Hefling v. City of Sharon

106 P.2d 680, 152 Kan. 512, 1940 Kan. LEXIS 12
Supreme Court of Kansas·Decided November 9, 1940·No. No. 34,771·Published·Cited by 4 cases

Opinion

The opinion of the court was delivered by

Thiele, J.:

This was an action brought by an engineer to recover from the defendant city for services alleged to have been rendered under the written contract hereafter mentioned. From an adverse judgment the city appeals, specifying various errors, among them being one that the trial court erred in not sustaining its demurrer to the plaintiff’s' evidence. The disposition of that specification will determine the appeal, and for that reason we have limited our statement of the pleadings and evidence.

[513] In the petition, after setting forth the status of the parties, it is alleged that on April 6, 1937, the plaintiff entered into a contract with the defendant city whereby plaintiff was employed as a consulting engineer to prepare reports, maps, plans, specifications and estimates and to supervise the construction of a complete waterworks and sewer system in the defendant city, a copy of the contract being attached as an exhibit; that in compliance with the contract, plaintiff prepared preliminary plans, etc., and rendered the services specified insofar as plaintiff was permitted by the defendant until about April 19, 1938, when the defendant breached its contract; that prior to that date plaintiff had prepared complete plans, etc., all of which were approved by the Federal Emergency Administration of Public Works; that at the time the contract was made, the parties had in contemplation the procuring of a grant from the above administration; that plaintiff assisted in matters preliminary to a bond issue and was at all times ready, willing and able to continue with the performance of the contract and to make the necessary and proper final maps, plans, etc., but defendant failed and refused to accept the same and breached its contract. After reference to provisions of the contract, it is alleged that on December 23, 1938, the city contracted for the construction of a waterworks and sewer system in the amount of $30,802.50, and had completed such construction; that by reason thereof and by reason of the breach of the contract by the defendant, plaintiff was entitled to his compensation of five percent of $30,-802.50, or the sum of $1,540.12, plus $200 for the preliminary plans, etc., or a total of $1,740.12, for which he prayed judgment.

So far as need be noticed, the contract, dated April 6 1937, provided plaintiff was to make all necessary reports, maps, etc., for the construction of a complete waterworks and sewer system in the defendant city, and to submit the same to the city for its approval; to attend necessary meetings of the governing body of the city to explain the reports, plans, etc.; to be present at all lettings for construction and to advise the city with respect to the awarding of contracts. Provisions as to a supervising engineer and his compensation need not be noticed, for no claim thereunder was made. It was further provided that as total compensation the city was to pay plaintiff a sum equal to five percent of the total construction cost, payable in the following manner: As compensation for preparing preliminary plans, etc., $100 for each project when the plans, etc., were filed with the city; two percent when the contracts were [514] awarded and construction work commenced under the approved procedure of any governmental agency; two percent upon monthly estimates allowed to the contractor, and the balance at the time the work was completed and accepted.

The answer denied generally, admitted execution of the contract but denied it was lawfully executed, alleged that plaintiff did submit certain plans, etc., for a waterworks system, and about January 27, 1938, sent his voucher to the city for $100, which was thereafter paid; that the plans, etc., were rejected as it was the intent of the city to build both a waterworks and sewer system; that the city paid plaintiff the sum of $100 in full for all services and that afterwards plaintiff had performed no service and the city was not further indebted to him; that on April 15, 1938, plaintiff addressed a letter to the mayor of the city stating he did not intend to charge the city for the sewer plans because of his conversation when it was suggested they wait and see what was going to happen, but that he had a few days’ spare time and had completed the plans. The city prayed the plaintiff take nothing.

Plaintiff’s reply was a general denial except for an admission he had received the $100.

Plaintiff’s evidence disclosed the following: Smith testified he was an employee of plaintiff and negotiated the contract on April 6, 1937, and in about ten days thereafter he made preliminary surveys for completing the water and sewer systems, which were submitted to the city for its approval about April 20th or 25th, and that these specifications were accompanied by an application to the Federal Works Administration for a grant of aid.

It was shown by the city’s records that the contract with the plaintiff was made April 6, 1937, and that later, on April 22, 1937, Smith met with the governing body and submitted plans for a waterworks system and a resolution directing the mayor to make application for federal aid. Although not so stated, the inference is that the resolution was adopted. At a later meeting on August 16, 1937, the governing body adopted a resolution calling for an election on a bond issue for a waterworks (not sewer) system, the bond issue to be $16,500 and to be supplemented by a federal grant, the total cost not to exceed $30,000. The city clerk testified that contracts for a waterworks and sewer system were let in the latter part of 1938, the exact date not being shown, although it is alleged in the petition to be December 23, 1938, and that the aggregate cost was [515] $38,543.71; that one contract was for tank, tower and footings, a second was for pump, well and pump house, and the third was for the water and sewer system combined.

Free access — add to your briefcase to read the full text and ask questions with AI

Hefling v. City of Sharon, 106 P.2d 680, 152 Kan. 512, 1940 Kan. LEXIS 12 (kan 1940).

106 P.2d 680 (Hefling v. City of Sharon) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Knoche v. Meyer Sanitary Milk Co.
280 P.2d 605 (Supreme Court of Kansas, 1955)
Ort v. Allied Industries, Inc.
203 P.2d 234 (Supreme Court of Kansas, 1949)
Burton v. Ostertag
201 P.2d 676 (Supreme Court of Kansas, 1949)
Evans v. Thornton
152 P.2d 853 (Supreme Court of Kansas, 1944)