Healer v. Department of Environmental Protection

22 Mass. L. Rptr. 438
CourtMassachusetts Superior Court
DecidedDecember 22, 2006
DocketNo. 200600700
StatusPublished

This text of 22 Mass. L. Rptr. 438 (Healer v. Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Healer v. Department of Environmental Protection, 22 Mass. L. Rptr. 438 (Mass. Ct. App. 2006).

Opinion

Hines, Geraldine S., J.

The plaintiffs filed this action pursuant to G.L.c. 30A, §14 on February 17, 2006, seeking review of a Final Decision of the Commissioner of the Department of Environmental Protection (“DEP”). This DEP decision established that a parcel of land situated in Falmouth, Massachusetts, which was determined to be a vernal pool,3 does not meet the definition of isolated land subject to flooding4 and, therefore, is not protected under the Wetlands Protection Act, G.L.c. 131, §40, and attendant regulations. Defendant Town of Falmouth (“the Town”) filed an answer on May 15, 2006, asserting counterclaims of malicious prosecution and abuse of process. Defendant DEP filed an answer on May 23, 2006. The Town then filed a motion to dismiss on June 13, 2006, and Plaintiffs filed a special motion to dismiss the Town’s counterclaims on June 14, 2006. For the following reasons, the Town’s motion to dismiss is ALLOWED and Plaintiffs’ special motion to dismiss is ALLOWED.

BACKGROUND

This dispute arose out of the Town of Falmouth’s plan to construct the New Silver Beach Sewer Collection and Treatment System, a public sewer system in the New Silver Beach section of Falmouth, Massachusetts. The new system would collect sewer effluent from 210 homes in the area, transport it to a 5,000 square foot treatment facility to be situated on a one-acre parcel owned by the Town, and then discharge it onto an adjacent leaching field. These 210 homes had private sewer systems, many of which had failed, and the area had been declared a public health emergency. On January 9, 2002, the Town filed a Notice of Intent for the project with the Falmouth Conservation Commission (“CC”) pursuant to G.L.c. 131, §40 and local wetlands by-laws. On June 17, 2002, the CC issued an Order of Conditions approving [439]*439the project and concluded that the parcel designated as a vernal pool did not qualify as isolated land subject to flooding.

On August 15, 2002, a group called Falmouth Residents for Fair Sewage Treatment (“FRFST”) filed an appeal of the CC Order of Conditions in Barnstable Superior Court. The Court initially allowed the stay requested by FRFST, but it was subsequently vacated by the Massachusetts Appeals Court. On January 28, 2004, the Barnstable Superior Court (Cannon, J.) upheld the CC’s decision concerning the project, and specifically noted in dicta that there was no evidence before the CC conclusively demonstrating that the parcel qualified as isolated land subject to flooding. FRFST appealed the Superior Court decision. On June 6, 2005, the Appeals Court affirmed the Superior Court decision, and in dicta specifically upheld the CC’s conclusion that the parcel did not qualify as isolated land subject to flooding.

After the CC issued its Order of Conditions, FRFST requested that the DEP issue a Superceding Order of Conditions. On December 22, 2002, the DEP issued a Superceding Order of Conditions approving the construction of the sewer line and a Superseding Determination of Applicability for construction of the treatment facility. The DEP also concluded that the parcel did not qualify as wetland resources subject to state protection. On January 2, 2003, FRFST appealed the DEP decision to the Office of Administrative Appeals. On July 1, 2003 an Administrative Magistrate conducted a hearing, and issued a Recommended Final Decision on October 17, 2005 affirming the DEP’s decision. On November 11, 2005, the Commissioner of the DEP adopted the Magistrate’s decision, and FRFST subsequently filed a Motion for Reconsideration. The Commissioner denied this motion on January 26, 2006, and the FRFST then filed the present action pursuant to G.L.c. 30A, §14.

DISCUSSION

A. The Town’s Motion to Dismiss

A motion to dismiss pursuant to Mass.R.Civ.P. 12(b)(6) should be granted only if “it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” General Motors Acceptance Corp. v. Abington Caves Ins. Co., 413 Mass. 583, 584 (1992), quoting Nader v. Citron, 372 Mass. 96, 98 (1977), quoting Coney v. Gibson, 355 U.S. 41, 45-46 (1957). For purposes of a motion to dismiss, all allegations in the plaintiffs complaint must be taken as true and the court must draw all reasonable inferences therefrom in favor of the plaintiff. Whitinsville Plaza, Inc. v. Kotseas, 378 Mass. 85, 87 (1979), quoting Nader, 372 Mass. at 98. A complaint is not subject to dismissal if it could support relief under any theory. Id. at 89.

The Town argues in its motion to dismiss that res judicata prevents this court from reviewing the DEP decision because the claims and issues asserted by the Plaintiffs have already been adjudicated in the Massachusetts Appeals Court. The Plaintiffs argue in opposition that res judicata does not apply because the Appeals Court reviewed the CC decision, and the claim before this court seeks review of the DEP decision. The CC and the DEP are two separate administrative agencies, and each issued a separate and distinct decision pursuant to its own wetlands protections scheme. The Plaintiffs correctly assert that the Appeals Court’s review of the CC decision does not address the same claims or issues as the claims and issues in the current action seeking review of the DEP decision. Thus, res judicata does not bar the present action.

The Town also alleges that the Plaintiffs’ claims pursuant to G.L.c. 30A, § 14 are moot because the local by-laws protecting wetlands are more stringent than state protections pursuant to G.L.c. 131, §40, particularly regarding isolated land subject to flooding and vernal pools.5 Specifically, the Town argues that the DEP lacks the power to supercede the CC decision because it was based on more stringent local by-laws, and thus this court cannot review the DEP decision because the CC decision governs. The earlier decisions in the Barnstable Superior Court and the Massachusetts Appeals Court regarding this parcel of land noted that the CC permissibly relied on Falmouth’s local by-laws in its evaluation. Additionally, according to Massachusetts case law, “[i]f a local wetlands protection by-law is more stringent than G.L.c. 131, §40, and the conservation commission operates thereunder, the DEP appears to lack the power to supersede the commission’s decision on a notice of intent to do work altering wetlands ...” Conservation Comm’n of Falmouth v. Pacheco, 49 Mass.App.Ct. 737, 741 n.4 (2000), citing Hamilton v. Conservation Comm’n of Orleans, 12 Mass.App.Ct. 359, 367-70 (1981). See also Hobbs Brook Farm Prop. Co., LLP v. Conservation Comm’n of Lincoln, 65 Mass.App.Ct. 142, 149 (2005) (“when a local conservation commission rests its decision on a wetlands by-law that provides greater protection than the act, its decision cannot be preempted by a DEP superseding order”); DeGrace v. Conservation Comm’n of Harwich, 31 Mass.App.Ct. 132, 135 (1991), citing Golden v. Selectmen of Falmouth, 358 Mass. 519, 525-26 (1970) (“local authorities do have final power . . . where they are acting pursuant to an ordinance or by-law which is consistent with the act, but which permissibly imposes ‘more stringent controls’ than the minimum Statewide standards set by the Legislature”).

A comparison of the Falmouth by-laws c. 235 and attendant regulations, and G.L.c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Whitinsville Plaza, Inc. v. Kotseas
390 N.E.2d 243 (Massachusetts Supreme Judicial Court, 1979)
Golden v. Board of Selectmen of Falmouth
265 N.E.2d 573 (Massachusetts Supreme Judicial Court, 1970)
DeGrace v. Conservation Commission of Harwich
575 N.E.2d 373 (Massachusetts Appeals Court, 1991)
Hamilton v. Conservation Commission of Orleans
425 N.E.2d 358 (Massachusetts Appeals Court, 1981)
General Motors Acceptance Corp. v. Abington Casualty Insurance
602 N.E.2d 1085 (Massachusetts Supreme Judicial Court, 1992)
Nader v. Citron
360 N.E.2d 870 (Massachusetts Supreme Judicial Court, 1977)
Duracraft Corp. v. Holmes Products Corp.
691 N.E.2d 935 (Massachusetts Supreme Judicial Court, 1998)
Fabre v. Walton
781 N.E.2d 780 (Massachusetts Supreme Judicial Court, 2002)
Kobrin v. Gastfriend
821 N.E.2d 60 (Massachusetts Supreme Judicial Court, 2005)
Conservation Commission v. Pacheco
733 N.E.2d 127 (Massachusetts Appeals Court, 2000)
Plante v. Wylie
824 N.E.2d 461 (Massachusetts Appeals Court, 2005)
Wynne v. Creigle
825 N.E.2d 559 (Massachusetts Appeals Court, 2005)
Hobbs Brook Farm Property Co. v. Conservation Commission
838 N.E.2d 578 (Massachusetts Appeals Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
22 Mass. L. Rptr. 438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/healer-v-department-of-environmental-protection-masssuperct-2006.