Harvey v. Denver & Rio Grande Railroad

44 Colo. 258
CourtSupreme Court of Colorado
DecidedApril 15, 1908
DocketNo. 5455; No. 3125 C. A.
StatusPublished
Cited by11 cases

This text of 44 Colo. 258 (Harvey v. Denver & Rio Grande Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harvey v. Denver & Rio Grande Railroad, 44 Colo. 258 (Colo. 1908).

Opinion

Mr. Justice Maxwell

delivered the' opinion of the court:

The complaint in this case stated two causes of action.

The first cause of action alleged a balance of $564.04 due plaintiffs from defendant upon a written contract, entered into on the 10th day of September, 1901, for the construction of certain foundations, »abutments, walls and stone work upon and along the line of defendant’s railway.

The second cause of action alleged that between the 20th day of September, 1901, and the 7th day of March, 1902, plaintiffs rendered services and furnished appliances and materials to the defendant, at defendant’s special instance and request, of the reasonable and agreed aggregate value of $3,330.90, setting forth in a bill of particulars, consisting of twenty-four items, the several amounts alleged to be due, aggregating the amount above stated.

It was further alleged that the amount had been due the plaintiffs from the defendant since the 7th day of March, 1902, and that the defendant had wholly failed and refused to pay the same, or any part thereof, although often requested so to do.

The demand was for a judgment for the total of the two amounts, to wit, $3,894.94.

The answer to the first cause of action admitted that on the 10th day of September, 1901, plaintiffs entered into a written coutract with defendant whereby plaintiffs were to perform certain services and’ furnish materials and appliances, and that plaintiffs performed certain services and furnished materials under that contract and became entitled to and were paid a large sum of money therefor, and that plaintiffs, under the terms and conditions of said contract, became entitled to payment in the further sum of [260]*260$564.04, upon condition that plaintiffs would sign and deliver to defendant “a full and valid release and complete discharge of and from any and all claims and demands whatsoever for all matters growing out of or in any way connected with said contract”; and further alleged that it had never refused to pay said sum of money to plaintiffs, but had frequently offered the same upon the signing and delivery of the release and discharge above referred to, and that defendant was now ready and willing to pay the same upon the signing and delivery of'such receipt; and to keep such tender good, that the defendant had deposited in court the- sum of $564.04, payable to the order of plaintiffs upon the signing and delivery of the release and discharge provided for by the terms of the contract.

To the second cause of action the defendant answered, a general denial of each and every allegation thereof, except such as were expressly admitted, and for a second and further defense denied that any agent of defendant company had authority to request or procure the plaintiffs to render the services or furnish the materials referred to; denied that defendant requested or procured the plaintiffs to render such services or furnish sucji materials.; denied that the plaintiffs rendered or furnished the services or materials, and alleged that on the 10th day of September, 1901, plaintiffs and defendant entered, into a written contract for certain Work in the construction of certain bridge abutments, subject to the covenants, conditions and limitations in said contract set forth, a copy of which contract was set forth in haec verba in the answer.

The answer further alleged that all services rendered and appliances and materials furnished defendant by the plaintiffs, as alleged in their second cause of action, if any such were rendered or fur[261]*261nished, were rendered and furnished under and in accordance with the terms, conditions, covenants and agreements of said contract,, and not otherwise, and that, under the terms and conditions of said contract there is due the plaintiffs the amount of money sued for in the first cause of action; that payment of said amount of money was conditional upon the execution and delivery by plaintiffs to defendant of a full and valid release and complete discharge of and from all claims and demands whatsoever growing out of, or in any way connected with, said contract, and that plaintiffs had failed and refused to execute and deliver to defendant such release and discharge.

A reply put in issue the allegations of new matter in the answer.

The trial was to the court and a jury.

Upon the conclusion of all the evidence offered, upon defendant’s motion, the court directed the jury to return a verdict in favor of -the plaintiffs for the sum of $564.04, being the amount sued for in the first cause of action, and admitted to be due by the answer.

The following facts are uncontroverted:

The only written contracts between the parties during the period of time covered by the matters in controversy herein, were the contracts of September 3 and September 10,1901. Previous to the commencement of this suit, the balances due plaintiffs from defendant under these contracts were ascertained and determined by the parties; the balance due under the contract of September 3 does not appear from the evidence, but was included in the sum of $12,-412.57, as shown by the receipt, release and discharge signed by plaintiffs dated April 21, 1902 (defendant’s Exhibit 4 of the record). The balance due under the contract of September 10 was ascertained to be $564.04, as alleged in the complaint and [262]*262admitted by the answer. About March 7, 1902, the plaintiffs presented a claim and made a demand on defendant for some three thousand dollars, for work done near Pueblo and at Fountain. Under date, April 21, 1902, the plaintiffs executed and delivered to defendant a receipt, release, discharge and acquittance for $1,294.60, a voucher and a receipt for the same amount, and a receipt, release, discharge and acquittance for $12,412.57. (Exhibits 1, 2 and 4.)

Plaintiffs objected to the introduction in evidence of these exhibits, upon the ground that they had not been pleaded.

The answer to the second cause of action, hereinbefore outlined, was a general and specific denial of the allegations of the complaint, and a further answer to the effect, that if plaintiffs rendered the services and furnished the materials sued for, the same were rendered and furnished under the contract of September 10; and not otherwise, and that payment of the balance admitted to- be due upon said contract was subject to the condition, that plaintiffs execute and deliver to defendant a full and valid release and complete discharge of all claims and demands whatsoever, “and that said plaintiffs have failed and refused, and still fail and refuse, to execute and deliver to this defendant such release and discharge as aforesaid. ’ ’ .

Under this state of the pleadings defendant contends, that the complaint having alleged non-payment, proof of payment was admissible under the general issue raised by the answer, and authorities are cited in support of this position.

Whatever may be the rule in other jurisdictions, it is settled in this state that payment is an affirmative defense and must be specially pleaded.—Esbensen v. Hover, 3 Col. App. 467; Perot v. Cooper, 17 [263]*263Colo. 80; Thomas v. Carey, 26 Colo. 485; Florence O. & R. Co. v. First Nat. Bank, 38 Colo. 119.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goff v. Boma Investment Co.
181 P.2d 459 (Supreme Court of Colorado, 1947)
Kruger v. Smith
260 P. 97 (Supreme Court of Colorado, 1927)
Index Shale Oil Co. v. Wheeler
255 P. 982 (Supreme Court of Colorado, 1927)
Wallace Plumbing Co. v. Dillon
205 P. 950 (Supreme Court of Colorado, 1922)
Bartholomew v. Emerson-Brantingham Implement Co.
68 Colo. 244 (Supreme Court of Colorado, 1920)
Stanley-Thompson Liquor Co. v. Southern Colorado Mercantile Co.
65 Colo. 587 (Supreme Court of Colorado, 1919)
New York Life Insurance v. MacDonald
62 Colo. 67 (Supreme Court of Colorado, 1916)
Harvey v. Denver & Rio Grande Railroad
56 Colo. 570 (Supreme Court of Colorado, 1914)
Nitro Powder Co. v. Kearns
50 Colo. 1 (Supreme Court of Colorado, 1911)
Welles v. Colorado National Life Assurance Co.
49 Colo. 508 (Supreme Court of Colorado, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
44 Colo. 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harvey-v-denver-rio-grande-railroad-colo-1908.