H.E. Davis & Sons, Inc. v. North Pacific Insurance

248 F. Supp. 2d 1079, 2002 U.S. Dist. LEXIS 25839, 2002 WL 32054623
CourtDistrict Court, D. Utah
DecidedAugust 20, 2002
Docket2:01CV139S
StatusPublished
Cited by9 cases

This text of 248 F. Supp. 2d 1079 (H.E. Davis & Sons, Inc. v. North Pacific Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H.E. Davis & Sons, Inc. v. North Pacific Insurance, 248 F. Supp. 2d 1079, 2002 U.S. Dist. LEXIS 25839, 2002 WL 32054623 (D. Utah 2002).

Opinion

MEMORANDUM DECISION

SAM, Senior District Judge.

Before the court is a motion for summary judgment submitted by defendant North Pacific Insurance Company. On June 13, 2002, the court heard oral argument on defendant’s motion. Present were John R. Lund, Esq., representing defendant, and George M. Allen, Esq., representing plaintiff H.E. Davis & Sons, Inc. The court, having reviewed and carefully considered the parties’ briefing and oral presentations, is now prepared to render the following ruling.

FACTUAL BACKGROUND

The following undisputed facts have been gleaned from the parties’ briefing. Plaintiff is a family-owned excavation and paving company headquartered in Spanish Fork, Utah. In 1994 and 1995, plaintiff performed site preparation, fill, and compaction construction for the building of the Spanish Fork Middle School. It did so under a contract with the Nebo School District. Plaintiff completed the work, and Mr. Earl M. Davis, son of founder Harry Davis and now head of the company, was satisfied that the work had been done properly at the time it was completed.

Shortly thereafter, however, it was discovered that the soils placed by plaintiff were not sufficiently compacted. Although it must be presumed that plaintiff had some responsibility for this problem, the central reason for the inadequate compaction appears to be the mistake of the soils engineer in specifying the method and/or standards for the compaction. In a cooperative effort with the school district to solve the problem, plaintiff, at its own cost, removed the offending soils and replaced them with properly compacted material.

Plaintiff notified defendant of the circumstances and demanded that defendant respond. Defendant had issued a commercial general liability insurance policy to plaintiff, including an endorsement that related specifically to the Spanish Fork Middle School project. 1 Defendant sent a claims representative to the site to investigate the problem.

During the course of the initial investigation, defendant corresponded in writing with plaintiff several times and contacted plaintiff by telephone to discuss the ongoing investigation. In September 1995, defendant responded to plaintiff with a letter detailing its investigation, reserving its rights, and denying coverage.

While plaintiff and defendant were involved with insurance coverage issues, a dispute developed between Nebo School District and Gramoll Construction Company, the company hired to build the Spanish Fork Middle School. Gramoll claimed it had suffered substantial damage resulting from Nebo’s undue delay in completing the construction of the school building. Ultimately, Gramoll obtained an arbitration award against Nebo.

In February 1999, the Nebo School District notified plaintiff that the district intended to pursue a claim against plaintiff relative to the Spanish Fork Middle School project. Defendant was not informed about and did not independently investi *1082 gate the factual contentions supporting Nebo’s specific claim against plaintiff. Correspondence in the record reveals that defendant confirmed receipt of information from plaintiff about Nebo’s claim and began analyzing the insurance policy to make a coverage determination relative to the arbitration award in favor of Gramoll and against Nebo.

Plaintiff brought suit against defendant in this court on March 14, 2000. That suit, however, was voluntarily withdrawn pursuant to a tolling agreement between the parties. After -withdrawing suit against defendant, plaintiff reached a settlement agreement with the Nebo School District. Plaintiff claims the cost of the 2000 settlement with Nebo plus the value of its cooperation with Nebo in 1995 total $862,717.00.

Plaintiff now brings suit against defendant claiming: (1) breach of contract, and (2) exemplary damages for willful misconduct. Plaintiff seeks to have defendant pay, as covered losses under plaintiffs insurance policy, costs relative to the following: (1) the removal, replacement, and re-compaction of the Spanish Fork Middle School site soil pad; (2) the removal and replacement of concrete footings poured by Gramoll Construction Company at the site; (3) plaintiffs 2000 settlement with the Nebo School District resulting from the arbitration award against Nebo and in favor of Gramoll; and (4) other events, including the possible delay of construction completion. Defendant moves for summary judgment on all of plaintiffs claims.

SUMMARY JUDGMENT STANDARDS

Under Rule 56 of the Federal Rules of Civil Procedure, summary judgment is proper only when the pleadings, affidavits, depositions or admissions establish there is no genuine issue regarding any material fact and the moving party is entitled to judgment as a matter of law. The burden of establishing the nonexistence of a genuine issue of material fact 2 is on the moving party. See Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). This burden has two distinct components: (1) an initial burden of production on the moving party, which burden when satisfied shifts to the nonmoving party; and (2) an ultimate burden of persuasion, which always remains on the moving party. See 10A Charles Alan Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure § 2727 (2d ed.1983).

When summary judgment is sought, the movant bears the initial responsibility of informing the court of the basis for the motion and identifying those portions of the record and affidavits, if any, he believes demonstrate the absence of a genuine issue of material fact. See Celotex, 477 U.S. at 323, 106 S.Ct. 2548. In a case where a party moves for summary judgment on an issue on which he would not bear the burden of persuasion at trial, his initial burden of production may be satisfied by showing the court there is an absence of evidence in the record to support the nonmovant’s case. 3 See id. “[Tjhere *1083 can be no issue as to any material fact ... [when] a complete failure of proof concerning an essential element of the nonmoving party’s case necessarily renders all other facts immaterial.” Id.

Once the moving party has met this initial burden of production, the burden shifts to the nonmoving party to designate “specific facts showing that there is a genuine issue for trial.” Fed.R.Civ.P. 56(e); Celotex, 477 U.S. at 324, 106 S.Ct. 2548.

If the defendant in a run-of-the-mill civil case moves for summary judgment ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acuity, a Mutual Insurance Co. v. McGinnis Homes, LLC
194 F. Supp. 3d 1204 (D. Utah, 2016)
Cincinnati Insurance Co. v. AMSCO Windows
593 F. App'x 802 (Tenth Circuit, 2014)
Cincinnati Insurance v. AMSCO Windows
921 F. Supp. 2d 1226 (D. Utah, 2013)
Continental Western Insurance v. Shay Construction, Inc.
805 F. Supp. 2d 1125 (D. Colorado, 2011)
Employers Mutual Casualty Co. v. Bartile Roofs, Inc.
618 F.3d 1153 (Tenth Circuit, 2010)
Great American Insurance v. Woodside Homes Corp.
448 F. Supp. 2d 1275 (D. Utah, 2006)
Green v. State Farm Fire & Casualty Company
2005 UT App 564 (Court of Appeals of Utah, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
248 F. Supp. 2d 1079, 2002 U.S. Dist. LEXIS 25839, 2002 WL 32054623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/he-davis-sons-inc-v-north-pacific-insurance-utd-2002.