Hastings v. IDWR

CourtIdaho Supreme Court
DecidedApril 24, 2024
Docket50273
StatusPublished

This text of Hastings v. IDWR (Hastings v. IDWR) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hastings v. IDWR, (Idaho 2024).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO

Docket No. 50273

JOHN HASTINGS, JR., ) ) Plaintiff-Counterdefendant-Appellant, ) Boise, February 2024 Term ) v. ) Opinion filed: April 24, 2024 ) IDAHO DEPARTMENT OF WATER ) Melanie Gagnepain, Clerk RESOURCES, a political subdivision ) of the STATE OF IDAHO, ) ) Defendant-Counterclaimant-Respondent. )

Appeal from the District Court of the Fourth Judicial District of the State of Idaho, Ada County. Lynn G. Norton, District Judge.

The order of the district court is affirmed.

J. Kahle Becker, Attorney at Law, Boise, for Appellant. J. Kahle Becker argued.

Raúl R. Labrador, Idaho Attorney General, Boise, for Respondent. Meghan M. Carter argued. _______________________________________________

MOELLER, Justice. This appeal arises from litigation between the Idaho Department of Water Resources (the “Department”) and John Hastings, Jr., a landowner in Blaine County who made unauthorized alterations to the Big Wood River. Hastings appeals from the district court’s decision to award summary judgment to the Department on the issue of a statute-of-limitations defense and the partial judgment entered against him. He contends that the Department was barred from pursuing an enforcement action against him based on the statute of limitations set forth in Idaho Code section 42-3809. For the reasons explained below, we affirm the district court. I. FACTUAL AND PROCEDURAL BACKGROUND Hastings owns real property in Ketchum, Idaho, adjacent to the Big Wood River and upstream from the Warm Springs Bridge. During a period of high spring runoff and summer flooding in 2017, Hastings placed rock armoring, or “emergency riprap,” along 193 feet of the streambank to stabilize it. While initially done with verbal approval from the city, the work 1 ultimately removed riparian vegetation and discharged fill material below the mean high-water mark of the Big Wood River without a permit from the Department for altering the channel. On September 11, 2017, the Department issued a notice of violation to Hastings for unauthorized alterations to the Big Wood River. Hastings was ordered to cease all unauthorized work below the mean high-water mark of the river. He was also ordered to submit a streambank bioengineering plan for river restoration, including “measures for replanting the riparian area(s)” with native trees and shrubs “and measures to restore fish and wildlife habitat.” Hastings and the Department met for a compliance conference on October 3, 2017. On January 26, 2018, Hastings and the Department entered into a consent order and agreement (the “Consent Order”) under Idaho Code section 42-1701B. The Consent Order required Hastings to pay a civil penalty and submit a restoration plan for the streambank. The Consent Order laid out the following terms: 1) By February 15, 2018, Respondent shall pay a civil penalty in the amount of $10,000 and submit a Joint Application for Permit (“application”) to the Department that proposes a plan to restore the streambank at the subject lands. The restoration plan must be designed to reduce further erosion and help restore more functional riverine conditions and include the following minimum requirements: a. bioengineering treatments to incorporate large woody material along the streambank (e. g. root wad engineered log jam and brush or tree revetment) b. a planting plan to help re-establish a native riparian buffer between the Big Wood River and the upland parcel at the subject lands. 2) Respondent shall comply with the terms and conditions of any permit the Department issues subsequent to the submittal of an acceptable application and restoration plan pursuant to Order paragraph no. 1. 3) Respondent shall contact the Department immediately after completing the restoration plan at the subject lands. The Department shall inspect the completed work within 14 days after notification of completion to determine if the work meets the criteria and conditions of the restoration plan. 4) The Department agrees to refund Respondent $7,500 of the civil penalty if the Respondent successfully completes the restoration plan by December 31, 2018, and meets the requirements of Order paragraphs 1-3. If there are circumstances beyond the control of Respondent, he will contact the Department by November 30, 2018, to request an extension of the deadline stated above. 5) Upon execution of this agreement, the Department’s receipt of the agreed civil penalty described above, and full compliance with the terms contained herein, NOV no. E2017-1236 will be considered resolved.

2 Hastings paid the $10,000 civil penalty pursuant to the Consent Order. Brockway Engineering, on behalf of Hastings, filed a proposed restoration plan with the Department, which it rejected. Over the next few months, two revised plans were submitted but were each rejected for failing to comply with the terms of the Consent Order. Although not at issue in this appeal, Hastings maintains that all of his proposals were in compliance with the Consent Order. Immediately following the rejection of Brockway Engineering’s revised plans, Hastings contacted Aaron Golart, the Department’s Stream Channel Coordinator, to request an extension of time to complete the restoration required by the Consent Order. Golart granted the extension in an email to Hastings’s attorney on November 2, 2018. Golart’s email stated: “With respect to the time extension you have requested, [the Department] is willing to grant the request to extend the time to complete construction on the restoration until March 15, 2019.” The parties agree that, aside from the extension of the deadline, the terms of the Consent Order were not modified and no new agreement was entered. The parties also agree that this email was a valid extension of the deadline originally set forth in the Consent Order. Brockway Engineering then submitted a third revised plan that addressed the Department’s concerns for the river restoration. Hastings and his corporation, Embassy Auditoriums, Inc., also submitted a joint application to the Department seeking a stream channel alteration permit for streambank stabilization. The Department conditionally approved Hastings’s restoration plan by issuing a “Conditional Permit,” which imposed several conditions related to completion of the restoration work required in the Consent Order. However, Hastings opposed these conditions and filed a petition for a hearing on May 21, 2019, as authorized by the Department’s Administrative Rule 37.03.07.70, which was adopted pursuant to the Idaho Rules of Administrative Procedure (“IDAPA”). Hastings’s petition stated that “[c]ertain requirements [in the Conditional Permit]. . . are inconsistent with the Consent Order and the agreement that led to the filing of the Restoration Plan.” In the same petition, Hastings also stated that he “would be willing to participate in an informal meeting to discuss resolution of this matter” to avoid unnecessary delay or litigation. While a declaration provided by a Department employee indicated that the Department entered “discussions on the conditional terms of the [Conditional] Permit” with Hastings, the Department also noted that the parties eventually “reached an impasse.” The record is silent concerning what, if anything, happened for the next two years, until November 15, 2021, when Hastings filed an action in Ada County District Court seeking a

3 declaratory judgment against the Department. In his complaint, he sought a ruling from the court declaring that the Department could no longer pursue an enforcement action against him. Hastings asserted that the two-year statute of limitations set forth in Idaho Code section 42-3809, the statute authorizing the director of the Department to commence an administrative enforcement action for violation of an order governing the alteration of a stream channel, had run.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. STATE EX REL. KEMPTHORNE
210 P.3d 86 (Idaho Supreme Court, 2009)
Ticor Title Co. v. Stanion
157 P.3d 613 (Idaho Supreme Court, 2007)
Gagnon v. Western Building Maintenance, Inc.
306 P.3d 197 (Idaho Supreme Court, 2013)
Jenkins v. Boise Cascade Corp.
108 P.3d 380 (Idaho Supreme Court, 2005)
Saint Alphonsus Regional Medical Center v. Elmore County
350 P.3d 1025 (Idaho Supreme Court, 2015)
State v. Bryann Kristine Lemmons
354 P.3d 1186 (Idaho Supreme Court, 2015)
Fagen, Inc. v. Lava Beds Wind Park, LLC
364 P.3d 1193 (Idaho Supreme Court, 2016)
Dennis J. Sallaz and Marcy Fox v. Eugene (Roy) Rice
384 P.3d 987 (Idaho Supreme Court, 2016)
Krinitt v. Idaho Department of Fish & Game
398 P.3d 158 (Idaho Supreme Court, 2017)
Estate of Ekic v. GEICO Indem. Co.
422 P.3d 1101 (Idaho Supreme Court, 2018)
Lunneborg v. My Fun Life, Corp.
421 P.3d 187 (Idaho Supreme Court, 2018)
Andrews v. Moore
94 P. 579 (Idaho Supreme Court, 1908)
Bass v. Esslinger
525 P.3d 737 (Idaho Supreme Court, 2023)
Smith v. Excel Fabrication, LLC
535 P.3d 1098 (Idaho Supreme Court, 2023)
Idahoans for Open Primaries v. Labrador
533 P.3d 1262 (Idaho Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Hastings v. IDWR, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hastings-v-idwr-idaho-2024.