Harvey Fertilizer & Gas Co. v. Pitt County

568 S.E.2d 923, 153 N.C. App. 81, 2002 N.C. App. LEXIS 1084
CourtCourt of Appeals of North Carolina
DecidedSeptember 17, 2002
DocketCOA01-1330
StatusPublished
Cited by11 cases

This text of 568 S.E.2d 923 (Harvey Fertilizer & Gas Co. v. Pitt County) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harvey Fertilizer & Gas Co. v. Pitt County, 568 S.E.2d 923, 153 N.C. App. 81, 2002 N.C. App. LEXIS 1084 (N.C. Ct. App. 2002).

Opinion

*82 McGEE, Judge.

Harvey Fertilizer and Gas Co. (plaintiff) filed a complaint on 16 May 2001 seeking a declaratory judgment that plaintiff had a vested right to complete its cotton gin project and a permanent injunction enjoining Pitt County and the Pitt County Board of Commissioners (Board of Commissioners) from enforcing a zoning ordinance and moratorium affecting the completion of the project. Plaintiff also requested a temporary restraining order and preliminary injunction. The trial court granted plaintiffs request for a temporary restraining order on 17 May 2001. Intervenor-defendants filed a motion to intervene in this action on 23 May 2001. The trial court held a hearing on both plaintiffs motion for preliminary injunction and intervenor-defendants’ motion to intervene. In an order filed 29 May 2001 the trial court granted plaintiffs motion for preliminary injunction. Two days later the trial court granted intervenor-defendants’ motion to intervene.

A hearing was held on 20 July 2001 on plaintiff’s motion for summary judgment and an order was entered on 3 August 2001 granting plaintiff’s summary judgment motion. The order declared that plaintiff had a vested right to complete its cotton gin project in Pitt County, and therefore Pitt County, its agents, and affiliated governmental units were permanently enjoined from enforcing the amended moratorium and zoning ordinance in a way that would prevent the completion or operation of the cotton gin project. Intervenor-defendants appeal from that order. In a cross-assignment of error, plaintiff appeals from the order granting the intervenor-defendants’ motion to intervene.

Plaintiff, an Eastern North Carolina agribusiness corporation, began searching in January 2001 for a location to build a cotton gin in Pitt County. Plaintiff looked at a site off of Manning Road (Manning site), west of Bethel, North Carolina. The Board of Commissioners enacted a zoning ordinance on 22 January 2001 that would in effect make a cotton gin a non-conforming use at the Manning site upon the effective date of the ordinance, 1 July 2001. The Board of Commissioners enacted a moratorium on 5 February 2001 which prohibited the establishment of certain conditional and special uses from that date until 1 July 2001, the effective date of the January 22 zoning ordinance. However, this moratorium did not specifically list cotton gins as a prohibited use.

■ Despite enactment of the zoning ordinance, plaintiff entered into a contract on 10 February 2001 for the purchase of the Manning site *83 from Frances Carson (Carson) for the amount of $250,167.24, with a closing and payment date in April 2001. Plaintiff alleges in its complaint that two days later, the North Carolina Agricultural Finance Authority entered into an “inducement agreement” with plaintiff for the issuance of $4,500,000.00 in agriculture revenue bonds to finance the cotton gin project.

The first in a series of assurances by Pitt County officials that the cotton gin project would not be hindered by the January 22 zoning ordinance or the February 5 moratorium occurred on 15 February 2001, when a planning technician with the Pitt County Planning Office advised Carson’s surveyor that the February 5 moratorium and the January 22 zoning ordinance would not affect the cotton gin project if plaintiff obtained the necessary building permits by 1 July 2001. Carson shared this information with plaintiff. Plaintiff entered into a contract for construction of a cotton gin with Consolidated Gin Co. on 16 February 2001. The contract price was $2,220,000.00 and plaintiff made a $550,000.00 down payment on the gin. Plaintiff entered into a contract with Crustbuster/Speed King on 22 February 2001 for the construction of a module feeder for the cotton gin project. The contract price was $163,350.00 and plaintiff made a down payment of $40,837.50 on 1 March 2001. Plaintiff alleges in its complaint that the estimated delivery dates for both the cotton gin and the module feeder were in June 2001.

The second instance of assurances by Pitt County officials occurred on 5 March 2001, when plaintiffs president spoke with the Pitt County Director of Planning. The Director of Planning assured plaintiff that the February 5 moratorium and the January 22 zoning ordinance would have no effect on the cotton gin project as long as plaintiff obtained a building permit for the site by 1 July 2001. In response to a request from the Director of Planning, plaintiff sent a letter to the Pitt County Planning Office that same day giving general information about the cotton gin project and a preliminary site plan. Plaintiff purchased three tractors for use at the gin for a price of $51,516.21 on 9 March 2001. Later that month, plaintiff agreed to pay approximately $180,000.00 for the conversion of three other tractors for use at the cotton gin. Plaintiff also made its first application for permits that month, when on 12 March 2001 it completed septic permit applications and paid the $300.00 application fee. Plaintiff received preliminary approval of its septic permit application on 21 March 2001 pending submission of a final site map.

*84 The third instance of assurances by Pitt County officials occurred in late March when plaintiff attended a meeting of the Board of Commissioners to make a presentation on the cotton gin project. At that meeting, the county attorney gave further assurances that plaintiff could proceed with the cotton gin project as long as it obtained the necessary permits by 1 July 2001. Plaintiff alleges that the chairman of the Board of Commissioners made similar statements at this meeting. Opposition to the cotton gin project was voiced at this meeting.

Plaintiff applied for air quality permits from the North Carolina Department of Environment and Natural Resources (DENR) on 4 April 2001 and paid the $50.00 application fee. However, before DENR could issue a permit, a compliance letter was required from the Pitt County Planning Office stating that the cotton gin project was consistent with local regulations. Plaintiff requested on 6 April 2001 that the Pitt County Planning Office send a compliance letter to DENR. Even though plaintiff requested this letter on 6 April 2001, the letter was not sent until 26 April 2001, almost three weeks after the request. A few days after contacting the Pitt County Planning Office, plaintiff delivered its site plan to the North Carolina Environmental Health Division (EHD) for final approval of septic permits.

The Board of Commissioners held a public hearing on 16 April 2001 on whether to specifically add cotton gins to the February 5 moratorium. At this meeting there was also a unanimous vote to notify Governor Mike Easley and the North Carolina Agricultural Finance Authority that the Pitt County Board of Commissioners opposed the construction and development of a cotton gin at the Manning site. These two letters were sent 17 April 2001 and a similar letter was sent to plaintiff on 19 April 2001.

Plaintiff completed its sedimentation and erosion control plan application and submitted it on 22 April 2001 to the Pitt County Planning Office, along with the $9,728.00 application fee. A few days later on 26 April 2001, the Pitt County Planning Office sent the compliance letter required by DENR. DENR issued the required air quality permits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dunhill Holdings
Court of Appeals of North Carolina, 2022
Dunhill Holdings v. Tisha Lindberg
Court of Appeals of North Carolina, 2022
Letendre v. Currituck Cnty.
817 S.E.2d 920 (Court of Appeals of North Carolina, 2018)
David Wichnoski, O.D., P.A. v. Piedmont Fire Prot. Sys.
796 S.E.2d 29 (Court of Appeals of North Carolina, 2016)
Saunders v. ADP TotalSource Fi Xi, Inc.
791 S.E.2d 466 (Court of Appeals of North Carolina, 2016)
Bohannan v. McManaway
705 S.E.2d 1 (Court of Appeals of North Carolina, 2010)
Bailey & Associates, Inc. v. Wilmington Board of Adjustment
689 S.E.2d 576 (Court of Appeals of North Carolina, 2010)
Adoption of D.D.B. v. Lovelis
2005 OK CIV APP 112 (Court of Civil Appeals of Oklahoma, 2005)
Nicholson v. F. Hoffmann-LaRoche, Ltd.
576 S.E.2d 363 (Court of Appeals of North Carolina, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
568 S.E.2d 923, 153 N.C. App. 81, 2002 N.C. App. LEXIS 1084, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harvey-fertilizer-gas-co-v-pitt-county-ncctapp-2002.