Harvey's Inc. v. AC ELECTRIC COMPANY

207 A.2d 660, 1965 D.C. App. LEXIS 164
CourtDistrict of Columbia Court of Appeals
DecidedMarch 11, 1965
Docket3621
StatusPublished
Cited by11 cases

This text of 207 A.2d 660 (Harvey's Inc. v. AC ELECTRIC COMPANY) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harvey's Inc. v. AC ELECTRIC COMPANY, 207 A.2d 660, 1965 D.C. App. LEXIS 164 (D.C. 1965).

Opinion

MYERS, Associate Judge.

In early 1961 the parties entered into a verbal agreement for renovation of the electrical system in appellant’s restaurant. Appellee completed the work on April 21, 1961, and it was approved by the District of Columbia. There is no dispute that the system operated satisfactorily until August 21, 1961, when it failed and appellant was without electricity for several hours during the evening. As a result, appellant allegedly suffered damages of $3,000 due to a loss of income from sales, spoilage of food and loss of reputation, for which it thereafter brought suit. Appellee counterclaimed for $803.95, the amount due for the renovation work. The trial judge found for appellee on both the complaint and the counterclaim. This appeal ensued.

Appellant first contends that the trial judge erred in ruling that the restaurant had failed to prove that appellee had performed the work in an improper, defective and unworkmanlike manner. Although conceding that the doctrine of res ipsa loquitur is not applicable to this case because it involves an alleged breach of contract rather than a tort, appellant argues that a counterpart of this rule should be invoked — that as appellee was in a better position to know the cause of the power failure, it had the burden of proving that the work was properly performed or explaining the reasons for the electrical failure and that the trial judge shoud have applied a fairer standard by inferring, from proof of the power failure, that the work was done in a defective manner. We disagree. It is well settled that one alleging a breach of contract has the burden of proving it. Boomhower, Inc. v. Lavine, 151 F.Supp. 563 (D.D.C.1957). Here appellant was unable to establish what actually caused the failure and it would be sheer speculation to conclude without proof that the cause was something within appellee’s control. We hold the trial judge correctly ruled that appellant had failed to carry its burden.

An agent of appellee testified that shortly after the power failure he told an agent of appellant that the failure was due to a defective breaker. He was later allowed to testify, over appellant’s objection, that he had learned from the manufacturer that it was not defective. Appellant contends that the latter testimony was hearsay and that its admission was error. We agree that the testimony in question is hearsay, but its admission was harmless. Even without the admission of this hearsay rebuttal testimony, there was insufficient uncontroverted proof of defective workmanship to satisfy the burden of proof as to cause.

Appellant also claims it was error to refuse to permit its expert witness to testify whether the system was properly installed. The record discloses that the expert proffered did not inspect the electrical system until about a year and a half after the power failure. The qualifications of an expert witness and the limitations as to his testimony are wholly within the sound discretion of the trial judge. Hitchner Wall Paper Co. v. Pennsylvania R. R., 168 Fed. 602 (3rd Cir. 1909). If it appears that the witness has no personal knowledge of the facts and the questions posed do not disclose them, he could have no reliable opinion on the subj ect and is incompetent to testify thereon. Shapiro v. Pennsylvania R. R., 65 App.D.C. 324, 83 F.2d 581 (1936). *662 Since the expert here was unacquainted with the condition of the system immediately after completion of the work and no facts regarding it were posed in a hypothetical question to him, the trial judge did not abuse 1iis discretion in refusing to allow the expert to testify.

As appellant failed to establish a breach of contract, the judgment in favor of appel-lee upon the counterclaim was correct.

Affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smartnet, Inc. v. Vorv
District of Columbia, 2009
Doe v. Medlantic Health Care Group, Inc.
814 A.2d 939 (District of Columbia Court of Appeals, 2003)
Hummer v. Levin
673 A.2d 631 (District of Columbia Court of Appeals, 1996)
Hughes v. Pender
391 A.2d 259 (District of Columbia Court of Appeals, 1978)
Ohio Valley Construction Co., Inc. v. Dew
354 A.2d 518 (District of Columbia Court of Appeals, 1976)
Logsdon v. Baker
366 F. Supp. 332 (District of Columbia, 1973)
Monacelli v. Monacelli
296 A.2d 445 (District of Columbia Court of Appeals, 1972)
Minor v. United States
294 A.2d 171 (District of Columbia Court of Appeals, 1972)
Waggaman v. Forstmann
217 A.2d 310 (District of Columbia Court of Appeals, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
207 A.2d 660, 1965 D.C. App. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harveys-inc-v-ac-electric-company-dc-1965.