Hedin v. United States

69 F. Supp. 113, 107 Ct. Cl. 558, 1947 U.S. Ct. Cl. LEXIS 83
CourtUnited States Court of Claims
DecidedJanuary 6, 1947
DocketNo. 45407
StatusPublished

This text of 69 F. Supp. 113 (Hedin v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hedin v. United States, 69 F. Supp. 113, 107 Ct. Cl. 558, 1947 U.S. Ct. Cl. LEXIS 83 (cc 1947).

Opinion

Madden, Judge,

delivered the opinion of the court:

The plaintiff, an individual, was formerly a member of a partnership which, on July 23, 1938, made a contract to [589]*589construct two buildings for the Veterans Administration at Bedford, Massachusetts. The plaintiff has succeeded to the rights of the partnership under the contract. In this opinion the word “plaintiff” will be used, for convenience, to describe either the partnership or the individual plaintiff, when activities in relation to the contract are discussed.

The first ground of claim asserted by the plaintiff is that the Government made an excessive deduction from the contract price, because the amount of rock actually excavated turned out to be only 42% cubic yards, whereas the estimated amount stated in the contract was 1200 cubic yards. Our findings 3, 4, and 5 show that the invitation for bids and the contract stated that the estimated quantity of rock to be excavated was 1200 cubic yards, and that if there should be more or less than that amount, when the actual excavation was done, an addition to or a deduction from the contract price should be made at the rate of $7.00 per cubic yard. The very great deficiency of rock resulted, of course, in a large deduction. The plaintiff says that the contract, properly construed, did not authorize the application of the $7.00 rate to so large a deficiency; that the parties contemplated, when they made the contract, that any excess or deficiency which would be found would be relatively small and would therefore have no important bearing on the contract price. The plaintiff says that in fact the current price at Bedford for excavating rock was $3.00 per cubic yard and that he subcontracted the excavation work for that price. In his adjustment of the deficiency with his subcontractor he was, therefore, only able to deduct $3.00 per cubic yard for the deficiency, and hence bore a loss of $4.00 per cubic yard as a result of the deduction. The plaintiff urges that, since the rate of deduction stated in the contract was not intended to apply to so large a deduction, the provisions of Article 4 of the contract which we have quoted in our finding 6 are applicable, and hence the true situation, when discovered, should have been treated as a subsurface and latent condition differing materially from the condition contemplated in the contract, and therefore calling for an equitable adjustment of price rather than the application of the $7.00 rate, regardless of the lack of equity in the result of its application.

[590]*590We are inclined to agree with the plaintiff that the contract provision for deducting $7.00 per cubic yard is not applicable to the situation that developed in this case. The invitation for bids called for a lump sum bid for the work. It stated the estimated yardage of rock excavation, to assist the bidder in computing his bid. This was, it seems to us, a representation that this estimate was reasonably accurate, and was based upon some investigation or knowledge which would make it so. Then the invitation stated the $7.00 per cubic yard price for excesses or deficiencies in the estimated yardage. A bidder might well discover that this $7.00 price was wrong. If it was, and if he made a close bid based upon a materially smaller unit figure which the excavation would actually cost him, then if the yardage turned out to be much less than the estimated amount, he would be badly hurt by the deduction at the $7.00 rate which would be in excess of the figure he actually used in computing his bid. Hence we are inclined to think that a bidder who, in those circumstances, received the contract, would not be bound to permit a deduction to be made at the arbitrary figure for such an extraordinary deficiency of yardage.

The plaintiff has not, however, shown that his situation is like the one described above. He asks for an equitable adjustment of the deduction but he does not show us what would be an equitable adjustment. His subcontractor, Dooley Brothers, agreed to do the rock excavation for $8.00 per cubic yard, but that had no effect upon the plaintiff’s computation of his bid, for he had no communication with Dooley Brothers until several days after his bid was in and the contract signed. If he had other bids from persons who wished to subcontract the excavation work, or if he had so much as conversations with persons who told him what the local rate for rock excavation was, it would seem that he could easily have proved that fact. But he has not proved it. Being a Baltimore contractor and having, so far as the proof shows, no information about local rates at Bedford, it would have been unlikely that he would have estimated rock excavation at Bedford at an amount materially less than the figure stated in the invitation for bids to be the price [591]*591-for excavating rock. If the contracting officer had undertaken to arrive at an equitable adjustment with the plaintiff, he could not, if he had had before him the evidence which is before us, have determined what would be an equitable rate of deduction. It would not have been equitable to make the deduction at the $3.00 rate and leave the plaintiff with an unearned profit of $4.00 per cubic yard for a large quantity of rock which he did not excavate, but which he estimated in his bid at the $7.00 rate. The plaintiff is not entitled to recover on this portion of his claim.

The rest of the plaintiff’s claim relates to damages alleged to have been caused to him by interference by the W.P.A. with his work and that of his subcontractor for the brick work on the buildings,. Allen Construction Corporation, to whose use the plaintiff seeks to recover a part of the alleged damages.

The plaintiff’s contract for the buildings included the installation of such plumbing facilities as water lines, sanitary sewer lines, and surface water drain pipes to points five feet outside the exterior walls of the buildings. It was evident, therefore, that at those points connections would be made by others with these facilities, and they would be extended, through ditches, to their destinations away from the new buildings. As shown in our finding 19, Article 13 of the contract provided that the Government might award other contracts and that the plaintiff should cooperate with other contractors. The Government did carry on other work as a W. P. A. project, which work included laying sewer, water, and steam service lines, grading, leveling, and road and sidewalk construction. The plaintiff claims that the doing of this work by the W. P. A. interfered with his work and that of the Allen Company in two respects: first, in that ditches were dug and earth piled on the surface in the neighborhood of the buildings which the plaintiff was constructing, making it more difficult to carry materials, build scaffolding, etc.; second, that in its work of ditching and clearing, the W. P. A. used explosives, causing the workmen of plaintiff and the Allen Company to seek safety, thus interrupting their work.

[592]*592We have no doubt that the fact that the W. P. A. work was going on was an inconvenience to the plaintiff, and that he could have done his work more economically if the W. P. A. ditches and other work had not been in progress. But the Government had the right to do these other things, in fact the buildings which the plaintiff was building would have been of no use without the connections which the W. P. A. made through the ditches of which the plaintiff complains. Unless, therefore, the W.PA did its work in a manner inconsiderate of the plaintiff’s interests, there was no breach of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
69 F. Supp. 113, 107 Ct. Cl. 558, 1947 U.S. Ct. Cl. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hedin-v-united-states-cc-1947.