HCE Pepperell, Inc. v. Energy Management, Inc.

2 Mass. L. Rptr. 351
CourtMassachusetts Superior Court
DecidedJuly 8, 1994
DocketNo. 91-8054F
StatusPublished

This text of 2 Mass. L. Rptr. 351 (HCE Pepperell, Inc. v. Energy Management, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HCE Pepperell, Inc. v. Energy Management, Inc., 2 Mass. L. Rptr. 351 (Mass. Ct. App. 1994).

Opinion

Fremont-Smith, J.

BACKGROUND

Cross-motions for summary judgment on defendants’ counterclaims have been submitted to the Court on an agreed statement of facts, for the Court’s findings, rulings and judgment, which are set forth below.

The dispute arises out of the construction of a co-generation plant in Pepperell, Mass. for the purpose of producing and selling electricity and steam. As part of Energy Management, Inc.’s (“EMI”) sale of a business to plaintiffs,3 the purchasers agreed that once the plant went into operation, plaintiffs would make quarterly payments to EMI under a Royalty Agreement and a Subordinated Note. Plaintiffs took custody and control of the plant from the general contractor in March 1990 and began to sell electricity and steam soon thereafter. They have, however, refused to make any payments, contending 1) that the substantial completion date has never occurred and 2) that payments are, in any event, prohibited under the provisions of the Subordinated Note, which prohibit payments during any period that the loan from Prudential Insurance Company is in default.

For the reasons stated below, summary judgment is entered for EMI, subject to the limitations indicated below on EMI’s right to receive payment or to levy on the judgment.

FINDINGS OF FACTS

PPA entered into a Royalty Agreement with EMI effective as of June 10, 1988 (the “Royalty Agreement"). Under §2.1 of the Royalty Agreement, PPA agreed to pay EMI $37,500 per quarter for the first fifteen years after the “Commercial Operation Date." Under §2.2, PPA agreed to make minimum royalty payments of $65,000 per quarter thereafter.

Also in June 1988, PPA executed a Subordinated Note (the “Subordinated Note”) in the amount of $5,250,000 evidencing PPA’s obligation to make royalty payments under §§2.1 and 2.2 of the Royalty Agreement for the first twenty-five years of the project. Section 5 of the Subordinated Note provides:

The indebtedness represented in this Note is expressly made subordinate and junior in all respects to the [Prudential] Debt on the basis of Annex D of the [Prudentiall Loan Agreement.

Annex D to the Prudential Loan Agreement, pursuant to which Prudential loaned PPA $41 million for construction, also provides that, if a Note given to Prudential was due, or if there was a default under the Loan Agreement, then no payment would be made by PPA to EMI. However, Annex D, paragraph (c) expressly recognized the right of EMI to bring suit against PPA to recover its indebtedness, as long as EMI agreed not to file any judgment liens or take any other action to levy on the property of PPA.4

Paragraph 2.1 of the Royalty Agreement provides that PPA would begin making quarterly royalty payments to EMI “on the first day following the last day of the first full calendar quarter following the Commercial Operation Date.” A similar provision appears in the Subordinated Note.

The “Commercial Operation Date,” as used in Paragraph 2.1 of the Royalty Agreement, is defined in paragraph 1.2 as “the Substantial Completion Date of the Project pursuant to a certain Construction Agreement dated as of February 29, 1988 between PPA and Blount International, Ltd.”

Under Section 6.4 of the Construction Agreement, “Substantial Completion” is defined as follows:

6.4. Substantial Completion. Substantial Completion shall be deemed to have occurred upon .the satisfaction of the following conditions:
6.4.1. performance testing of the Facility shall have been completed in conformance with the Test Procedures and such performance tests shall have satisfied the Guarantees, all in accordance with the procedures set forth in Section 6.1 through 6.3 hereof;
[352]*3526.4.2. the performance of the Work shall have been completed with the exception of those items specified in a punch list prepared by Contractor and agreed to by Owner, which items shall not cost more than $500,000 in the aggregate to complete and shall be of such a nature that their completion shall not in any way impair the normal daily operation of the Facility after Substantial Completion;
6.4.3. the Facility shall be ready to be occupied and operated for the use for which it was intended;
6.4.4. Contractor shall have delivered to Owner and the Lender’s Engineer all documents required to be delivered to them by Section 3.4;
6.4.5. Contractor shall have delivered to Owner and Lenders’ Engineer a notice signed by the Contractor certifying that all of the preceding conditions in this Section 6.4 have been satisfied; and
6.4.6. Lender’s Engineer shall have delivered to Owner a certificate stating that all of the preceding conditions in Section 6.4 have been satisfied.
Upon the satisfaction of all of the foregoing conditions, Owner shall accept the Facility, subject to Final Completion in accordance with Section 6.5 hereof, by delivering to Contractor notice of such acceptance, and Contractor shall turn over control and operation of the Facility to Owner. The date upon which such acceptance occurs shall be the “Substantial Completion Date.”

By March 1990, the Plant was operational, but tests indicated that the Plant did not satisfy certain performance guarantees under the Construction Contract.

On or about March 23, 1990, PPA entered into a written agreement with Blount (the “Care and Custody Agreement”). The Care and Custody Agreement provides (among other things) that:

a. PPA would take care, custody and control of the Plant from Blount effective March 23, 1990 (¶1);
b. Blount would have an additional 180 days to achieve certain Performance Guarantees identified in the Care and Custody Agreement and Construction Contract and to perform other work (¶2);
c. If Blount were unable to satisfy the Performance Guarantees within 180 days, then Blount would pay PPA liquidated damages, to be deducted to the extent possible from the retainage then being held by PPA (912(a));
d. If Blount concluded that further modification to the Plant would not satisfy the Performance Guarantees, Blount could elect to pay liquidated damages without waiting for expiration of the 180 day period (912(b)); and
e. Upon payment of liquidated damages, Blount “shall be deemed to have satisfied" the Performance Guarantees (12(b)).

(Emphasis supplied.)

In accordance with the Care and Custody Agreement, PPA was operating the Plant no later than March 28, 1990. On that date, PPA began selling electricity generated by the Plant to Commonwealth Electric Company.

On October 23, 1990, Blount notified PPA that the conditions contained in Sections 6.4.1 to 6.4.4 of the Construction Contract had been satisfied, and during 1991, Blount demanded arbitration against PPA for payments of the amount due under the Construction Contract. PPA denied that any sums were owing and sought an affirmative recovery against Blount. The arbitration took place under the Construction Industry Arbitration Rules of the American Arbitration Association.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wisnouse v. Telsey
367 F. Supp. 855 (S.D. New York, 1973)
Culp v. Tri-County Tractor, Inc.
736 P.2d 1348 (Idaho Court of Appeals, 1987)
Minority Equity Capital Co., Inc. v. Jackson
798 F. Supp. 200 (S.D. New York, 1992)
Johnson Controls, Inc. v. Bowes
409 N.E.2d 185 (Massachusetts Supreme Judicial Court, 1980)
Kurtz v. American Export Industries, Inc.
49 A.D.2d 557 (Appellate Division of the Supreme Court of New York, 1975)
Barry v. Frankini
191 N.E. 651 (Massachusetts Supreme Judicial Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
2 Mass. L. Rptr. 351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hce-pepperell-inc-v-energy-management-inc-masssuperct-1994.