Hartwell v. Minneapolis-Moline Power Implement Co.

186 P.2d 228, 117 Colo. 291, 1947 Colo. LEXIS 245
Supreme Court of Colorado·Decided November 3, 1947·No. No. 15,751.·Published

Opinion

Mr. Justice Hays

delivered the opinion of the court.

H. F. Hartwell, plaintiff below, brought suit in the district court in Lincoln county, against Minneapolis-Moline Power Implement Company, a corporation, and M. Meyers, to recover damages alleged to have been sustained by him growing out of his order for two Model G-4 harvesters, and the alleged failure or refusal of defendants to deliver same. The trial court directed a verdict in favor of defendants, and entered judgment accordingly. The plaintiff is here by writ of error seeking reversal of the judgment.

The pertinent facts are: On January 3rd, 1942, Hart-well signed an order for the purchase of two harvesters from the Company through its branch store, to be shipped “via Co. truck” to the plaintiff at Arriba, Colorado, “when available 1942 (or as soon thereafter as the company can do so).” It is also recited in the purchase order, “cash with order $200.00,” and the balance of $3,003.90 to be paid “cash on or before delivery.” On June 2nd, 1942, the company wrote Hartwell: “We can ship one machine for you this month, but the second machine will not be available until in August. This may be too late for the second machine and, if so, we ask that you please advise us to that effect in order that we may reallot it to another territory where the harvest will be later.” On June 3rd, 1942, the plaintiff replied: *293 “August is out of the question for a combine. Wheat is advancing rapidly due to the dry weather and I could well be in harvest in two weeks or possibly three. I was foresighted enough to realize that parts and combines would be hard to get this fall and had full assurance from the Denver Branch that I would get two machines, if that number was shipped to the Denver house. If Denver Branch is shipped only one machine this fall, I’ll be satisfied. If more than one is shipped or sold through this Branch, I’ll expect both my combines. That is the way they were bought and that is the way I expect the Co. to deliver.”

Thereafter about June 20th, 1942, plaintiff purchased one of the company’s harvesters through the Frúhling Motor Company at Flagler, Colorado, and took delivery at that place. At the time of that purchase he was required by the Company to, and did, sign a new or resale order; whereupon plaintiff demanded the two hundred dollars deposit made on the purchase of the two harvesters June 2nd, 1942, above mentioned, be returned to him and applied on the purchase price of said harvester then and there delivered. Plaintiff not only demanded the return of his deposit of two hundred dollars, but refused upon request to sign an order for a second harvester or leave one hundred dollars on deposit therefor or otherwise indicate in writing that he was obligated for the purchase of a second harvester, stating as a reason for such refusal that he “didn’t know whether he would need it [harvester] or not, that it depended upon the crop.”

Counsel for Hartwell state in their brief that the issue is herein narrowed down to: “1. Whether or not the order placed by the plaintiff with the Denver branch of the defendant Company was accepted, irrespective of the language contained in Exhibit J; if there was such an acceptance, whether by conduct, unreasonable delay, correspondence, acceptance and retention of the initial payment, partial performance, then a contract existed *294 between the plaintiff and the defendant Company, and if such existed the defendant Company was responsible to the plaintiff for the breach of that contract, not only for the customary damages but the unusual damages which result therefrom and which were brought to the attention of the defendant Company. 2. Whether or not the defendant Company was responsible for the acts of its agents, the co-defendant, Meyers, in diverting the said machine contrary to the instructions given to the said defendant, Meyers, in view of the fact that the said defendant Company approved and ratified said acts by accepting payment from the defendant, Meyers, at a time when the defendant Company knew the machine had been diverted. 3. Whether or not the defendant, Meyers, was responsible for his intentional acts in interfering with the relationship that existed between the plaintiff and the defendant Company and knowingly diverting the machine from its destination to his own use and profit.”

Assuming, but not deciding, that the purchase order of June 2, 1942, constituted a valid offer to purchase two harvesters from the defendant company, and that said offer was duly and properly accepted in one or all of the various ways mentioned by the plaintiff in error, it is clear that the latter cannot prevail herein, and that the trial court did not err in granting the motion for a directed verdict against him.

Hartwell, by his conduct abandoned, and revoked, the order for two harvesters and thereby terminated and rescinded the alleged contract by the withdrawal of his deposit June 20, 1942, and his refusal to be further obligated for the purchase of a second harvester. In his dealing with the Fruhling Motor Company, the agent of the defendant company, he made it plain that the purchase of the second harvester depended upon the condition of the crop to be harvested. Under the circumstances the alleged contract, assuming its binding force prior to June 20th, 1942, became a nullity on that date *295 and unenforceable by either party thereafter. Valley Dew Co. v. Messner, 50 Colo. 451, 455, 115 Pac. 531. A party to a contract cannot treat it as binding and rescind it at the same time. Chadbourne v. Davis, 9 Colo. 581, 13 Pac. 721.

Free access — add to your briefcase to read the full text and ask questions with AI

Hartwell v. Minneapolis-Moline Power Implement Co., 186 P.2d 228, 117 Colo. 291, 1947 Colo. LEXIS 245 (Colo. 1947).

186 P.2d 228 (Hartwell v. Minneapolis-Moline Power Implement Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First National Bank v. Henning
150 P.2d 790 (Supreme Court of Colorado, 1944)
Tisdel v. Central Savings Bank & Trust Co.
6 P.2d 912 (Supreme Court of Colorado, 1931)
Morath v. Perkins
278 P. 611 (Supreme Court of Colorado, 1929)
Landis v. McGowan
165 P.2d 180 (Supreme Court of Colorado, 1946)
Chadbourne v. Davis
9 Colo. 581 (Supreme Court of Colorado, 1886)
Valley Dew Distilling Co. v. Messner
50 Colo. 451 (Supreme Court of Colorado, 1911)