Haycraft v. Mid-State Construction Co.

915 So. 2d 1117, 2005 Miss. App. LEXIS 1000, 2005 WL 3289393
CourtCourt of Appeals of Mississippi
DecidedDecember 6, 2005
DocketNo. 2004-CA-00960-COA
StatusPublished
Cited by1 cases

This text of 915 So. 2d 1117 (Haycraft v. Mid-State Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haycraft v. Mid-State Construction Co., 915 So. 2d 1117, 2005 Miss. App. LEXIS 1000, 2005 WL 3289393 (Mich. Ct. App. 2005).

Opinion

GRIFFIS, J.,

for the Court.

■ ¶ 1. Jeffrey and Donna Haycraft filed an application for arbitration pursuant to Mississippi Code Annotated Section 11-15-105 (Rev.2004). Hinds County Circuit Court Judge Bobby Delaughter denied the application as barred under the three year general statute of limitations and by equitable estoppel. On appeal, the Haycrafts argue that the trial court erred: (1) because the [1119]*1119seven year statute of limitations was applicable, (2) in calculating the commencement of the statute of limitations, and (3) in applying equitable principles to bar their motion to enforce the arbitration order. We find no error and affirm.

FACTS

¶ 2. In 1986, Mid-State Construction Company was the general contractor that built St. Andrew’s Episcopal School in Ridgeland. Mid-State entered into a subcontract with Jericho Roofing Company, which was owned by the Haycrafts,1 to install a copper roof.

¶ 3. According to the construction plans, another subcontractor had to install the roof sub-deck before Jericho could install the roof. Problems arose when Jericho came onto the project to install the copper roof over the sub-deck. Jericho experienced many problems during the actual installation. Mid-State terminated Jericho’s contract, and the roof was eventually installed by another subcontractor.

¶ 4. Shortly thereafter, the legal proceedings began. Mid-State sued Jericho and its bonding company. In January 1994, the Haycrafts filed suit in the Circuit Court of Hinds County against Mid-State, the architect, and the sub-deck subcontractor. Mid-State filed a motion to dismiss the case. According to the record before us,2 the subcontract gave Mid-State the exclusive right to elect arbitration to resolve all claims and disputed. Apparently, Mid-State did not seek arbitration in the lawsuit that it filed, but did choose to exercise its right of arbitration in the lawsuit filed by the Haycrafts.

¶ 5. On August 22, 2001, the Haycrafts filed an application for arbitration. The application attached a copy of Circuit Judge Breland Hilburn’s order, dated August 24, 1994, and asked the court to enter “an order mandating arbitration.”

¶ 6. The Haycrafts claim that “Mid-State never initiated the arbitration it demanded, and the Haycrafts lawsuit against the remaining defendants proceeded to a slow conclusion due to bankruptcy of certain defendants.” ■ The Haycrafts repeatedly describe their application as a “motion to enforce/renew the order requiring arbitration of the Mid-State portion of the dispute.” Mid-State claims that the application was the first communication it had received from the Haycrafts regarding arbitration.

¶ 7. Mid-State filed its objection to the application on December 7, 2001. Judge Hilburn took the application under advisement and did not rule on it prior to leaving office. A hearing was held before Judge Delaughter on July 18, 2003. Judge De-laughter denied the application, and an order was entered. The Haycrafts appeal this order.

STATEMENT OF THE ISSUES

¶ 8. The Haycrafts present the following issues, quoted verbatim:

[1120]*11201. The trial court erroneously relied upon the three-year limitations period of Miss.Code Ann. § 15-1-49 to bar Haycraft’s request to enforce/renew a previous court decree mandating arbitration. The correct statute, Miss.Code Ann. § 15-1-43, provides that a court decree is good and enforceable for seven years and may be renewed. Haycraft’s motion to enforce/renew the prior court order mandating arbitration was timely submitted.
2. Alternatively, the trial court erroneously held that the [Haycrafts’] request to enforce/renew the prior court order was time-barred. The trial court’s error resulted from an improper assessment of when the “cause of action”, accrued. Hay-craft’s “cause of action” did not accrue until Mid-State formally refused to arbitrate in 2001. Hay-craft’s request to enforce arbitration was timely submitted.
3. The trial court erroneously applied applicable principles to dismiss Hay-craft’s request to enforce/renew the previous court order mandating arbitration.

STANDARD OF REVIEW

¶ 9. The question of which statute of limitations to apply is a legal question and, as such, is reviewed de novo. Stephens v. Equitable Life Assurance Soc’y of U.S., 850 So.2d 78, 82(¶ 10) (Miss.2003). Factual findings regarding equitable estoppel are upheld when “supported by credible evidence or reasonable inferences which may be drawn” therefrom. Nicholas v. Nicholas, 841 So.2d 1208, 1213(¶ 15) (Miss.Ct.App.2003) (quoting Knight v. McCain, 531 So.2d 590, 597 (Miss.1988)).

ANALYSIS

I. Which statute of limitations applies to the Haycrafts’ application for arbitration?

¶ 10. The Haycrafts argue that the trial court should have applied the seven year statute of limitations, codified in Section 15-1-43 of the Mississippi Code Annotated (Rev.2003). Mid-State argues that Section 15-1-43 was not applicable. Instead, Mid-State argues that Judge Delaughter was correct to apply the general three year statute of limitations, codified in Section 15-1-49(1) of the Mississippi Code Annotated (Rev.2003).

¶'11. In the original action, Mid-State sought to enforce the arbitration clause of the subcontract. Paragraph 10.16 of the subcontract read:

All claims, disputes and other matters in question arising exclusively between the Subcontractor and Contractor and not involving the Owner ... and not arising out of the interpretation of the Contract ... shall at the option of the Contractor be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining.

Mid-State filed a motion to dismiss or alternatively to stay pending arbitration. By Order, dated August 24, 1994, Judge Hilburn held “that the Plaintiffs claims for relief in this cause which relate to the separate Defendant, Mid-State Construction Company, should be and hereby are dismissed without prejudice to the rights of the parties and said claims shall be submitted to arbitration in accordance with the provisions of Miss.Code Ann. § 11 — 15— 101 et séq.”

¶ 12. The Haycrafts now argue that this “decree ... which mandated arbitration, was nothing more than a decree or judgment within the meaning of Miss.Code [1121]*1121Ann. § 15-1-43.” Section 15-1-43 of the Mississippi Code Annotated provides that:

All actions founded on any judgment or decree rendered by any court of record in this state, shall be brought within seven years next after the rendition of such judgment or decree, and not after, and an execution shall not issue on any judgment or decree after seven years from the date of the judgment or decree.

Hence, the Haycrafts now argue that the August 24, 1994 order of dismissal was a “judgment or decree” that they could execute upon, and they had seven years to execute on it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
915 So. 2d 1117, 2005 Miss. App. LEXIS 1000, 2005 WL 3289393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haycraft-v-mid-state-construction-co-missctapp-2005.