstex N. Tex. Pipeline, L.P. v. Gardiner, No. 15-0049, 2016 WL 3483165, at *24

–4– (Tex. June 24, 2016); Dow Chem. Co. v. Francis,

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
Varner v. Cardenas
218 S.W.3d 68 (Texas Supreme Court, 2007)
Forest Oil Corp. v. McAllen
268 S.W.3d 51 (Texas Supreme Court, 2008)
Smith v. Patrick W.Y. Tam Trust
296 S.W.3d 545 (Texas Supreme Court, 2009)
Haase v. Glazner
62 S.W.3d 795 (Texas Supreme Court, 2002)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
MBM Financial Corp. v. Woodlands Operating Co.
292 S.W.3d 660 (Texas Supreme Court, 2009)
Patton v. Saint Joseph's Hospital
887 S.W.2d 233 (Court of Appeals of Texas, 1994)
Schlumberger Technology Corp. v. Swanson
959 S.W.2d 171 (Texas Supreme Court, 1997)
Randy v. Squires Construction, Inc.
188 S.W.3d 396 (Court of Appeals of Texas, 2006)
RAS Group, Inc. v. Rent-A-Center East, Inc.
335 S.W.3d 630 (Court of Appeals of Texas, 2010)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
Ford v. Panhandle & Santa Fe Railway Co.
252 S.W.2d 561 (Texas Supreme Court, 1952)
Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)
Bocquet v. Herring
972 S.W.2d 19 (Texas Supreme Court, 1998)
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
995 S.W.2d 647 (Texas Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Hejin Hong v. Nations Renovations, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hejin-hong-v-nations-renovations-llc-texapp-2016.