Hastings & Avoca R. R. v. Miles
This text of 9 N.W. 336 (Hastings & Avoca R. R. v. Miles) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
—
I. The petition alleges that defendant Miles executed a written contract to convey to plaintiff the right of way over certain lands upon the completion of the grading of the railroad; that the road-bed has been graded and defendant refuses to execute a deed conveying the right of way, and has instituted proceedings to assess his damages, resulting from the appropriation of the land for the use of the right of way of plaintiff’s railroad. The sheriff, who is conducting the proceedings of ad quod darnmnim, is made a defendant, and the petition prays that defendants be restrained from further prosecuting the proceedings, and defendant Miles be required to specifically perform his contract to convey the right of way.
The defendant Miles admitted that he executed the contract set out in the petition, but alleged that it did not when he signed it contain a description of the land owned by him; that it was never by him delivered, and the possession thereof was fraudulently obtained by plaintiff; that the conditions [448]*448upon wliioil it was to bfe delivered had not been performed; that defendant had withdrawn the contract before it had reached plaintiff’s hands on the ground of the non-performance by plaintiff of its terms and conditions, and that of all • these things plaintiff had full notice before the contract was received by them.
The evidence, we think, shows that defendant executed the contract upon the condition that a subscription should be raised to aid the building of the railroad in the sum óf $1,500, which, with the contract and others of like character, plaintiff should accejit as a consideration of the location of the railroad upon a certain line. The plaintiff refused to receive a subscription of $1,500, and demanded that it should amount to $2,000. Thereupon defendant declared to the party holding the contract that he would not assent to the plaintiff’s proposition, and that he would withdraw his proposition and contract to give the right of way. The preponderance of proof establishes that defendant’s contract was executed upon these conditions, which were not complied with.
Plaintiff insists that the contract of defendant was independent of, and had no connection with, the subscription. We think this proposition is not sustained by the‘proof, and moreover, is unreasonable. It is not denied that the contract was executed as a part of the consideration for the location of the railroad. Now, surely, if the contract and others of the same kind, with a subscription of $1,500, was not sufficient to induce the plaintiff to locate the rorxl as required, [449]*449tliis contract alone could not be so regarded. If the contract was independent of the subscription, it of course constituted alone a consideration for the location of the road. This leads to an absurd result, and is in conflict with the drift of all the evidence.
III.* The refusal of plaintiff to accept the contract -and a subscription of $1,500 constituted a non-performance of the condition upon which defendant signed the contract.
IY. The preponderance of the evidence clearly shows that defendant did proclaim to the parties who had the custody of the contract, that he withdrew his assent to its delivery to plaintiff, and that as it was not accepted under the ‘terms upon which it was executed, he would not regard himself as bound by it.
The preponderance of the evidence satisfactorily shows that the parties who held the contract before it came into the hands of plaintiff, one of whom it is claimed was plaintiff’s agent, had notice of defendant’s repudiation of his proposition and the contract. That plaintiff had lull notice thereof, there can be no doubt. It is clearly shown that plaintiff was informed before the contract came into its hands, that defendant claimed he was not to be bound by it and would refuse to perform it, and plaintiff agreed, at the time the contract was delivered to it, to conduct a suit against defendant to recover upon the contract. This was demanded by other parties who became bound to furnish the subsidy to the railroad company.
"We reach the conclusion, which is based upon the evidence, that the conditions upon which plaintiff executed the contract were not performed, and that defendant thereupon withdrew his assent to the delivery of the writing, and proclaimed that he would not be bound thereby. Of all this plaintiff had full notice when the contract came into its hands.
Arjtrmed. •