Heavenly Days Crematorium, LLC v. Harris, Smariga & Associates, Inc.

32 A.3d 155, 202 Md. App. 252, 2011 Md. App. LEXIS 157
CourtCourt of Special Appeals of Maryland
DecidedDecember 1, 2011
Docket1453, Sept. Term, 2010
StatusPublished
Cited by1 cases

This text of 32 A.3d 155 (Heavenly Days Crematorium, LLC v. Harris, Smariga & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heavenly Days Crematorium, LLC v. Harris, Smariga & Associates, Inc., 32 A.3d 155, 202 Md. App. 252, 2011 Md. App. LEXIS 157 (Md. Ct. App. 2011).

Opinion

MATRICCIANI, J.

On October 29, 2009 appellant, Heavenly Days Crematorium, LLC (“Heavenly Days”), filed a complaint against appellee, Harris, Smariga and Associates, Inc. (“HSA”), in the Circuit Court for Frederick County seeking monetary damages for breach of contract and professional negligence. On August 16, 2010, the circuit court entered an order granting HSA’s motion to dismiss, without prejudice, for failure to file a certificate of qualified expert under Maryland Code (1973, 2006 Repl.Vol.), Courts and Judicial Proceedings Article (“CJP”) section 3-2C-02. Heavenly Days presents one question for our review, which we have edited for clarity: 1

I. Was the circuit court legally correct in granting HSA’s motion to dismiss for failure to file a certificate of qualified expert?

For the reasons set forth below, we answer yes and affirm the judgment of the circuit court.

FACTS AND PROCEEDINGS

Heavenly Days owns and operates the Greenbriar Kennels Memorial Crematorium (“crematorium”), an animal cemetery and crematorium in Urbana, Maryland. In August of 2004, Heavenly Days applied to move its crematorium—at that time operating in Rockville, Maryland—to its current location in *257 Urbana. The application process required Heavenly Days to obtain plan approval, zoning variances, and various building permits from the State of Maryland and Frederick County. Heavenly Days hired HSA, a firm that offers site planning and civil engineering services, to assist Heavenly Days with the permit application and approval process.

From 2004 through 2007, HSA employee Chris Mayo was Heavenly Days’s contact person during the application process. Mayo submitted a site plan to the Frederick County Planning Commission (“FCPC”) in the fall of 2004, and on January 19, 2005 the FCPC gave the site plan a conditional approval. There were seven conditions attached to the conditional approval, one of which was that construction of the crematorium had to begin within two years to vest the approval. Under the Frederick County Zoning Ordinance (“Zoning Ordinance”) site plan applicants may request a one-time six month extension, provided the request is made at least thirty days before the expiration of the two year conditional approval period. Zoning Ordinance § 1-19-3.220.

After the FCPC granted the conditional approval, other Frederick County agencies made comments on the site plan that needed to be addressed before the county would sign off on the site plan. Additionally, Heavenly Days wished to increase the size of the crematorium and HSA had to relocate the crematorium building because it had not accounted for the effect that the exhaust fans would have on dog kennels located outside the building. To address the comments and reflect changes in the site plan, Mayo worked with Heavenly Days and the FCPC to submit a revised site plan.

By the fall of 2006, however, certain issues with the site plan had not yet been resolved. The conditional approval was due to expire on January 19, 2007 unless a request for a six month extension was made by December 19, 2006. Mayo requested a December 15, 2006 meeting with the county to submit a revised site plan and request the six month extension. The county never responded to Mayo’s request, however, and the December 19 deadline passed without anyone requesting a six *258 month extension. On January 5, 2007 Mayo, along with representatives from Heavenly Days and its subcontractors, met with county planners and requested an extension. The county denied this request as untimely. Mayo submitted a revised site plan on January 10, 2007. The county did not approve the revised site plan before the January 19 deadline passed, and thus the original site plan’s conditional grant of approval lapsed.

Heavenly Days alleged that Mayo did not use reasonable care in preparing the site plan by failing to: (1) correct errors in Heavenly Days’s site plan; (2) satisfy timely the conditions of a conditional approval granted by the county, and; (3) request timely an extension to satisfy such conditions. Heavenly Days contends that Mayo’s negligence caused the site plan’s deficiencies; that as a result of Mayo’s negligence Heavenly Days incurred penalties and fines, suffered construction delays, and had to repeat certain construction tasks; and that Mayo’s negligence ultimately forced Heavenly Days to restart the application process.

Heavenly Days filed suit against HSA in the Circuit Court for Frederick County on October 29, 2009, seeking monetary damages for breach of contract and “professional negligence.” 2 On January 20, 2010 HSA filed a motion to dismiss for failure to state a claim upon which relief can be granted, arguing that Heavenly Days failed to make out a case for the breach of contract claim, and that Heavenly Days’s negligence claim was barred by the economic loss rule. On February 22, 2010 Heavenly Days filed an opposition to HSA’s motion to dismiss, and filed therewith an amended complaint. HSA withdrew its initial motion to dismiss, but on March 19, 2010 filed a motion to dismiss Heavenly Days’s amended complaint. HSA based this second motion to dismiss on Heavenly Days’s failure to file a certificate of qualified expert (“certificate”) *259 within ninety days of filing the original complaint as required by CJP § 3--2C-02. Heavenly Days’s opposition to HSA’s second motion to dismiss included as an exhibit a certificate identifying Thomas Lane as an expert qualified to testify on the standards of practice as a property line surveyor.

In an August 12, 2010 motions hearing, Heavenly Days asked the circuit court to exercise its discretion under CJP § 3-2C-02(c) to waive or modify the certificate requirement and extend the ninety-day deadline for filing the certificate. HSA argued that Heavenly Days had not made a timely showing of good cause to waive or modify the certificate requirement, and therefore the circuit court did not have discretion to do so. On August 16, 2010 the Circuit Court for Frederick County entered an order granting HSA’s motion to dismiss without prejudice. Heavenly Days filed timely notice of appeal to this Court on August 24, 2010.

DISCUSSION

I. Standard of Review

In Kearney v. Berger we reviewed the trial court’s grant of the defendant’s motion to dismiss a medical malpractice claim for failure to file a certificate under § 3-2A-04(b)(4). 182 Md.App. 186, 957 A.2d 682 (2008). We noted:

In reviewing a trial court’s grant of a motion to dismiss, the truth of all well-plead relevant and material facts is assumed, as well as all inferences which can be reasonably drawn from the pleadings. Dismissal at the trial court level will only be proper if, after assuming the allegations and permissible inferences flowing therefrom are true, the plaintiff would not be afforded relief, (internal quotation and citations omitted).

Id. at 190-91, 957 A.2d 682.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heavenly Days Crematorium, LLC v. Harris, Smariga & Associates, Inc.
72 A.3d 199 (Court of Appeals of Maryland, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
32 A.3d 155, 202 Md. App. 252, 2011 Md. App. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heavenly-days-crematorium-llc-v-harris-smariga-associates-inc-mdctspecapp-2011.