Hatfield Township Municipal Authority v. Pennsylvania Public Utility Commission

853 A.2d 1, 2004 Pa. Commw. LEXIS 420
CourtCommonwealth Court of Pennsylvania
DecidedJune 4, 2004
StatusPublished

This text of 853 A.2d 1 (Hatfield Township Municipal Authority v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hatfield Township Municipal Authority v. Pennsylvania Public Utility Commission, 853 A.2d 1, 2004 Pa. Commw. LEXIS 420 (Pa. Ct. App. 2004).

Opinion

OPINION BY Judge SMITH-RIBNER.

The Hatfield Township Municipal Authority (Hatfield) petitions for review of an order of the Pennsylvania Public Utility Commission (PUC) that denied Hatfield’s exceptions to the initial decision of an Administrative Law Judge (ALJ) and dismissed Hatfield’s complaint against the [2]*2PECO Energy Company (PECO). Hatfield states the following questions: whether the PUC’s order resulted in unlawful discrimination by denying Hatfield the same, 8.71% discount rate that the PUC approved for the only other customers for which stranded cost buyouts were calculated; whether the PUC erred by capriciously disregarding irrefutable . evidence; whether substantial evidence existed to support the PUC’s decision; and whether the appropriate remedy is placing Hatfield in the same position it would have been in but for PECO’s actions.

I

In December 1996 the General Assembly adopted the Electricity Generation Customer Choice and Competition Act (Competition Act), 66 Pa.C.S. §§ 2801 — ■ 2812, to introduce competition into the generation aspect of the electric utility business by requiring electric utilities to unbundle generation from their other rates and services. Each electric utility company, now defined as an “electric distribution company” was required to offer open access over its transmission and distribution system to competitive suppliers, and each was required to file a restructuring plan to bring itself into compliance with the Competition Act and with PUC regulations. The legislature recognized that electric utilities undertook long-term investments in generation facilities, which “stranded costs” might not be recoverable in a competitive market.1 Section 2808 of the Competition Act, 66 Pa.C.S. § 2808, provided for a competitive transition charge (CTC) and an intangible transition charge (ITC) (relating to transition bonds issued under a PUC qualified rate order) to customers as means of recovering these costs gradually in monthly payments over an extended transition period.

PECO filed its restructuring plan with the PUC on April 1, 1997, and various parties contested the plan. On April 29, 1998, the parties filed a Joint Petition .for Full Settlement of PECO’s restructuring plan and related appeals, for a qualified rate order and for transfer of generation assets (Restructuring Settlement). The PUC approved the settlement in Application of PECO Energy Company for Approval of its Restructuring Plan Under Section 2806 of the Public Utility Code, et al. (Nos. R-00973953 and P-00971265, final order filed May 14, 1998). Paragraph 25 of the Restructuring Settlement provided:

All Rate HT industrial customers, LILR customers, and Rule 4.6 and EER customers shall have the right to pay all applicable CTC/ITC charges in one lump sum. For customers exercising this option, PECO and the customers will negotiate a mutually acceptable lump sum using the customer’s most recent 12 months of demand and energy usage as billing determinants, unless such demand and energy usage will not be representative of the customer’s likely demand and energy consumption during the CTC/ITC recovery period (in which case representative values will be used), applied to the CTC/ITC charges for the entire CTC/ITC recovery period, discounted using PECO’s after-tax cost of [3]*3capital. Exercise of the rights in this paragraph and paragraph 26 below shall impose no additional burdens on any other customer classes. Prior to agreeing to such lump sum payment, PECO shall submit for Commission approval a proposal for determining how the lump sum payment of CTC/ITC will affect reconciliation. (Emphasis added.)

This CTC/ITC buyout provision was incorporated into PECO’s electric tariff.2

In June 1999 the Philadelphia Suburban Water Company (PSW), a large Rate HT customer, first proposed a buyout of its CTC/ITC obligations. The parties negotiated over a period of eighteen months, and they eventually agreed on a buyout amount that was calculated using 8.71% as the discount rate to determine the lump sum amount. The PSW buyout was filed, and the PUC approved it by an order entered January 11, 2001. In March 2001 Hatfield inquired about a buyout, and in June 2001 PECO informed Hatfield that the appropriate discount rate for its buyout was 3.93%. On December 10, 2001, Hatfield filed a complaint with the PUC alleging that use of the 3.93% discount rate was in conflict with PECO’s tariff and would result in an overcollection of CTC/ ITC obligations. It requested that the PUC order PECO to use 8.71% as the discount rate and to use July 19, 2001 as a hypothetical “effective date” for determining the buyout amount.

ALJ Charles E. Rainey, Jr. received written testimony and conducted a hearing on October 2, 2002. In an initial decision of February 24, 2003, ALJ Rainey dismissed Hatfield’s complaint. The ALJ held that Hatfield as the moving party had the burden of proof, and he found that the 8.71% after-tax cost of capital used as the discount rate in the PSW proceeding was derived from testimony of PECO’s rate of return witness in the restructuring proceeding.3 The ALJ noted that PECO’s after-tax cost of capital reflected in its financial statement filings (Forms 10Q and 10K) with the Securities and Exchange Commission (SEC) for March 2001 was 3.93% and for March 2002 was 4.19%. The ALJ observed that the parties agreed that the case turned upon whether the requirement in Paragraph 25 to discount using PECO’s after-tax cost of capital meant that the 8.71% figure should be used in the calculation of all buyouts, as Hatfield contended, or whether PECO’s present after-tax cost of capital should be used.

Hatfield argued that 8.71% was used by PECO in its restructuring filing as the after-tax cost of capital to determine the present value of the stream of revenue from PECO’s generating plants, a function similar to valuing a stranded-cost discount; that PECO used 8.71% to support CTC rates proposed in an August 1997 Partial Settlement, which was not approved; and that PECO used 8.71% to evaluate Full [4]*4Settlement proposals and the PSW and Amtrak buyout amounts, even though PECO’s actual after-tax cost of capital at the time was lower, namely, 5.94%. PECO responded that the parties deliberately refrained from designating a particular discount rate because they knew that PECO’s after-tax cost of capital could and would change during the stranded-cost recovery period. PECO’s witness Stephen R. Xan-der explained that when the parties agreed to a CTC/ITC buyout discount using PECO’s after-tax cost of capital, they also agreed to numerous settlement provisions that would, when implemented, change that cost of capital, including the issuance of $4 billion in new transition bonds and the transfer of billions of dollars of generating assets and associated capitalization (equity) to an affiliate company. Further, Alan B. Cohn of PECO testified that the PUC and the parties knew that actions PECO could take would lower its cost of capital.

The ALJ was persuaded by the testimony from Xander and Cohn. He concluded that the disputed phrase was meant to refer to PECO’s present after-tax cost of capital, which varies over time, and that evidence indicated that the parties intended buyouts to be calculated using discount rates that reflected PECO’s opportunity cost when the buyout was negotiated. Moreover, the figure 8.71% does not appear in Paragraph 25, making it more likely that after-tax cost of capital referred to present

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Popowsky v. Pennsylvania Public Utility
706 A.2d 1197 (Supreme Court of Pennsylvania, 1997)
Indianapolis Power & Light Co. v. Pennsylvania Public Utility Commission
711 A.2d 1071 (Commonwealth Court of Pennsylvania, 1998)
Leon E. Wintermyer, Inc. v. Workers' Compensation Appeal Board
812 A.2d 478 (Supreme Court of Pennsylvania, 2002)
Aronson v. Pennsylvania Public Utility Commission
740 A.2d 1208 (Commonwealth Court of Pennsylvania, 1999)
Fraternal Order of Police v. Pennsylvania Labor Relations Board
735 A.2d 96 (Supreme Court of Pennsylvania, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
853 A.2d 1, 2004 Pa. Commw. LEXIS 420, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hatfield-township-municipal-authority-v-pennsylvania-public-utility-pacommwct-2004.