Hasbrouck v. City of Milwaukee

17 Wis. 266
CourtWisconsin Supreme Court
DecidedJune 15, 1863
StatusPublished
Cited by1 cases

This text of 17 Wis. 266 (Hasbrouck v. City of Milwaukee) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hasbrouck v. City of Milwaukee, 17 Wis. 266 (Wis. 1863).

Opinion

By the Court,

Cole, J.

In disposing of this canse we shall confine our attention mainly to a consideration of two questions which arise in various ways upon the record: First. What effect must be given to the estimates of the city engineer as to any work done or materials furnished by reason of the change or alteration in the plan of the harbor which materially increased the expense of constructing it? Second. Was there suficient evidence in the case to submit the question to the jury, whether, "after the adoption of the government plan, it was agreed and understood between the city authorities and the contractors that thereafter the work should proceed upon a cash basis, and be paid for in cash, or in bonds at their cash or market value instead of their nominal value?1

There are several clauses in the contract which have an important bearing in the solution of the first question. In the first place, the contractor agreed to furnish all materials and construct a harbor at the “straight cut” in the city of Milwaukee, “ in accordance with the plan and specifications made by the city engineer,” which were made a part of the agreement ; was to perform an amount of work on said contract each month equal to one twelfth part of the first three sections; “all of said work to be done in the most perfect and durable manner, and in accordance with said plan and specifications, subject to any alterations which the party of the first part may direct to be made, which shall not materially increase the expense of said work; and if any alterations in the plan of said work shall be made which shall materially increase the expense of constructing said work, if the person or persons appointed by said city to see the said work and direct in relation thereto, cannot agree with the party of the second part as to the value of such extra work, then the same shall be fixed by three disinterested persons, one of said persons to be selected [278]*278by each party, and tbe two so selected to select tbe third, and tbe decision of tbe three, or any two of them, to be conclusive between tbe parties.”

Monthly estimates were to be made by tbe engineer, from time to time as tbe work progressed, of tbe work performed and materials furnished, and the contractor was entitled to receive ninety per cent, of tbe value of such estimates, or thereabouts. And in tbe event there should be an essential change in tbe plan of tbe improvement, as it was provided there might be in tbe above clause of the contract, and arbitrators should be chosen to determine the gross amount of the expense resulting from such change, then in that case, we suppose, it was intended the engineer should make monthly es-" ti mates for a like purpose, namely, to enable the contractor to recover a ratable share of the gross amount while prosecuting the work under the new plan. The contract likewise provided that “ said work shall be done under the survey and directions of the city engineer, acting under the direction and approval of the harbor committee; and if any material alterations are desired by the party of the first part in said work, the same shall be directed in writing, to be signed by the engineer and indorsed by the harbor committee appointed by the party of the first part, and the appraisal of the difference of expense by the appraisers above referred to, shall be made in writing and filed with the clerk of the city ; and if the stone or timber, as specified in said specification, shall fall short of completing said work agreeably to said plan, then the party of the second part is to have extra compensation for the same; and if the materials in said estimate and specifications shall exceed the amount required, the value thereof is to be deducted, the value of such excess or deficiency to be fixed by the city engineer, and to be conclusive between the parties ; and in case there shall be any misunderstanding between the parties in relation to the true construction and meaning of said plan and specifications, or either of them, the same shall be [279]*279submitted to said city engineer for bis instruction and determination, and bis decision shall be conclusive between tbe parties.”

There was a still further clause, which provided that the estimates of said chief engineer shall be conclusive between the parties to this contract, and when the whole contract shall be fully performed by said party of the second part, and the estimates fully made by said engineer, the party of the first part will then pay the balance which shall remain due and unpaid to the party of the second part on the bonds as aforesaid; the above sum of forty-eight thousand and nine hundred dollars being the consideration for the construction of said sections one, two and three.”

After the work had progressed for a time, the city authorities resolved to change and alter the plan and mode of constructing the harbor, by abandoning the plan mentioned in the contract, and adopting in lieu thereof a plan proposed by the government of the United States. The change was a very material and substantial one, and greatly enhanced the cost and expense of constructing the harbor over the one first projected. But still, though the city plan was abandoned, yet the original contract was not wholly lost sight of, and the work progressed under it so far as its stipulations could be made applicable to the new plan. A great deal of additional work was done, and expensive materials were furnished, in consequence of the alteration of the plan, for which the city engineer made estimates. These estimates the circuit court held tobe conclusive between' the parties, and refused to permit the city to prove, on the trial, the actual value of the extra work and materials over and above what was called for by the original contract. And in support of this ruling it is contended, that the contract provides that such estimates shall be conclusive; and the principle is relied on, that when parties agree to rely upon the judgment and skill of an architect or engineer in determining the value of work and materials under contracts of this [280]*280character, then they must abide by tbe estimate of the umpire cbosen, or impeach it upon sufficient legal grounds. There can be no doubt about the correctness of the principle of law invoked ; and the only question is, does the contract provide that the estimates of the city engineer shall be conclusive as to the gross value of the extra work and materials when the plan was so changed as to materially increase the expense of constructing the work ? It appears to us not. Of course, such a construction is to be placed upon this contract as will effectuate the intention of the parties, and give effect, if possible, to every part of it. It will be seen from the clause of the contract first above cited, that if any alteration in the plan of the work was made which should materially increase the expense of constructing it, then, in case of a disagreement between the persons appointed by the city to oversee the work and direct in relation thereto, and the contractor, arbitrators were to be selected to determine the value of the extra work. Now, although arbitrators in fact were never selected, yet indisputably there was a case of disagreement-in regard to the value of extra work done by reason of the material change in the plan. This was the precise case provided for by the contract, when the judgment of arbitrators, and not the estimates of the city engineer, was to determine the value of the work. Upon certain materials embraced within the contract, it was agreed that the estimates of the city engineer should be conclusive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kingsley v. City of Brooklyn
5 Abb. N. Cas. 1 (New York City Court, 1878)

Cite This Page — Counsel Stack

Bluebook (online)
17 Wis. 266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hasbrouck-v-city-of-milwaukee-wis-1863.