Heckler Electric Co. v. City of New York

186 Misc. 2d 77, 715 N.Y.S.2d 619, 2000 N.Y. Misc. LEXIS 449
CourtNew York Supreme Court
DecidedOctober 10, 2000
StatusPublished

This text of 186 Misc. 2d 77 (Heckler Electric Co. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heckler Electric Co. v. City of New York, 186 Misc. 2d 77, 715 N.Y.S.2d 619, 2000 N.Y. Misc. LEXIS 449 (N.Y. Super. Ct. 2000).

Opinion

OPINION OF THE COURT

Marcy S. Friedman, J.

In this action, plaintiff, Heckler Electric Co., Inc. (Heckler), seeks damages for breach of contract. Defendants, City of New York and New York City Transit Authority (City), move for partial summary judgment dismissing the first through fifth causes of action of the complaint.

It is undisputed that plaintiff and defendants entered into a contract for plaintiff’s performance of electrical work on defendants’ construction project; that plaintiff was to complete work under the contract within three years of the date of delivery of the general construction contract, by mid-January 1981; and that plaintiff was delayed in achieving substantial completion for approximately six months, until mid-July 1981.

It is further undisputed that the first through fifth causes of action of the complaint seek various damages for the delay. Defendants move for summary judgment on the ground that plaintiff is barred from seeking such damages based on plaintiff’s failure to comply with article 43 of the parties’ contract, which defendants contend required notice and documentation of delay damages.

Article 43 provides that where a contractor claims that damage was sustained due to the City’s fault, the contractor must, within a limited number of days after the damage is sustained, give the City a written statement “of the nature of the damage sustained” and “an itemized statement of the details and amount of such damage.”1

As a threshold matter, plaintiff appears to dispute that article 43 applies to claims for delay damages. In American [79]*79Std. v New York City Tr. Auth. (167 AD2d 494 [1990], lv denied 78 NY2d 860 [1991]), the Appellate Division, Second Department, held that a virtually identical provision was applicable to a contractor’s claim for delay damages. The Court further held that the contractor’s noncompliance with the provision required dismissal of the delay damage claim, notwithstanding that the contractor had given contemporaneous notice of the delays (specifically, the conditions which threatened to delay performance) under a different provision of the contract.

In Gemma Constr. Co. v City of New York (246 AD2d 451 [1998]), the Appellate Division of this Department was called upon to determine the applicability to a delay damage claim of a notice provision similar to that in American Std. (supra) and the instant case. The Court noted the American Std. holding but, for several reasons, held that the notice provision did not apply to delay damages.

First, the Gemma Court examined the notice provision in the context of the contract as a whole. The Court held that its requirement of contemporaneous notice was in conflict with another provision of the contract which permitted deferred notice of delay damages, and that application of the notice provision to delay damages would therefore violate “ ‘a cardinal rule of construction’ ” by rendering the delay damage provision meaningless. (Gemma Constr. Co. v City of New York, supra, at 454.)

The Court also noted that the notice provision was contained in an article of the contract, located within a chapter of the contract, which governed claims for damages for extra work. Moreover, the notice provision provided that the documentation of the damages was required “ ‘[i]f the Contractor shall also claim to be sustaining damages by reason of any act or omission of the City’.” (Gemma Constr. Co. v City of New York, [80]*80supra, at 455 [emphasis in the original].)2 Focusing on the use of the word “also” in this provision, the Gemma Court reasoned that the provision was applicable only where the plaintiff asserted a claim for delay damages as well as such other damages as extra work, but that it had “no application to a claim predicated entirely on the City’s delay.” (Id., at 455.)

While recognizing that prior authority “seem[ed] to accord universal application” to the notice provision (Gemma Constr. Co. v City of New York, supra, at 454) — that is, its application to delay damages — the Gemma Court concluded, upon review of the case law, that similar notice provisions had been applied to delay damage claims only where such claims had not been clearly differentiated from claims for extra work or other damages.

Gemma (supra) also supplied a rationale for distinguishing between extra work and delay damage claims for purposes of enforcement of such a notice provision: the Court explained that in the case of an extra work claim, detailed contemporaneous records of the work are necessary to enable the City to verify whether the extra work was done and, if so, whether the price was reasonable. In contrast, while delay damages may involve additional work performed on account of a delay, “ ‘delay damage claims seek compensation for increased costs * * * whether the costs result because it takes longer to complete the project or because overtime or additional costs are expended in an effort to complete the work on time’ [citation omitted].” (Id., at 453.) “A significant item in delay damages is the increase in fixed costs and overhead incurred by reason of the deferral of the completion date of the project.” (Id.)

Gemma (supra) clearly signaled this Department’s reluctance to apply a contemporaneous notice provision such as article 43 to a delay damage claim. However, the holding was grounded in the Court’s interpretation of a particular contract provision. Prior to Gemma, as the Court noted in its opinion, this Department had applied strict notice requirements to claims which included delay damages. (See, e.g., Nab-Tern-Betts v City of New York, 241 AD2d 379 [1997]; MRW Constr. Co. v City of New York, 223 AD2d 473 [1996], lv denied 88 NY2d 803.) Recently, in Healy/Yonkers/Atlas-Gest v City of New York (258 AD2d 363 [1999]) the Court upheld the dismissal of a delay [81]*81damage claim for failure to comply strictly with a damage documentation requirement. Interestingly, this decision cited American Std. v New York City Tr. Auth. (supra) approvingly. However, as the decision did not quote the notice provision in question, it cannot be determined whether it was the same as that involved in American Std. and the instant case.

Whether or not Healy/Yonkers/Atlas-Gest (supra) presages an erosion of the authority of Gemma (supra), this court concludes, based on interpretation of the contract, that article 43 is distinguishable from the contract provision in Gemma, and that it covers plaintiffs delay damage claim. More particularly, article 43, entitled “Contractor’s Claim for Damage,” appears in chapter 5 of the contract, entitled “Payments to Contractor.” Article 43 and chapter 5 do not contain any limitation as to the categories of damages to which they apply. Indeed, article 43 and chapter 5 do not refer to or distinguish between delay damages and damages for extra work. In addition, there is no other provision of the contract which expressly sets forth notice requirements for recovery of delay damages by the contractor.* *3 In contrast, the notice provision in Gemma was located within an article and chapter of the contract which governed damages for extra or disputed work as opposed to delay damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berley Industries, Inc. v. City of New York
385 N.E.2d 281 (New York Court of Appeals, 1978)
A.H.A. General Construction, Inc. v. New York City Housing Authority
699 N.E.2d 368 (New York Court of Appeals, 1998)
American Standard, Inc. v. New York City Transit Authority
167 A.D.2d 494 (Appellate Division of the Supreme Court of New York, 1990)
Huff Enterprises, Inc. v. Triborough Bridge & Tunnel Authority
191 A.D.2d 314 (Appellate Division of the Supreme Court of New York, 1993)
Lasker-Goldman Corp. v. City of New York
221 A.D.2d 153 (Appellate Division of the Supreme Court of New York, 1995)
MRW Construction Co. v. City of New York
223 A.D.2d 473 (Appellate Division of the Supreme Court of New York, 1996)
Nab-Tern-Betts v. City of New York
241 A.D.2d 379 (Appellate Division of the Supreme Court of New York, 1997)
Gemma Construction Co. v. City of New York
246 A.D.2d 451 (Appellate Division of the Supreme Court of New York, 1998)
Marek v. Alexander Laufer & Son, Inc.
258 A.D.2d 363 (Appellate Division of the Supreme Court of New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
186 Misc. 2d 77, 715 N.Y.S.2d 619, 2000 N.Y. Misc. LEXIS 449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heckler-electric-co-v-city-of-new-york-nysupct-2000.