Hegeman-Harris Co. v. Tebbetts & Garland Co.

262 Ill. App. 524, 1931 Ill. App. LEXIS 222
CourtAppellate Court of Illinois
DecidedOctober 9, 1931
DocketGen. No. 34,903
StatusPublished
Cited by2 cases

This text of 262 Ill. App. 524 (Hegeman-Harris Co. v. Tebbetts & Garland Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hegeman-Harris Co. v. Tebbetts & Garland Co., 262 Ill. App. 524, 1931 Ill. App. LEXIS 222 (Ill. Ct. App. 1931).

Opinion

Mr. Presiding Justice Gridley

delivered the opinion of the court.

In an action in assumpsit, commenced on April 22, 1930, and based upon a building contract, plaintiff (contractor) sought to recover of defendant (owner) the sum of $17,024.88. The cause was tried before the court without a jury and on November 18, 1930, the court found the issues in favor of defendant and entered a judgment against plaintiff for costs. The present appeal followed.

Plaintiff’s declaration consists of two special counts and the common counts. In the first special count the contract, dated March 17, 1928, is set forth in full. It is signed.by defendant, as first party and designated as the “Owner” and by plaintiff, as second party ahd designated as the “General Contractor.” It recites that on December 14, 1927, the parties entered into another contract by the terms of which the contractor was to commence the erection of a building at Nos. 16-30 West Washington street, Chicago; that it commenced the work; that complete plans and specifications have been drawn by Schmidt, Garden and Erik-son, architects; that in pursuance of the work already, done various contracts have been let for parts of the work by the contractor “in the name of and as the agent of the owner ’ ’; and that it has been determined to make a contract between the parties by which the contractor “shall become the General Contractor for the erection and construction of said building, according to said complete plans and specifications.” Then follow 24 paragraphs, some of which are in substance as follows:

Paragraph 1. The General Contractor (plaintiff) is to furnish all labor, materials, etc. necessary for the erection and completion of the store and office building on the premises, as called for by the complete plans and specifications and under the directions of the architects.

Par. 3. The Owner (defendant) is to pay to the General Contractor “the actual cost of said erection and completion plus a fixed fee to the General Contractor of five per cent (5%) on said actual cost” (except on the cost of the steel delivered on which the 'fixed fee is to be 2%) subject to the following qualifications, terms and conditions:

“The General Contractor hereby guarantees to the Owner that the cost of the erection and completion of said building (including the cost of all work heretofore contracted for and/or completed or partially completed by the General Contractor under said contract of December 14, 1927), including the fixed fee of said General Contractor, will not exceed the sum of $2,254,418, which, sum is hereinafter referred to as the ‘Maximum Guaranteed Cost,’ and if the actual cost of said building, as above defined, inclusive of the fixed fee of the General Contractor, exceeds said Maximum Guaranteed Cost, then the General Contractor agrees to pay from its own funds all amounts in excess of said Maximum Guaranteed Cost.” (Then follows the statement that in said Maximum Guaranteed Cost no provision has been made for seven mentioned items entering into said construction. Two of these items are (4) “the cost of bonds, if any, furnished by subcontractors,” excepting one mentioned bond already given, and (7) “the amount by which any subcontract let at the direction of the Owner shall exceed the amount of any bid for the same work received by the General Contractor from a subcontractor, who shall be approved by the Architects and whom the Owner directs the General Contractor not to contract with”). . . .

“In no event however shall the Owner be required to pay to the General Contractor a greater amount than the actual cost of the erection and completion of said building according to said complete plans and specifications, plus said fixed fee of said General Contractor, as aforesaid.”

Par. 4. “The General Contractor may with the written approval of the Architects and the Owner, sublet all or any portion of the work required to be done hereunder.” . . . “The question of requiring surety bonds from the subcontractors, or any of them, shall be determined by the General Contractor.”

“The General Contractor shall, however, and does hereby, assume full responsibility for the performance by the subcontractors, in the manner and under the conditions provided and required under the complete plans and specifications and the terms of this agreement, of the work called for by such subcontracts, and full responsibility for the performance of all work remaining unfinished under any and all contracts heretofore let by the General Contractor in the name of and as agent of the Owner” (subject to certain qualifications mentioned in succeeding paragraphs.)

Par. 10. The General Contractor is to submit monthly requisition statements to the Owner and Architects, showing all work done by it and the cost thereof, and also all work done and/or materials furnished by any subcontractor together with the amount due therefor. ‘‘Architects’ certificates shall be issued within ten (10) days after such requisition statement is made therefor for the amounts as determined by the Architects to be due the General Contractor for the work done by said General Contractor, including the proportionate ámount of the fixed fee then due to the General Contractor and for 85 per cent of the amount due any and all subcontractors. ’ ’

Par. 11. After the work of any subcontractor has been completed and a sufficient time has elapsed to demonstrate that such work has been properly done, etc., “all or any part of said 15 per cent reserved from the amount due any subcontractor shall, upon architects’ certificates be paid to the General Contractor for such subcontractor.”

Par. 13. “All moneys at any time paid hereunder to the General Contractor shall be deposited by it in a special bank account-in the Bank of America, in which no other funds are to be deposited except the special trust fund of $10,000, hereinafter provided for. The moneys in such special bank account at any time are to be applied and disbursed prior to the final completion and payment in full for said improvements only as follows :

1. To the payment of the amount due the General Contractor, as shown by the 'Architects’ certificates issued to it.

2. To the payment of the amount due the subcontractors, material men and others as directed by Architects’ certificates theretofore issued.” . . .

Par. 20. ‘1 The Owner reserves the right to require the General Contractor to employ a subcontractor designated by the Owner and approved by the Architects on any part of the work which is to be sublet; and to require the General Contractor to take bids on any part of the work which the General Contractor itself proposes to do, . . .”

In said first special count it is alleged that “plaintiff has done all things necessary for the construction and completion of the building as required under said contract”; that the building “was substantially completed and accepted by the Owner (defendant) more than one year prior to the date of the institution of this suit and has ever since been occupied and used by it and its tenants”; that the total “actual cost” for the construction and completion of the building, “exclusive of the cost of extras and additions. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Cash Register Co. v. Unarco Industries, Inc.
490 F.2d 285 (Seventh Circuit, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
262 Ill. App. 524, 1931 Ill. App. LEXIS 222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hegeman-harris-co-v-tebbetts-garland-co-illappct-1931.