Hatzel & Buehler, Inc. v. Station Plaza Associates, L.P.

150 B.R. 560, 1993 Bankr. LEXIS 267, 1993 WL 49812
CourtUnited States Bankruptcy Court, D. Delaware
DecidedJanuary 27, 1993
Docket17-12668
StatusPublished
Cited by13 cases

This text of 150 B.R. 560 (Hatzel & Buehler, Inc. v. Station Plaza Associates, L.P.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hatzel & Buehler, Inc. v. Station Plaza Associates, L.P., 150 B.R. 560, 1993 Bankr. LEXIS 267, 1993 WL 49812 (Del. 1993).

Opinion

HELEN S. BALICK, Bankruptcy Judge.

This is the Court’s decision on the Motion of Station Plaza Associates, L.P. (Defendant) to Amend its Counterclaim against Hatzel & Buehler, Inc. (Plaintiff).

Background:

This motion arises from an adversary proceeding involving a breach of contract *561 action brought by former debtor Hatzel & Buehler against Station Plaza. Plaintiff, a subcontractor, agreed to provide electrical work on Station Plaza III (the Trenton, New Jersey construction project subject of this proceeding) under a contract between Hatzel & Buehler and Station Plaza (contract). Plaintiff contends that it experienced great difficulty in obtaining progress payments for completed electrical work on the project as required by the terms of the contract. As a result of this alleged breach by Defendant, Hatzel & Buehler contends it was forced to discontinue work on the project, albeit it had completed substantially all of the work required under the contract.

On October 26, 1987 Hatzel & Buehler filed a petition for reorganization under Chapter 11 of the Bankruptcy Code. On September, 30, 1988 Hatzel & Buehler brought an adversary action against Station Plaza to compel turnover of the remaining funds allegedly due under the contract (approximately $100,000).

Defendant Station Plaza filed its Answer, New Matter, and Counterclaim on January 6, 1989. In the New Matter and Counterclaim, Station Plaza alleged breach of contract on the part of Hatzel & Bueh-ler, contending that Plaintiff failed to complete the electrical work as set forth in the contract. Defendant also disputed Hatzel & Buehler’s allegation that it was forced to discontinue work on the project because of Station Plaza’s refusal to make agreed upon progress payments. According to Defendant, Plaintiff refused, despite repeated demands, to complete its performance. Station Plaza requested that the action be dismissed with prejudice and that damages be awarded in the amount of $50,-000, the alleged cost of completing the electrical work on Station Plaza III.

Hatzel & Buehler emerged from bankruptcy by Confirmation Order dated December 19, 1989. Although Plaintiff filed this adversary proceeding in September 1988, discovery was not commenced until the'Spring of 1991. On November 18, 1992 Station Plaza moved to amend its Counterclaim to seek additional damages for loss of rental income due to the delay in completing Station Plaza III, allegedly resulting from Hatzel & Buehler’s breach. Additionally, Defendant has moved to bifurcate the question of damages from the main trial in order to avoid delaying that procedure.

Discussion:

Hatzel & Buehler objects to Defendant’s motion on several grounds. First, although Plaintiff acknowledges that Defendant’s original counterclaim may be recognized as an informal proof of claim, it makes a passing argument that Station Plaza never filed a formal proof of claim and, therefore, has no claim against Hatzel & Buehler. Second, Plaintiff contends that Fed.R.Civ.P. 13(f) and Fed.R.Bankr.P. 7013 are the proper rules governing counterclaims and preclude the amendment sought by Station Plaza. Finally, Hatzel & Bueh-ler argues that Defendant’s proposed amendment for lost rent is a new claim, the allowance of which would violate the statutory discharge under section 1141 of the Bankruptcy Code and this Court’s Confirmation Order setting a bar date of February 19, 1990 for all remaining claims against Hatzel & Buehler. 11 U.S.C. § 1141(d)(1)(A).

Bankruptcy courts recognize the validity of an informal proof of claim. In re Wilbert Winks Farm, Inc., 114 B.R. 95 (Bankr.E.D.Pa.1990) (and cases cited therein). To be recognized, an informal proof of claim “must be in the form of a pleading filed in the Bankruptcy Court which shows ‘that a demand is made against the estate’ and ‘the creditor’s intention to hold the estate liable.’ ” Id. at 97 (citing Third Circuit precedent). Station Plaza’s original counterclaim meets the foregoing standard in that it was a pleading filed in this Court which set forth a claim for breach of contract against Plaintiff and sought damages from Plaintiff for the alleged breach. Thus, Hatzel & Buehler’s reference to “no claim” is without merit.

As Plaintiff contends, Fed. R.Bankr.P. 7013 (adopting Fed.R.Civ.P. 13(f)) governs counterclaims and provides for omitted counterclaims as follows: *562 “When a pleader fails to set up a counterclaim through oversight, inadvertence, or excusable neglect, or when justice requires, the pleader may by leave of court set up the counterclaim by amendment.” Fed. R.Bankr.P. 7013. Whether the Court will permit that amendment is not governed by Rule 7013, however, but by Rule 7015 which provides that “a party may amend the party’s pleading only by leave of court or by written consent of the adverse party; and leave shall be freely given when justice so requires.” Fed.R.Bankr.P. 7015 (incorporating Fed.R.Civ.P. 15). Permission to amend a claim falls within the sound discretion of the court. United Services Automobile Ass’n v. Foster, 783 F.Supp. 916, 919 (M.D.Pa.1992) (citing Adams v. Gould, Inc., 739 F.2d 858, 864 (3d Cir.1984), cert. denied, 469 U.S. 1122, 105 S.Ct. 806, 83 L.Ed.2d 799 (1985)). Although, as Plaintiff submits, an amendment to a claim filed post bar-date must be scrutinized to assure that it is not an attempt to file a new claim, “amendment is freely allowed where the purpose is to cure a defect in the claim as originally filed, to describe the claim with greater particularity or to plead a new theory of recovery on the facts set forth in the original claim.” In re International Horizons, 751 F.2d 1213 (11th Cir.1985) (emphasis added). “A court will deny leave to amend only if there is undue delay, motivated by bad faith, or prejudicial to opposing party.” Adams, 739 F.2d at 868.

Although considerable time has elapsed since the original complaint and counterclaim were filed, there is evidence that Hatzel & Buehler was at least partially responsible for the delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
150 B.R. 560, 1993 Bankr. LEXIS 267, 1993 WL 49812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hatzel-buehler-inc-v-station-plaza-associates-lp-deb-1993.