H.E. Contracting v. Franklin Pierce

2005 DNH 047
District Court, D. New Hampshire·Decided March 17, 2005·No. CV-04-484-PB·Published

Opinion

H.E. Contracting v . Franklin Pierce CV-04-484-PB 03/17/05 P UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

H.E. Contracting

v. Civil N o . 04-484-PB Opinion N o . 2005 DNH 047 Franklin Pierce College

ORDER

H.E. Contracting (Plaintiff or “HEC”) filed a complaint against Franklin Pierce College (Defendant or “FPC”) on December 2 1 , 2004 asserting claims based o n , inter alia, breach of contract and quantum meruit (document n o . 1 ) . HEC concurrently filed a Petition for Ex Parte Attachment to Secure Mechanic’s Lien (document n o . 4 ) . The Court granted HEC permission to attach certain real estate held by the Defendant in the amount of $600,000.00 on December 2 3 , 2004 (document n o . 5 ) .

Before the Court for consideration is the Defendant’s objection to Plaintiff’s petition for ex parte attachment and to this Court’s order of December 2 3 , 2004 (document n o . 1 3 ) . The Court held a hearing on the objection on February 4 , 2005 and March 7 , 2005. For the reasons set forth below, the Court finds that the amount of Plaintiff’s attachment should be reduced from $600,000.00 to $146,360.42.

Standard of Review

Pre-judgment attachments are available to secure satisfaction of judgments “under the circumstances and in the manner provided by the law of the state where the district court is held.” Fed. R. Civ. P. 6 4 . Under New Hampshire law, a mechanic’s lien is a statutory right that arises automatically upon the provision of labor or materials. See N.H. Rev. Stat. Ann. (“RSA”) Chapter 447:2. 1 The lien provides security against the property owner for the value of the labor or materials rendered. Pine Gravel, Inc. v . Cianchette, 514 A.2d 1282, 1285 (N.H. 1986).

Under the statute, a labor and materials lien continues for 120 days after the services are performed or the materials are furnished. RSA 447:9. The lien may be secured by attachment of the property upon which it exists at any time while the lien

1 RSA 447:2 provides in relevant part that:

If any person shall, by himself or others, perform labor or furnish materials to the amount of $15 or more for erecting or repairing a house or other building or appurtenances, . . . , by virtue of a contract with the owner thereof, he shall have a lien on any material so furnished and on said structure, and on any right of the owner to the lot of land on which it stands.

(emphasis added).

continues. RSA 447:10. The lien holds a favorable priority position with respect to other creditors in that it takes precedence over all prior claims except tax liens. RSA 447:9.

RSA 511-A, which governs procedures for pre-judgment attachments, applies to proceedings to secure liens under RSA 447. Chagnon Lumber Co., Inc. v . Stone Mill Constr. Corp., 474 A.2d 5 8 8 , 589 (N.H. 1984). “RSA chapter 511-A was enacted in 1973 to conform the law of this State to standards of due process.” Id.

RSA 511-A generally requires notice and an opportunity to be heard before a pre-judgment attachment is made. See RSA 511-A:1 and A : 2 . Under RSA 511-A:8, however, courts may grant certain attachments without prior notice to the defendant “if the plaintiff establishes probable cause to the satisfaction of the court of his basic right to recovery and the amount thereof.” A specific exemption from the prior notice requirement is provided in cases where the plaintiff seeks to perfect a labor and materials lien under RSA 447. See RSA 511-A:8(III); see also Chagnon Lumber, 474 A.2d at 589. After an ex parte attachment is granted, the defendant is given notice and is entitled to a prompt hearing upon request. See RSA 511-A:8.

In Judge Manias’ convincing and well-written opinion in Consolidated Elec. Distrib., Inc. v . SES Concord Co., N o . 89-C- 571/579 (Merrimack Superior Ct., Nov. 2 1 , 1989) (copy attached to Plaintiff’s Reply to Defendant’s Objection as Exhibit 1 ) , the court held that the provisions of RSA 511-A:3, which require a plaintiff to demonstrate a likelihood of success on the merits to obtain an attachment, and permit a defendant to avoid an attachment by establishing that its assets are sufficient to satisfy a judgment, do not apply in a proceeding on a mechanic’s lien under RSA 447. The court found that applying RSA 511-A:3 to mechanic’s lien proceedings “would frustrate the underlying purpose and design of the mechanics lien statute” in that it could cause a plaintiff to lose its statutory entitlement to an attachment and priority status in bankruptcy. Id. at 5-8. Accordingly, notwithstanding Defendant’s argument to the contrary, I find that the provisions of RSA 511-A:3 do not apply to the determination of whether the ex parte attachment granted to the Plaintiff in this case was appropriate.

According to the court in Consolidated Elec., the content and focus of a post-attachment hearing on a mechanic’s lien is whether the plaintiff has met its burden under RSA 511-A:8, which

defendant may rebut. Id. at 6. The defendant may challenge the plaintiff’s basic right to recovery under RSA 4 4 7 , the lien amount, or notice provisions. Id.; see also West Side Dev. Group, LLC v . D’Amour, N o . 04-C-018, (Carroll County Superior Ct., March 2 4 , 2004) (copy attached to Plaintiff’s Reply to Defendant’s Objection as Exhibit 2 ) (finding that the provisions of RSA 511-A:3 specifying the “reasonable likelihood of success test” and the “sufficiency of assets test” do not apply to a mechanic’s lien proceeding under RSA 4 7 7 ) . The Court applies the standard of review employed in Consolidated Elec. in considering the Defendant’s objection to Plaintiff’s ex parte attachment.

Background

In April 2004, the Defendant invited Eric Lenardson, President of HEC, to bid on work related to the construction of athletic fields and associated facilities on land held by FPC. Plaintiff’s initial bid for the entire project amounted to between $3,700,000 and $4,160,000 depending upon various options that could be chosen by FPC.

After reviewing the bids that it received, FPC determined that all of the bids exceeded its budget. FPC requested that certain contractors, including the Plaintiff, submit separate

bids for portions of the project including the site work, artificial turf installations, site lighting, and the construction of press-boxes and dugouts. Plaintiff made a new proposal for “the clearing and grubbing of project site to prepare for design/build soccer field and baseball field.” Pl.’s Ex. 10. 2 Plaintiff stated that its price to provide “base work, drainage and artificial turf (E-turf) was $1,189,000.” Id. Plaintiff stated that its price “for Base work only” was $625,000. Id.

Defendant awarded Plaintiff a site work contract in May 2004 for which the parties agreed that Plaintiff would be paid $625,000. Pl.’s Ex. 1 1 . Defendant paid Plaintiff $375,000, or sixty percent of the contract price, in advance. Id. Defendant issued a purchase order to HEC in connection with the $375,000 payment dated June 7 , 2004 that stated that the payment was for “construction contract to provide all site work, as per contract to follow.” Id. Although Plaintiff began working at the project site on June 2 , 2004, the contract between the parties is dated June 9, 2004. Pl.’s Ex. 6.

2 Citations to exhibits refer to the exhibits introduced during the post-attachment hearing unless otherwise noted.

In late July 2004, Plaintiff submitted nine change orders.3 Defendant requested that Plaintiff provide documentation to support those change orders. Plaintiff next submitted a requisition dated August 1 6 , 2004, asserting that it had completed ninety percent of its work under the contract and was entitled to an additional payment of $187,500.00. Df.’s Ex. D. Defendant rejected the requisition.

Free access — add to your briefcase to read the full text and ask questions with AI

H.E. Contracting v. Franklin Pierce, 2005 DNH 047 (D.N.H. 2005).

2005 DNH 047 (H.E. Contracting v. Franklin Pierce) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Williams v. United States
382 A.2d 1 (District of Columbia Court of Appeals, 1978)
D. M. Holden, Inc. v. Contractor's Crane Service, Inc.
435 A.2d 529 (Supreme Court of New Hampshire, 1981)
Black v. National Football League Players Ass'n
87 F. Supp. 2d 1 (District of Columbia, 2000)
H.E. Contracting v. Franklin Pierce College
360 F. Supp. 2d 289 (D. New Hampshire, 2005)
Pine Gravel, Inc. v. Cianchette
514 A.2d 1282 (Supreme Court of New Hampshire, 1986)