Harvard Properties, LLC. v. City of Springfield

262 S.W.3d 278, 2008 Mo. App. LEXIS 1148, 2008 WL 3982682
CourtMissouri Court of Appeals
DecidedAugust 29, 2008
Docket28601
StatusPublished
Cited by4 cases

This text of 262 S.W.3d 278 (Harvard Properties, LLC. v. City of Springfield) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harvard Properties, LLC. v. City of Springfield, 262 S.W.3d 278, 2008 Mo. App. LEXIS 1148, 2008 WL 3982682 (Mo. Ct. App. 2008).

Opinion

JEFFREY W. BATES, Judge.

Harvard Properties, LLC (Harvard) owned four basement apartments which were damaged by two sewer backups that occurred after heavy rainfall in January 2005. In 2006, Harvard filed suit against the City of Springfield (City) and sought to recover damages based upon negligence and inverse condemnation theories of recovery. After a bench trial, the court found in favor of Harvard on its inverse condemnation theory and awarded it $6,870.35 in damages. On appeal, the City contends the trial court erred in finding for Harvard on that theory because the judgment is not supported by substantial evidence. This Court agrees. Consequently, the judgment is reversed. The cause is remanded with directions to enter a judgment for the City.

In this court-tried case, appellate review is governed by Rule 84.13(d). 1 The judgment must be affirmed unless it is not supported by substantial evidence, it is against the weight of the evidence, or it erroneously declares or applies the law. Ewanchuk v. Mitchell, 154 S.W.3d 476, 478 (Mo.App.2005). Substantial evidence is evidence which has probative force and from which the trier of fact could reasonably find the issues in harmony with its decision. See State v. Kimes, 234 S.W.3d 584, 586 (Mo.App.2007); Halford v. Missouri State Highway Patrol, 909 S.W.2d 362, 364 (Mo.App.1995).

As the court noted at the conclusion of the trial, there was little dispute about the facts giving rise to this controversy. The City installed a main trunk line for sewage underneath Patton Alley in Springfield, Missouri. The sewer fine was made of vitrified clay pipe (VCP) and was eight inches in diameter. VCP has not been used by the City since 1976. During periods of heavy rainfall, VCP is more susceptible to infiltration by surface and ground water than the types of pipe currently used. Such infiltration would increase the amount of water flowing through the sewer main. The Patton Alley trunk fine could be accessed through Manhole 109. The sewer main was controlled by gravity and drained south to north. The bottom of the main was 41 inches below street level. To ensure proper drainage, the lowest point in a user’s building or residence should be higher than the bottom of the main.

The City maintained the sewer main, but it was the property owner’s responsibility to install and maintain the lateral lines that connected to the main. In order for a lateral fine to drain properly, it should have a “positive slope” of 1/4 inch of drop per foot of run from the building to the main. A positively sloping lateral fine would typically connect to the sewer main at or above the 3 o’clock position on the right or the nine o’clock position on the left.

*280 Harvard owned Southwinds Apartments, which was an apartment complex located on South Avenue in Springfield, Missouri. This complex was built after the sewer main on Patton Alley had been installed. Building B bordered Patton Alley on the west. This building had four “garden” apartments whose floors were located 36 inches below ground level. These apartments’ plumbing elbows, which were underneath a concrete slab, extended at least 8 more inches below floor level. Therefore, the lateral line running to the City’s sewer main was 44 inches or more below ground level. All of the complex’s sewage traveled through this four-inch lateral line. It was approximately 20 feet long and had a “negative slope” of 1/8 inch of drop per foot of run. Consequently, it was connected at the very bottom of the sewer main and sloped downward back toward the apartments. Because the apartment building had multiple stories, the head pressure from water flowing downward tended to help push sewage through the lateral. However, the negatively sloping lateral line did not drain properly and was prone to sewage backups. In addition, any water flowing through the sewer main would naturally tend to fill the lateral and flow backwards toward Building B.

At some point prior to 1994, there was a manually operated gate valve that Harvard’s maintenance personnel could close whenever an incident occurred that was likely to cause a backup. This valve ceased to function because it could no longer be completely closed, so Harvard removed it from the lateral line. Harvard later dug a pit next to Building B and installed a sump pump in it. The pump was used to remove effluent from the pit and dump it onto the street. That practice ceased once the City became aware of it and told Harvard that it was not lawful to pump raw sewage onto the street.

Between 1994 and 2004, City records showed that Harvard reported four sewage backups at Building B. None of these backups were associated with heavy rainfall. In March 1998, there was a backup due to a stoppage in the main line. In January 1999, there was a backup due to heavy grease in the lateral line. The main line was clear. In April 2003, there was a backup due to a break in the lateral line. The main line was clear. In December 2004, there was another backup due to heavy grease in the line. Building B experienced more sewage backups than any other property serviced on that main sewer trunk line.

Plumber Herbert Reed also had been to Building B quite a few times to unstop blockages in the lateral line for Harvard. In February 2004, Reed was asked to reroute the lateral in an attempt to gain a proper flow. The outgoing pipe from Building B was under a concrete slab, so its elevation could not be changed. To work properly, the lateral line needed a positive drop of about five inches over the length of the line. Reed did not observe any defects in the construction of the sewer main. He rerouted the lateral, but he was unable to obtain a positive slope that would keep water running in the right direction. He installed a backflow valve in the lateral line. Due to the negative slope of the lateral, however, the backflow valve could be held open by solids that were not pushed completely through the valve due to insufficient head pressure. Reed recommended that Harvard install a lift station. This proposed fix would catch raw sewage in a sealed pit that was connected to an ejector pump located above ground. The pump would lift the sewage and force it under pressure into the sewer main. A one-way check valve on the pump would prevent any sewage from backing up. This would work even if the main were infiltrated with rainwater. The City in *281 spector who reviewed Reed’s work was told that the lateral repairs were temporary and would be replaced later by a lift station. Harvard opted not to install the lift station, so Reed filled in the excavation. The work permit remained open, and the City was never asked to conduct a final inspection of the February 2004 repairs.

After a heavy rain on January 5, 2005, sewage backed up into the four garden apartments of Building B. The same thing occurred again after another heavy rain on January 13, 2005. These two occurrences affected only the four garden apartments in Building B. No other buildings along Patton Alley had any sewage backups. The City’s records show that, on each of those dates, there was an elevated flow in the main due to heavy rainfall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drake Development & Construction LLC v. Jacob Holdings, Inc.
366 S.W.3d 41 (Missouri Court of Appeals, 2012)
Grider v. Tingle
325 S.W.3d 437 (Missouri Court of Appeals, 2010)
Rader Family Ltd. Partnership v. City of Columbia
307 S.W.3d 243 (Missouri Court of Appeals, 2010)
Christ v. Metropolitan St. Louis Sewer District
287 S.W.3d 709 (Missouri Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
262 S.W.3d 278, 2008 Mo. App. LEXIS 1148, 2008 WL 3982682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harvard-properties-llc-v-city-of-springfield-moctapp-2008.