Hawley Down-Draft Furnace Co. v. Southern Chemical & Fertilizing Co.

25 So. 470, 51 La. Ann. 914, 1899 La. LEXIS 498
CourtSupreme Court of Louisiana
DecidedFebruary 6, 1899
DocketNo. 12,915
StatusPublished
Cited by8 cases

This text of 25 So. 470 (Hawley Down-Draft Furnace Co. v. Southern Chemical & Fertilizing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hawley Down-Draft Furnace Co. v. Southern Chemical & Fertilizing Co., 25 So. 470, 51 La. Ann. 914, 1899 La. LEXIS 498 (La. 1899).

Opinion

The opinion of the court was delivered by

Blanchard, J.

Plaintiff company submitted in writing a proposition to defendant company to furnish the latter three Hawley-Down Draft furnaces, and lower portion of fronts for ash doors, for the sum of $2160.00, These furnaces were for horizontal tubular boilers in .use at defendant company’s works in the city of New Orleans.

Certain guarantees as to the work of the furnaces were embodied in .the proposition of the company, as follows:

1. To consume 95% of the smoke, burning any grade of bitumin■ous coal.

2. Will increase the efficiency of the boilers over 35% over their .rated capacity.

3. Burning any bituminous coal will save over 15% in cost of fuel •over ordinary method of making steam, to be compared with smaller size boilers at the Louisiana Electric Light Company.

4. Burning a certain kind of coal (naming it) will evaporate over ••9 lbs. of water per lb. of coal making steam.

5. Burning any bituminous coal will evaporate water into steam as dry as ordinary furnaces.

'It was stipulated that final test was to be made on completion of the work of setting the boilers, making necessary attachments, connections, etc., and that if the furnaces failed to do as guaranteed -plaintiff company were to remove them and replace former setting at ■their expense.

Also that the furnaces were to remain their property until accepted and paid for by the purchaser.

Defendant company accepted the proposition in writing.

The furnaces’ were delivered, fitted to the boilers, all attachments added, all connections adjusted, and everything made ready for the test.

The test came first on the boilers fitted with the Hawley-Down furnaces, and three days later on those with the ordinary furnaces.

By agreement the horizontal tubular boilers with ordinary furnaces at defendant’s works were substituted for similar boilers at the La. Electric Light Company’s works. That is to say, the comparison of [916]*916the results achieved by the boilers with the Hawley-Down, furnaces at defendant company's works was made with results obtained under similar conditions oil boilers with ordinary furnaces in use at defendant's works.

The test in each case was seven hours — from 9 a. m. to '4 p. m.

The result showed that 9.82 pounds of water per pound of coal had been evaporated during the seven hours by the boilers with the Ilawley-Down furnaces, and 10.1G pounds of water per pound of coal by the boilers with the ordinary furnaces.

This was a superior showing for the ordinary furnace over the Ilawley-Down furnace, and defendant' company, thereupon, refused to receive and pay for the furnaces supplied by the plaintiff company, basing its 'action on the failure of the guaranty of the contract.

This suit was the outcome.

It is brought to recover the purchase price of the three furnaces, the substantial averments of the petition being the sale and delivery of the furnaces, the compliance by plaintiff company with its obligations under the contract of sale, and the fulfillment of the guarantees of the contract. Mention is made of the test of the furnaces sold with the ordinary furnace, and it is represented that this test demonstrated, to the satisfaction of experts, the superiority of plaintiff’s furnaces over the other furnaces.

And the further allegation is made that defendant having expressed dissatisfaction with the results of the test, complainant had stood reády to make another test, which defendant company refused to assent to, except upon such onerous and unreasonable conditions with regard to the expense thereof and its imposition upon plaintiff company, that the latter was forced to decline it.

The defense is non-liability of defendant company because of the utter failure of the guaranties of the contract upon the practical application of the test as agreed upon; and it is averred that upon the failure of plaintiffs’ furnaces to render the service contracted to be performed, they, (plaintiffs) requested the privilege of another test, to which defendant company consented, provided the same be made immediately, or within two days thereafter, to which plaintiff agreed, and a day was fixed for the second test, on which day defendant was in readiness and prepared for the test, but plaintiff company declined' to proceed, stating it preferred the test should be postponed, not, however, naming another day for it.

[917]*917It is further represented that nothing more in relation to the matter was heard from plaintiff for some two weeks, when a demand for payment of the price of the furnaces was made, and that, subsequently, to-wit, some twenty days after the first test was concluded, plaintiff company again requested a second test, to which defendant company again assented, provided the expense necessary and incident to the same be borne by plaintiff.

The answer then goes on to describe the situation existing at that time .at defendant company’s works, different from what it was when the first test was made, what would have to be done, what changes effected, in order to prepare for the second test, and avers that the same would have entailed a total expense of two thousand dollars, which, under the circumstances, it was contended, plaintiff company .should bear. The right of defendant to refuse the second test was averred, but its willingness to agree to same if the expense thereof were assumed by plaintiff, was signified.

There was judgment favorable to plaintiff in the court below and defendant company appeals.

The case presents mainly questions of fact. .

We find that this sale has never been completed, that defendant ha.s never accepted the furnaces, and that, under the contract, they remain the property of plaintiff company until accepted and paid for.

On the question as to whether defendant company was justified in refusing to accept them; we find that in the seven hours’ test provided for in the contract, the guaranty of* plaintiff company as to the superior evaporating- qualities of its furnaces failed. That is to say, the third guaranty mentioned in the contract, viz.: "Burning any bituminous coal will save over 15 per cent in cost of fuel, over ordinary method of making steam,” was not fulfilled.

As to the other guaranties of the contract plaintiff affirms their fulfillment, while defendant denies it.

Plaintiff does not claim that the third guaranty, quoted above, was fulfilled, taking the seven hours the test lasted as the gauge. But ■ does claim that it was fulfilled, taking the first three hours of the test as the gauge, at the end of which time, it is contended, the results as to evaporation on the boilers equipped with ordinary furnacés showed • only 7 92-100 pounds of water per pound of coal, whereas for the last four hours it showed 12 2-10. It is insisted, on behalf of plaintiff .company, that this showing as to the last four hours is abnormal, and [918]*918demonstrated that something was wrong in the test. Just what was wrong is not asserted, nor does the evidence show it. There is an intimation that some of the water must have escaped in some other way than by evaporation into steam, but no proof of this appears. On the contrary, the evidence seems to negative the same.

The test provided for by the contract was for seven Hours.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fouchaux v. Board of Com'rs
53 So. 2d 128 (Supreme Court of Louisiana, 1951)
Hemenway, Inc. v. Williamson
173 So. 781 (Louisiana Court of Appeal, 1937)
Chas. A. Kaufman Co. v. Gillman
142 So. 159 (Louisiana Court of Appeal, 1932)
Dugue v. Safety Oil Burners, Inc.
142 So. 161 (Louisiana Court of Appeal, 1932)
A. Baldwin Sales Co. v. Mitchell
142 So. 700 (Supreme Court of Louisiana, 1932)
Stewart v. Mumme
131 So. 683 (Louisiana Court of Appeal, 1930)
Bohanon v. Stewart
4 La. App. 150 (Louisiana Court of Appeal, 1926)
Etchison Drilling Co. v. Flournoy
59 So. 867 (Supreme Court of Louisiana, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
25 So. 470, 51 La. Ann. 914, 1899 La. LEXIS 498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawley-down-draft-furnace-co-v-southern-chemical-fertilizing-co-la-1899.