HDR Engineering, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 15, 2025
Docket62723
StatusPublished

This text of HDR Engineering, Inc. (HDR Engineering, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HDR Engineering, Inc., (asbca 2025).

Opinion

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) HDR Engineering, Inc. ) ASBCA No. 62723 ) Under Contract No. W912EP-10-D-0017 )

APPEARANCES FOR THE APPELLANT: Douglas L. Patin, Esq. Lee-Ann C. Brown, Esq. Bradley Arant Boult Cummings LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney John F. Bazán, Esq. Patrick Sean Murphy, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Los Angeles

OPINION BY ADMINISTRATIVE JUDGE O’CONNELL

Appellant, HDR Engineering, Inc. (HDR), appeals a final decision in which the United States Army Corps of Engineers (USACE) asserted a government claim for professional negligence related to the design of a dam. The Board conducted a hearing from May 13-20, 2024. Both entitlement and quantum are before us. The Board sustains the appeal. FINDINGS OF FACT

This appeal arises from a project with a lengthy history. We will start with a brief description of the overall project, then summarize the three construction contracts, and finally describe HDR’s design contract and task orders.

The Project

1. The project is known as the C-44 Reservoir/Stormwater Treatment Area, which is part of a Comprehensive Everglades Restoration Plan (R4, tab 12 at 5 1). “C-44” is the name of a canal. The water in the C-44 Canal comes from the C-44 Basin, a 202-square-mile area in Martin County, Florida. (R4, tab 12 at 5-6) The purpose of the project is to improve water quality and slow down the flow of freshwater during rain events from the canal into the St. Lucie Estuary. The project

1 Citations are to the .pdf page number in the electronic file. NOT FOR PUBLIC DISTRIBUTION This document contains protected material and is subject to the terms of an ASBCA Protective Order.

pumps water from the C-44 Canal into an elevated reservoir that is surrounded by a 30-foot-high embankment dam. Water from the reservoir then flows by gravity through a discharge canal to stormwater treatment cells in which aquatic plants remove nitrogen and phosphorous. Water from the cells is then discharged into collection canals and then back into the C-44 Canal. (Id. at 5-6, 29; app. supp. R4, tab 2482; tr. 5/17-19) It takes about two weeks for water to pass through this system (tr. 5/18).

2. In the 2000s, the project was managed by the South Florida Water Management District (SFWMD), a water district in the state of Florida. Fla. Stat. § 373.069(1)(e). SFWMD planned on building the project through a single construction contract (R4, tab 14 at 8). SFWMD retained HDR as the designer sometime prior to August 1, 2005 (see app. supp. R4, tab 2154). Between 2005 and 2008 HDR produced extensive documentation for SFWMD (app. supp. R4, tabs 2038-2043, 2154, 2155), including a Basis of Design Report dated April 14, 2006 (app. supp. R4, tab 2040), and drawings marked “Issued for Bid” dated April 18, 2008 (app. supp. R4, tab 2043).

3. At some point between 2008 and 2010, USACE became involved with the project. USACE and SFWMD decided to divide the construction contract into three contracts, with USACE responsible for the first two contracts, and SFWMD responsible for the third (tr. 3/161-62).

4. Contract One was for an intake canal and a project access road. Contract Two, the contract relevant to this appeal, included the reservoir, an intake pump station and outlet works, and the embankment dam. The reservoir was designed to have a storage volume of 50,600 acre-feet 2 of water and had an exterior perimeter of 9.3 miles. Contract Three included the stormwater treatment areas. (R4, tab 12 at 7, 29; tab 14 at 8; tr. 6/69) The project site covers approximately 12,000 acres (18.75 square miles) (app. supp. R4, tab 2062 at 6).

5. On July 23, 2010, USACE entered into a contract with HDR. The contract described the scope of work as “providing engineering services to complete the C-44 Reservoir and STA Project in compliance with USACE standards.” (R4, tab 3 at 1, 17) The contract provided that HDR would perform the work pursuant to task orders (id. at 18). The contract incorporated Federal Acquisition Regulation (FAR) 52.236-23, Responsibility of the Architect-Engineer Contractor (Apr 1984) (the “Architect-Engineer clause”) (R4, tab 2 at 77). This clause provides:

2 An acre-foot is the volume of water necessary to cover one acre of land with water to a depth of one foot and is equal to approximately 325,580 U.S. gallons. Stockton E. Water Dist. v. United States, 583 F.3d 1344, 1349 n.6 (Fed. Cir. 2009).

2 NOT FOR PUBLIC DISTRIBUTION This document contains protected material and is subject to the terms of an ASBCA Protective Order.

(a) The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings, specifications, and other services furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other services.

(b) Neither the Government’s review, approval or acceptance of, nor payment for, the services required under this contract shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of this contract, and the Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor’s negligent performance of any of the services furnished under this contract.

(Id.)

6. While this clause specifies the designer’s professional responsibilities, the contract also required HDR to design within USACE’s budget. The contract incorporated FAR 52.236-22, Design Within Funding Limitations (Apr 1984), which provides that: “(a) The Contractor shall accomplish the design services required under this contract so as to permit the award of a contract, using standard FAR procedures for the construction of the facilities designed at a price that does not exceed the estimated construction contract price . . . ” (R4, tab 2 at 76).

7. In August of 2010, HDR appointed Keith Ferguson as the designer of record for the embankment (tr. 1/18, 126). Mr. Ferguson has Bachelor of Science (1977) and Master of Science (1979) degrees in Civil Engineering from the University of Colorado and is a registered Professional Engineer in Florida and several other states (app. supp. R4, tab 2412 at 1). During his career, Mr. Ferguson has been involved in over 250 dam projects including numerous embankment dams on which he acted as the engineer of record, project manager and in other capacities (tr. 1/96; app. supp. R4, tab 2412 at 4-12). There is no dispute that Mr. Ferguson was well-qualified for this role.

3 NOT FOR PUBLIC DISTRIBUTION This document contains protected material and is subject to the terms of an ASBCA Protective Order.

The HDR Task Orders

8. Two task orders are relevant to the dispute. Task Order No. 3 in the amount of $569,882.03 is dated September 30, 2011 (R4, tab 12). The scope of work for this task order provides that it:

[i]s for the additional data collection, re-evaluation of existing data, analyses, and technical coordination necessary for the C-44 Reservoir . . . previously completed under separate contract to the South Florida Water Management District . . .

(id. at 5). As evidenced by this description, the work did not include a complete redesign.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stockton East Water District v. United States
583 F.3d 1344 (Federal Circuit, 2009)
City of Mounds View v. Walijarvi
263 N.W.2d 420 (Supreme Court of Minnesota, 1978)
Bonadiman-McCain, Inc. v. Snow
183 Cal. App. 2d 58 (California Court of Appeal, 1960)
Coombs v. Beede
36 A. 104 (Supreme Judicial Court of Maine, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
HDR Engineering, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/hdr-engineering-inc-asbca-2025.